Most of these projects have no funds allocated at this time.
Out of the US$ 47 billion, 36 billion are for energy projects.If you dont have electricity you wont have any industrial parks, if you dont have any industrial parks there is no need to have a road built with fibre optics, rail, electricity gas line.Federal govt. has so far failed to put the relevant electricity into the national grid.Most of these projects below have been ongoing for past 10-15 years with slow progress.
Sindh : Jhimpir and Gharo Wind Power Plant (200 MW)
Guddu Thermal Power (747 MW)
2 Nucleir plants in Karachi (2,200MW )
10 coal power projects in Gadani, 2 coal power projects in Port Qasim, 10 coal power projects in Thar
Punjab:
- Quaide-Azam Solar Plant , US$3 million allocated for Phase II (100MW)
- Chashma Plant (600 MW)
- Taunsa Muzaffargarh Hydropower (135MW)
- Coal based Thermal power plants in Muzaffargarh and Rahimyar khan (4500MW)
AJK:
- Neelum-Jhelum Hydro Power Project ( 969 MW)
- GulPur Hydropower Project (102MW)
KPK:
- Dasu Hydro Power Project 2 stages. (4,320 MW)
- Tarbela-IV Extension Hydro Power Project (1,410 MW)
- Golan Gol Hydro Power Project (106 MW)
GB:
1. Diamir Bhasha Dam (4,500 MW)
I cant the put the exact expenditure for these projects as exact figures not available, there are different figures for many projects and things are not very transparent about the source. The energy produced goes to national grid and NAPRA distributes it to other provinces.
.KPK generates 4,000 MW of electricity, the province kpk requires around 2,500 MW of electricity. However, the federal government is squeezing it out by providing less than 1,500 MW's .NAPRA even denies kp its due tariff which has been unchanged since 90s despite the fact KPK is the largest contributor.
========================================================================================================================================================================================================================
The rest of the US$ 11 billion out of 47 billion
Baluchistan :
- New Gwadar International Airport (NGIA) (CPEC) ECNEC 12.01.2015 22947.650
- Rehabilitation of D.I Khan Mughal Kot 50 km Section N-50 (FERP Phase-II) ECNEC 10.04.2015 (Total Rs. 49,863 M) 4025.846
- Gwadar - Turbat - Hoshab Section (200 km) of Gwadar - Ratodero Road (892 km) M-8, including Khuzdar - Shahdadkot - Ratodero (143 km)-(Gwadar, Turbat, Khuzdar in Balochistan and Kamber, Shahdadkot & Larkana in Sindh) NHC 25.03.1999 23168.660
- Widening & Improvement of N-85, Hoshab-Nag - Basima - Surab Road (459 km) (Khuzdar, Panjgur) ECNEC 06.09.2007 22412.464
- Construction of Eastbay Expressway (CPEC) ECNEC 12.01.2015 14061.790
- Zhob Mughal Kot 81 Km N-50 (NHDSIP, ADB) ECNEC 21.01.2010 (Total Rs. 49,954.78 M)
- Railway (i) PC-II for Feasibility Study to Connect Gwadar with Karachi . (ii) Feasibility Study from Gwadar to Basima and from Basima to Jacobabad via Khuzdar (CPEC) CDWP 29.11.2013
- 132 KV Sub Stations at Deep Sea Port Gwadar (QESCO) (CPEC) CDWP 01.03.2008 909.279
Sindh:
Multan - Sukkur Section (387 km) Credit Financing (90:10) - PK Motorway ECNEC 03.07.2014 259353.000
Punjab :
Multan - Sukkur Section (387 km) Credit Financing (90:10) - PK Motorway ECNEC 03.07.2014 259353.000
ML1 -China Pakistan Economic Corridor (CPEC) Support Project at Ministry of Railways CDWP 06.01.2015 252.000
GB:
- Improvement and Widening of Jaglot - Skardu Road (S-1, 167 km) ECNEC 09.12.2010 22154.037
- Construction of Cross - Border Optical Fiber Cable (OFC) System between China and Pakistan for International connectivity of Voice / Data Traffic (GB) (CPEC) ECNEC 01.12.2010
KPK:
- Land Acquisition / Construction of Western Alignment and other CPEC Projects Un-Approved 60000.000
- Construction of Burhan-Havelian Expressway (E-35) 59.1 Km CDWP 03.07.2014 39494.150
- Thakot to Havelian 120 KM (Construction) (Phase-I) (CPEC) ECNEC 4.12.2014 95410.000
- Railway -Comprehensive Feasibility Study for Upgradation/Rehabilitation of Mainline 1 (ML-I) and New Dry Port at Havelian (Buldhair) District Haripur under ChinaPak Economic Corridor (CPEC) CDWP 25.06.2014 390.000
Source:
http://www.pc.gov.pk/wp-content/uploads/2015/06/PSDP-2015-16-Final.pdf
OK so you need to understand that Nationalist Pashtuns consider this
Havelian expressway to be a
Hazara project not a Pashtun project. Hazara is ALSO a votebank area of PMLN so the concerns pick more girth .With that there is
NO progress on the Pashtun region western alignment which develops the mistrust. PTI actually called the ANP bluff by playing this card so they can get more political mileage in the province as well as raise voice on this federals negligence on western
pashtun area western route.
I personally dont like this ego issue between pashtuns and pahari people but
PMLN should start working on the land acquisition mentioned above and give KPK its due share from NAPRA for the electricity it produces.
This will resolve the issue.This issue isnt really that big but if it lingers on it can cause trouble in future.Ball is in Nawaz's court.