India's Scorpene Subs Delayed
By vivek raghuvanshi, NEW DELHI
Published: 21 Jul 2009 17:50
Technical problems are delaying India's Scorpene submarine program, Defence Minister A. K Antony told Parliament July 20.
"On account of some teething problems, absorption of technology and delays in augmentation of industrial infrastructure and procurement of Mazagon Docks Limited (MDL) purchased materials (MPM), slippage in the delivery schedule is expected. Delay in scheduled delivery of submarines is likely to have an impact on the envisaged submarine force levels," Antony said.
The program got underway in 2005, when India licensed the right to build six Scorpenes for $3.9 billion from France. Construction of the first, second and third submarine began in December 2006, December 2007 and August 2008 respectively. The first sub was to have been delivered in December 2012, with one more each year through 2017, said Antony.
The Navy currently operates 16 submarines, including two Foxtrots due to retire. By 2012, there will be only nine submarines left, said a senior Indian Navy official.
The official noted that China is building several nuclear submarines to add to its sub fleet of roughly 30 modern boats and a few dozen older ones.
India's Scorpene Subs Delayed - Defense News