hopefully our local firms will be trained enough to build all local hydro projects
this will be cheaper and will ensure employment of local people
 
.
FWO can now take on smaller projects, hopefully after bhasha dam it can even do full fledge projects not only in pakistan but eslewhere as well
 
.
Mohmand_Dam - The Slope stability works are in progress for the diversion tunnels Inlets. The excavation work for diversion Tunnels are expected to start next at the end of this Months.

The Excavation from Outlet side are already in Progress.


1612831823000.png






1612831849221.png
 
. .
800 MW Mohmand Dam Hydropower Project
Under Construction since September 2019
Gross Storage 1.2 MAF
Annual Energy Production 2,862 GWh
Completion date: May 2025




1616847359720.png






1616847384500.png
 
. . .
Largest Pelton turbines in Pakistan for Suki Kinari Hydropower Project.


1618861480127.png


ANDRITZ supplying these four 225MW Pelton units for this project, which will be the largest Pelton turbines in the country.
Vevey Lab, Switzerland conducted the model acceptance test in 2019. On the very day, 20 globally leading turbine experts from all stakeholders witnessed the model acceptance test.
After uninterrupted tests for nearly 150 hours (six days and nights), all the tested items, including efficiency, vibration, speed, air admission as well as the geometric size, met the Contract requirements and manufacturing is in progress.
 
. .
Damsite of Suki Kinari Hydropower Project -884MW
Preparations are going on for final diversion of River Kunhar through Lower Spillway Bays.



1619464670002.png
 
.
Secondary River Closure Ceremony of 884 MW Suki Kinari Hydel Power Project.


1619805814787.png




1619805835170.png
 
.
Mangla Refurbishment Project is designed to improve the operational efficiency of the power plant and assist the capacity expansion of the main generator.

The project financed by United States Agency for International Development(USAID).

Under the strategy, WAPDA has not only initiated new hydropower projects but has also been rehabilitating and upgrading its existing hydel power stations to maximize the ratio of environment-friendly and low-cost hydel electricity in the National Grid.