Admiral Gorshkov delay upsets India.


PIX+-+2+VIKRAMADITYA+PREPARING+TO+LEAVE+HARBOUR+FOR+SEA+TRIALS.jpg




NEW DELHI: India will 'strongly' take up with Russia the delay in delivery of aircraft carrier INS Vikramaditya, the refurbished Admiral Gorshkov, asking it to deploy additional manpower to ensure the large warship's 'refit package' is completed within six-seven months.

Defence minister A K Antony will stress this to his visiting Russian counterpart Anatoly Serdyukov during the 12th meeting of India-Russia Inter-Governmental Commission on Military Technical Cooperation (IRIGC-MTC) here on Thursday, said sources.

The delivery of the already much-delayed Vikramaditya was to take place on December 9, as per the re-revised timeline, but crippling engine-boiler malfunctions during the carrier's recent sea trials have put paid to the plan. It has been a double whammy for the Navy as far as its long-standing ambition to deploy two operational carrier battle groups (CBGs) by 2015 was concerned. First, delivery schedule of the 40,000-tonne indigenous aircraft carrier (IAC) being built at Cochin Shipyard was pushed to 2018.

And now, it's certain the 44,570-tonne Vikramaditya will not be ready for induction anytime before end-2013 at the earliest. So, India will have to soldier on with its solitary carrier, the over 50-year-old 28,000-tonne INS Viraat, for the foreseeable future. This when China has recently commissioned its first aircraft carrier, the 65,000-tonne Liaoning, and the US seeks to 'rebalance' six of its 11 potent CBGs towards Asia-Pacific.

"We will tell the Russians to step up the workforce at the Sevmash shipyard for the refit-repair of Vikramaditya. A leeway of three to four months is provided in the contract after the December delivery date...Beyond that, penalty clauses and liquidity damages could kick in,'' said a source.

India has already paid $2.33 billion for Vikramaditya's refit, instead of the original $974 million earmarked in the January 2004 contract under which the carrier was to be delivered by August, 2008. New Delhi is spending another $2 billion to induct 45 Russian MiG-29K naval fighters to operate from the decks of Vikramaditya and IAC.

During the delegation-level talks on Thursday, India and Russia will also discuss ongoing projects for 272 Sukhoi-30MKI fighters and 1,657 T-90S main-battle tanks. While IAF has so far inducted 160 Sukhois towards getting all 272 by 2018 at a cost of over $12 billion, transfer of technology (ToT) problems continue to plague the T-90S tanks. India had first ordered 310 tanks for Rs 3,625 crore in 2001, then another 347 for Rs 4,900 crore in 2007. But indigenous manufacture of another 1,000 T-90S tanks has been painfully slow, with the Army having just about 710 of the tanks so far. While Russia will remain India's largest defence supplier for many years, Moscow's tendency to delay deliveries and ToT, jack up costs midway and faulty product support has forced New Delhi to increasingly look at countries like Israel and US for military hardware and software.


Admiral Gorshkov delay upsets India - The Times of India
 
.
2015 the earliest。and that's after an additional outlay of 500 million US dollars。
 
.
2015 the earliest。and that's after an additional outlay of 500 million US dollars。

Not if the Russkies want to keep one of their biggest clients, and not if the MoD needs a scandal on their hands, in any case your estimate is speculative and not definitive unless you have reliable proof to back it up.
 
.
2015 the earliest。and that's after an additional outlay of 500 million US dollars。

Comprehension problem ?? Atleast read the article, it clearly states delay is six-seven months, AC will be in Indian ocean in mid-late 2013.

NEW DELHI: India will 'strongly' take up with Russia the delay in delivery of aircraft carrier INS Vikramaditya, the refurbished Admiral Gorshkov, asking it to deploy additional manpower to ensure the large warship's 'refit package' is completed within six-seven months.

"We will tell the Russians to step up the workforce at the Sevmash shipyard for the refit-repair of Vikramaditya. A leeway of three to four months is provided in the contract after the December delivery date...Beyond that, penalty clauses and liquidity damages could kick in,'' said a source.
 
.
deceived by the Russians again !No more honest customers than the Indians
 
. .
deceived by the Russians again !No more honest customers than the Indians

We are overwhelmed by the love and affection, chines members have shown towards us in this hour of vikramaditya delay, there can't be any honest adversaries then the chines.
 
.
I would be miffed if there wasn't a delay.

Delays are the norm in India and Russia.

I am glad atleast you are happy :D
BTW does your user name here describ situation back home ??? Just asking No offence :P
 
.
chufiya banane k dhandey hai yar, dont worry all is fine with our relation with Russia :angel:

this AC is a just a boogeyman to make other payments indirectly (missile seeker payments were made when the India agreed to pay the Hiked price of Vikramiditya, so how do u pay them in white money for the secret things u buy frm them :azn: ???)


and this warning from India is just a hogwash!
 
. . .
Oh lala. All these money spent on importing weapons, better for Scatland to speed construction of basic roads, railways.....toilets for its billion living in slums and in abjecty poverty. Moreover India is spending so much in importing weapons from foreign countries while China spend perhaps the same amount even less but by injecting money in its own economy and creating jobs in China for Chinese people. While India by importing massively its weapons is creating jobs for Russia and US.
 
.
Guys, this is the second or third thread running on the same topic.

Request the Moderator to merge all the three threads.
 
.

Country Latest Posts

Back
Top Bottom