What's new

Type 052D DDG News & Discussions

The US TV show claims that the Type 052D is a ripoff of the Arleigh Burke class.

How can an AESA Aegis being a ripoff of a PESA Aegis?

@Economic superpower @Beast


3098961001e939010382549e73ec54e737d1964b.jpg


8150698b4710b912a6092f5ecbfdfc0393452203.jpg


47ce7b22720e0cf30c4fdf5b0246f21fbf09aa70.png


a517a410b912c8fca289646df4039245d78821b1.png
 
Last edited:
I don't like "The Last Ship" TV show, and I'm glad because of it. At least, I don't have to waste my time for that.
But wait, that TV-show come to China?

Not banned, but that TV Show is about as realistic as the Independence Day 2.

Hopefully they won't feature the Type 055 in the Season 4, they should go after France.
 
Yep, D7 is fully completed right now, and why it cannot be deployed within this year?

According to my statistics model, CX#07 (what you called D7) should be commissionned around Septembre 2017.

The raison behind is simple : Completed doesn't mean tested, tested doesn't mean trained, trained doesn't mean they are ready to accept the boat.

Take an example of Type 052C - 10 months after being launched the propulsion, navigation and communication tests begin and these will last for 8 months.

Once finished those stuff finished they start the first phase of combat systems tests (especially ASW capacities) for 5 months, followed by 6 months of main weapon systems tests.

And from official delivery to commissioning ceremony, you need to count 1 month more.

That's the reason why the boat "seems to be" ready for you but is is "still" not deployed. Too quick is not "科学", as what you guys say, right ?

The next one to be commissionned should be 117 Xining by Novembre this year.