xxxKULxxx
SENIOR MEMBER
- Joined
- Feb 4, 2013
- Messages
- 4,504
- Reaction score
- 30
- Country
- Location
I remember there was a problem but i saw details now...
This is what Turkey wants from Airbus Military on A400M
This is what Turkey wants from Airbus Military on A400M
C4Defence reached the details of Turkish claims on bargain between Undersecretariat for Defence Industries (SSM) and Airbus Military on A400M airlifter. Airbus Military refrained from making any further declaration as it had previously accused Turkey for locking whole process and called Turkish behaviour “unbearable”.
Last negotiations took part on March 4th and some agreement is reached at the meeting but according to Turkish source Airbus Military’s precondition is erasing the penalty to put the agreement in practice.
Critical pieces must be delivered at once
Turkey claims that it ordered four thousand parts and pieces as spare part or equipment to keek aircraft running. Sixty percent of it is delivered and not all critical parts. An agreement is reached recently so that Airbus Military will provide the critical part within five days in case of need occurs.
One major, 100 minor mismatch
The design and agreement conditions do not fully meet practice according to Turkish side. They have found 1 major and 100 minor mismatch. The major issue is about Propeller Gear Box Cover. It is claimed that the 0.25 micron gap is allowed between the gear box and cover. Two of covers are 0.80 and 0.90. Turkish side claims that this may cause oil leak. According to Turkish claims Airbus Military accepted change of cover but asked erasing penalty debt. Turkish authorities narrated Airbus Military’s position as the company to believe the penalty unjust as it did pay five million Euro in the past.
Pilot’s training is not complete
Turkey claims that pilots have received training on a simulator but it lacked some configuration. Pilots did not actually fly on real plane or lack training. Turkey asks for eight pilots to be trained.
Previous penalty is different from delay penalty
Airbus military asked for revision on conditions and called all countries to meeting. According to the new agreement Turkey will receive first aircraft in Initial Operation Configuration (IOC) and will be converted to Standard Operation Configuration (SOC) later. Turkey had to receive that plane on SOC at first agreement. Turkey considered this gap as a lack of capacity for two years and asked five million Euro from the Company. According to Turkish authorities this penalty is different from delay penalty as this is the penalty for flying aircraft in IOC in state of SOC. Turkish authorities state that the bill increases every day the delivery of aircraft is delayed.
This is what Turkey wants from Airbus Military on A400M
This is what Turkey wants from Airbus Military on A400M
C4Defence reached the details of Turkish claims on bargain between Undersecretariat for Defence Industries (SSM) and Airbus Military on A400M airlifter. Airbus Military refrained from making any further declaration as it had previously accused Turkey for locking whole process and called Turkish behaviour “unbearable”.
Last negotiations took part on March 4th and some agreement is reached at the meeting but according to Turkish source Airbus Military’s precondition is erasing the penalty to put the agreement in practice.
Critical pieces must be delivered at once
Turkey claims that it ordered four thousand parts and pieces as spare part or equipment to keek aircraft running. Sixty percent of it is delivered and not all critical parts. An agreement is reached recently so that Airbus Military will provide the critical part within five days in case of need occurs.
One major, 100 minor mismatch
The design and agreement conditions do not fully meet practice according to Turkish side. They have found 1 major and 100 minor mismatch. The major issue is about Propeller Gear Box Cover. It is claimed that the 0.25 micron gap is allowed between the gear box and cover. Two of covers are 0.80 and 0.90. Turkish side claims that this may cause oil leak. According to Turkish claims Airbus Military accepted change of cover but asked erasing penalty debt. Turkish authorities narrated Airbus Military’s position as the company to believe the penalty unjust as it did pay five million Euro in the past.
Pilot’s training is not complete
Turkey claims that pilots have received training on a simulator but it lacked some configuration. Pilots did not actually fly on real plane or lack training. Turkey asks for eight pilots to be trained.
Previous penalty is different from delay penalty
Airbus military asked for revision on conditions and called all countries to meeting. According to the new agreement Turkey will receive first aircraft in Initial Operation Configuration (IOC) and will be converted to Standard Operation Configuration (SOC) later. Turkey had to receive that plane on SOC at first agreement. Turkey considered this gap as a lack of capacity for two years and asked five million Euro from the Company. According to Turkish authorities this penalty is different from delay penalty as this is the penalty for flying aircraft in IOC in state of SOC. Turkish authorities state that the bill increases every day the delivery of aircraft is delayed.