For the better IMO. These net-new projects force sprawl and simply move upper-income groups out of the core. Don't get me wrong. If consumers want it, they should get it. However, I'd much rather see a focus on overhauling core Karachi's infrastructure from top to bottom. Unfortunately, that work requires stern and forward-looking leadership, and a population that can handle the 'stress' of construction, moving cables underground, expanding roads, adding public transit to replace some roads (e.g., old city areas), and so on.Have seen tons of computer rendered projects like this for Karachi over the past 20 years. Very few come to fruition. Mostly the less fantastic types.
Thanks to some new technologies IF employed some of the stress on population can be mitigated. For example, use of TBM and micro TBM can help building underground service lines for cables and revamp severance system with minimum disruption.For the better IMO. These net-new projects force sprawl and simply move upper-income groups out of the core. Don't get me wrong. If consumers want it, they should get it. However, I'd much rather see a focus on overhauling core Karachi's infrastructure from top to bottom. Unfortunately, that work requires stern and forward-looking leadership, and a population that can handle the 'stress' of construction, moving cables underground, expanding roads, adding public transit to replace some roads (e.g., old city areas), and so on.
𝐏𝐑𝐎𝐉𝐄𝐂𝐓 𝐔𝐏𝐃𝐀𝐓𝐄: 𝐊𝐚𝐫𝐚𝐜𝐡𝐢 𝐓𝐫𝐚𝐧𝐬𝐟𝐨𝐫𝐦𝐚𝐭𝐢𝐨𝐧 𝐏𝐥𝐚𝐧 - 𝐑𝐞𝐡𝐚𝐛 𝐨𝐟 𝐃𝐫𝐚𝐢𝐧𝐬
Work continues on rehabilitation of two major drains in Karachi.
𝐆𝐮𝐣𝐣𝐚𝐫 𝐃𝐫𝐚𝐢𝐧 𝐏𝐫𝐨𝐠𝐫𝐞𝐬𝐬
Removal of Solid Waste (550,000 tons) & widening of drain was completed in phase-I. This resulted in smooth flow of rainwater during Monsoon 2021. After Monsoon season, work on balance activities will be started; likely to be completed by end July 2022
View attachment 781827
View attachment 781826
View attachment 781828
𝐌𝐞𝐡𝐦𝐨𝐨𝐝𝐚𝐛𝐚𝐝 𝐃𝐫𝐚𝐢𝐧 𝐏𝐫𝐨𝐠𝐫𝐞𝐬𝐬
Required dredging and excavation was completed well before onset of Monsoon 2021. Construction of RCC wall was also completed in record time while 70,000 tons of solid waste was removed, resulting in smooth flow of water.
Work on laying of sewers, construction of roads and some other activities is in progress. Project has entered in completion stage and InshAllah will be completed by 31 October 2021
© FWO
View attachment 781829
View attachment 781830
View attachment 781833
These areas are pretty much example where no building code / standard is followed , anyone can build 2-3 level houses by cheap construction and no paint on exterior
The water drainage goes thru middle of such neighborhoods