Ok back to metro.
Vietnam government said "Transport Ministry are guilty" for Hanoi metro delay.
Why is GoV attacking GoV? The reason is part of GoV such as Ministry of Transport has developed warlordism, or declared de facto independence from the higher authorities.
The no longer heed the leaders, which is now controlled by Northern Factions.
They only follow the orders of Southern Faction.
The Southern Factions need to be purged.
Also I urge PDF members to empathized Vietnam more. We are having a difficult situation.
***************************
The Ministry of Transport's mismanagement in allowing piecemeal work has resulted in ballooning costs and prolonged delays, state auditors say.
The ministry (MoT) permitted contractors to make technical designs for each section of Hanoi’s Cat Linh – Ha Dong metro line separately as the line was being constructed, causing piecemeal work, delays, and quality risks, says Deputy State Auditor General Doan Xuan Tien.
The MoT also failed to evaluate all technical aspects of the project, causing planning to be changed multiple times. Furthermore, it conducted land clearance and handovers at a sluggish pace, slowing down the metro line, said Tran Hai Dong, head of the auditing team for the project.
"In the process of setting up the metro project, all phases from getting consensus on architectural plans, approving changes, clearing and handing over land, were delayed by 1-5 months. The delays caused labour and material costs to soar," Dong said.
The State Audit agency also found that investors had not factored in operating costs, which would account for a large proportion of costs once the metro service began operation, in its financial evaluations. This resulted in an incorrect financial appraisal of the project and its costs, he added.
https://e.vnexpress.net/news/busine...anoi-metro-delays-state-auditors-3948738.html