What's new

Suki Kinar Hydropower Project - 884 MW

Latest updates...

1663852587273.png




1663852621981.png




1663852566763.png
 
.
Updates....
CPEC’s clean energy project successfully completed another remarkable milestone!..
The combined efforts of Chinese and Pakistani staff have made tremendous progress.

1666455922348.png




1666455939196.png




1666455957616.png
 
.
,.,.
The excavation of deepest Pressure shaft System has been completed successfully at Suki Kinari Hydropower Project.

On October 22, 2022, the breakthrough of upper pressure shafts (PS1&PS2) occurred successfully. The Pressure shaft system consist of 6 pressure shafts and 8 horizontal pressure tunnels and overall depth/elevation difference is almost 740m which break the world record of deepest pressure shaft system of Sinclare Hydropower station in Ecuador. The completion of excavation laid down the solid foundation for steel liner installation which are already in progress at completed sections.


1666530987332.png





1666531036342.png





1666530966710.png
 
. .
.,.,
Federal Minister for Energy to lay foundation stone of 500KV transmission line at Malakandi Paras, 75km.. 500 KV transmission line will add electricity generation to the national grid from 884 MW Suki Kinar Hydropower project.


1668014070785.png
 
.
.,,,.,.
Inauguration Ceremony Ski Kanari Transmission Line.

The 75 kilometer long 500 KV transmission line is being constructed at a cost of Rs 18704 million.
Electricity generation from the 884 megawatt ski edge hydropower project through the transmission line will be added to the national grid.
Ski Kanari hydropower project was launched with a serious sum of $2100 million in 2017 under CPEC.
The project will generate approximately 3.129 billion units of electricity annually.
The project created more than 6000 people employed, the power plant will start producing electricity in November 2024.
Domestic, agricultural and industrial consumers will benefit from the cheap electricity generated by the Ski Kanari Hydro Power Project.
 
. . . .
Construction progress..
The largest Pelton-type turbines (4 x 221MW) in the country are getting in place at Suki Kinari Hydropower Project. ANDRITZ Hydro is the supplier of these monster turbines. It is pertinent to mention here that SKHPP is the highest head project in the country with a gross head of 922.7 m.
The construction activities were started in 2017 and expected completion date of the project is 2024.


326391976_572943141029164_8459753532595832617_n.jpg




326448569_5832440226794370_1197063864757290312_n.jpg
 
. .
.,.,
The largest Pelton-type turbines (4 x 221MW) in the country are getting in place at Suki Kinari Hydropower Project.

326381962_857380482040540_553851063116540087_n.jpg




326509984_1311106289731411_8275121023506732709_n.jpg
 
.
.,.,
The rotor of the 2nd unit at Suki Kinari Hydropower Project was successfully hoisted.

On the morning of 31st Jan 2023, the rotor of Unit#2 was successfully hoisted, achieving another major milestone at the Project. Total weight of rotor is about 406 tons, which is the heaviest hoisting component in the electromechanical equipment of the entire unit.


327944459_1352842042175192_322791375400822578_n.jpg



328454549_5425683630869364_2850686657744711835_n.jpg



328462305_723373802636983_435918156722013233_n.jpg



328536340_564744118885910_5350575012187472440_n.jpg
 
. . .

Latest posts

Country Latest Posts

Back
Top Bottom