Turkish Naval Programs

DWv1ty-WsAAsCu3.jpg


DWv1smSWkAAOT5E.jpg


DWghMX1XUAY-hj7.jpg
 
First welding ceremonial for third U214TN submarine "Muratreis"
DW4cMmuWkAAYURd.jpg
DW4cOJ0WAAAbeux.jpg




Planned commissioning dates:

TCG Pirireis (S-330): 2020
TCG Hizirreis (S-331): 2021
TCG Muratreis (S-332): 2022
TCG Aydinreis (S-333): 2023
TCG Seydi Alireis (S-334): 2024
TCG Selmanreis (S-335): 2025


Credit goes to :NUTUK
 
Red ring must be the 3rd unit where they are welding

Second unit must be the one behind where the modules are welded together we can see the 2nd module in grey

The 1st started in 2015 so must be fabricated and wiring and installation must have started so it can’t be the empty shell in the background photo

By 2021 hopefully they will have 1st commissioned and 6th starting
 