What's new

Suki Kinar Hydropower Project - 884 MW

.
Progress....

330396656_490242379807115_8670297518336781277_n.jpg
 
.
.,.,
884MW - Suki Kinari HPP (under construction)

The construction activities are in progress with severe weather conditions. The civil and electro-mechanical works are going on.

The construction activities were started in 2017 and the expected completion date of the project is 2024.


331950388_900483894536354_6267649219485448823_n.jpg



332079377_518421013561688_8328600124142024663_n.jpg



331917656_875723670325651_2820152463344302043_n.jpg
 
. .
.,.,,.
884MW Suki Kinai Hydropower Project - Steel factory
A Straight-of-the-art steel factory has been established at an area of 4200 sq.m within the construction site to produce Steel liner for the Headrace tunnel and Penstock system.
The factory is equipped with hydraulic press, gantry crane, CNC cutting machine, welding cross arm, and other advanced equipment. The factory peak monthly production capacity is over 950 Tons.

 
.
..,.,
Progress Update on 884MW Suki Kinari HPP:
90% construction work completed, water intake facility completed, N15 alternate road along with tunnel completed,
Total investment $2bn...

339899098_1177354266274097_8244638018001730074_n.jpg



340008468_1280743962790606_2207295669018374515_n.jpg




339097346_610884887600564_3144316385513623495_n.jpg
 
.
,..,,.
Under Construction Transmission Line from 884 MW Suki Kinari Hydropower to National grid.
Location ...... Balakot, . KPK.


336378016_149522394720816_7782150722976608063_n.jpg
 
.
,.,,.,.
CPEC Project Updates: The first shaft penstock of the Suki Kinari hydropower station project in Pakistan was successfully installed, laying a solid foundation for the water storage and power generation of the hydropower station. generation capacity of 874 MW.


342812907_176811778637544_2653687449449183473_n.jpg




342481811_632560741563235_6518907974297024346_n.jpg




342440456_923149052239002_7039926151400714115_n.jpg
 
. . .
,.,.,

90 percent work of the Sukki Kinari hydro project completed​

May 2, 2023



As per a media report, the Sukki Kinari hydropower project is nearing completion, with approximately 90% of the work already finished. The project is equipped with four sets of impulse turbines, providing a total gross installed capacity of 873.508-MW. The heavy transmission line installation is currently underway at a rapid pace.

This project is a foreign direct investment venture by Suki Kinari Hydro (Private) Limited, in which White Crystal Limited from Saudi Arabia holds a 58% stake, while Eden Inc. Behad from Malaysia and China Gezhouba Group Company Limited (CGGC) each hold a 20% stake.

ISLAMABAD: Around 90 percent work of the Sukki Kinari hydropower project has been completed while the installation of the heavy transmission line is in progress at a rapid pace.

According to a report published by Gwadar Pro, the total gross installed capacity of Sukki Kinari Project is 873.508-MW with the supply of 4 sets of impulse turbines. SK project is a foreign direct investment project by Suki Kinari Hydro (Private) Limited.

It is a joint venture by White Crystal Limited, Saudi Arabia (58%), Eden Inc. Behad, Malaysia (20%) and China Gezhouba Group Company Limited (CGGC) (20%).

Meanwhile, Chinese engineers have successfully installed a Shaft pan in Sukki Kinari 884 megawatts hydropower project which would provide a base for water preservation and power generation.

The run-of-river facility is one of the early-harvest clean energy projects under the China-Pakistan Economic Corridor (CPEC). Gezhouba Group, China is implementing the project at around USD 2 billion.

The pan shaft has an important role in generating electricity by converting energy from an outflow between the upstream water and downstream water.

The system comprises a vertical shaft, the shaft crown of which forms an inlet level that is essentially parallel to the bottom and which below the water level of the upper water runs, said a statement released here.

Under Construction Suki Kinari Hydropower Project-884MW Shaft 234m deep double chamber surge shaft is being constructed to neutralize the hammering effect of water due to the sudden shutdown of generating units last year.
 
.
.,.,
Suki Kinari Hydropower Project,
It has successfully achieved another remarkable milestone of smooth backfilling completion of asphalt core rockfill dam!


347552867_796000112109856_1731670244356719970_n.jpg




347404654_988621315468026_8842148422351200566_n.jpg
 
. .
.,.,.,
On May 19, the CENTRAL POWER PURCHASING AGENCY (CPPA-G) delegation visited SK Hydropower Project which is invested in and constructed by CEEC, and listened to the report on the overall situation and construction progress of the project.


347229135_932539988028253_4365586729206421284_n.jpg




348419287_975750740100437_2381689814763809911_n.jpg
 
. .

Pakistan Affairs Latest Posts

Back
Top Bottom