What's new

Suki Kinar Hydropower Project - 884 MW

Construction Updates........

1650492226524.png




1650492266486.png




1650492319266.png
 
.,.,
"China-Pakistan Economic Corridor".
SKHPP is equipped with four Pelton turbine generators with a single unit capacity of 221 MW, with a total installed capacity of 884 MW, a maximum net head of 922m, and an average annual power generation of 3.212 billion kWh.

1652447461700.png



1652447487324.png



1652447446586.png
 
When will electricity generation start?
 
.,.,
The rotor of the first unit at Suki Kinari Hydropower Project was successfully hoisted.
On the morning of 11th June 2022, the rotor of Unit#4 was successfully hoisted, achieving another major milestone at the Project. Total weight of rotor is about 406 tons, which is the heaviest hoisting component in the electromechanical equipment of the entire unit.


1655035612338.png





1655035632589.png





1655035661565.png
 

By Tahir Ali | Gwadar Pro Jun 21, 2022



MANSEHRA, June 21 (Gwadar Pro) - China Gezhouba Group of Companies (CGGC)’s team reached one more milestone on Tuesday with another headrace tunnel section breakthrough with each other at Suki Kinari Hydropower Project (SKHPP), Mansehra.
According to an official of the project, the 4.5-kilometer-long section was the toughest and the most difficult part of the entire headrace tunnel due to high water doorway, high overburden and several fault zones. “However, the hard work and dedication of the Chinese and their Pakistani coworkers made it possible,” he said.
The total length of the headrace tunnel is over 23 kilometers which has already been completed. Currently, the concrete lining is in progress between breakthrough sections of the headrace tunnel. “The work on the concrete lining is going with fast speed,” the official said. Earlier this month, the rotor of the first unit was successfully hoisted at SKHPP.
The 884MW SKHPP is developed under the umbrella of China-Pakistan Economic Corridor (CPEC) at River Kunhar (a tributary of River Jhelum) at Mansehra, Khyber Pakhtunkhwa (KP). CGGC Ltd is the sponsor of the project which is being executed by Suki Kinari Hydro (Pvt) Ltd.
The total investment of the project is $1.96 billion. The project has created more than 4,000 jobs during the construction while more than 70% of the work is completed. Upon completion the project will each year produce 3.2 billion kwh for Pakistan. The project is expected to be completed later this year.
 
.,.,.
Another headrace tunnel sections breakthrough with each other at Suki Kinari Hydropower Project Today dated 21st June 2022.

Almost 4.5km section was one of the difficult section in whole Headrace Tunnel part which have challenging geological conditions due to high water ingress, several fault zones and high over burden.

However, the skilled team comprises of International and National members, made it happen.
Most of the headrace tunnel (23.2km) had already been completed and the concrete lining is in progress between breakthrough sections of Headrace Tunnel.


1655849394082.png




1655849417145.png




1655849440465.png
 
.,..,
On August 11, relocated N15 road & Tunnel within the Suki Kinari Hydropower Project scope has been opened for traffic. The existing N15 highway, will be inundated with the reservoir impounding therefore relocated N15 was constructed at higher elevation.

On August 12, 2022, the last Stator frame has been hoisted successfully and lowered into the unit pit. The total lifting weight was 335 Tons which was accomplished with the help of the tandem operation of Bridge cranes. The Project has four (04) generating units.


1660766119474.png





1660766146542.png
 
.,.
Last breakthrough of the Headrace Tunnel at Suki Kinari Hydropower Project took place on 8th September 2022.

23.2Km long headrace tunnel is being excavated through different access Adits/Tunnels.
More than 3kilometer long tunnel sections (Adit A7- Adit A7a) breakthrough with high-accuracy alignment...

1662641571474.png




1662641594157.png




1662641552733.png
 
,..,.,
Suki Kinari Hydropower Project, a CPEC clean energy project with total capacity of 884MW, achieved another remarkable milestone! Joint efforts by both Chinese & Pakistani staff always make steady progress for the ongoing CPEC project!!!



1662993967932.png




1662993997496.png
 

Latest posts

Back
Top Bottom