Featured Pakistan Navy Type 054AP Frigates - Update, News & Discussion

.
Normally it took about 12 months for a type 054A from launch to commissioning. During this period, the ship would undergo out-fitting and sea trials. Some ships took more than 12 months, some took less than that.

Pakistan's type 054AP has some different equipment compare with Chinese ship. And as the first ship of the class, it may take more than 12 months period since testing and verification of new equipment take more time than those that have been tested numerous time.

Set you time line to September 2021 for take-over by PN crew, and the on-the-job orientation for PN sailors might take a month or two before the ship sails back to Pakistan under adequately trained hands.
Thank you Sir .
Type 054A/P #1's first sea trial is coming very soon.
Thank you sir , so we can expect it in Pakistan in 2021 ??? or we have to wait for 2022 ???
 
. . . .
Update:
Google Earth photo dated February 2021, on the 3rd and 4th 054A/P frigate constructions.