INORDINATE delays and slow progress on infrastructure projects is likely to adversely impact the Sindh Engro Coal mining project, which was kicked off by Prime Minister Nawaz Sharif on January 31.

Originally, coal extraction was to commence by June 2012, whereas the mining project is now to be completed in 2017. Its parameters have also been revised a number of times. In the first phase, the mine was to produce 6.5m tonnes of lignite (sufficient for the 1,200MW power plant planned by company), but it was later reduced to 3.8m tonnes after the power plant’s capacity was revised down to 660MW.

Now, the Sindh Engro Coal Mining Company — a joint venture between the Sindh government and Engro Corporation — will instal the first of two 300MW units of equal capacity in the first phase. Furthermore, the project has not reached financial close yet. A consortium of Chinese and local banks are expected to finance this project, but it requires a sovereign guarantee of $700m, which has only recently been arranged.

The Sindh budget FY15 has allocated over Rs20bn for the energy sector, focusing on development of Thar coal and power generation projects. a sum of Rs13.5bn will be spent during the year on ongoing and planned infrastructure schemes in Tharparkar, which is a pre-requisite for implementing the coal projects. This includes packages of Rs500m for the Thar Development Plan and Rs400m for uplift of Tharparkar district.

None of the important infrastructure projects for Thar coal mining has achieved significant physical progress, despite over Rs50bn spent over the last five years
Meanwhile, the federal budget FY15 incorporates in its development outlay Rs205bn for the underground coal gasification project in Thar and for transmission lines for dispersal of power from the proposed Thar power plants. While one expects that these allocations would help speed up various long-awaited coal mining and power generation projects, past performance belies the hopes, notwithstanding the government’s current policy of pursuing multiple power projects based on imported coal.

The Sindh Engro Coal Mining Company is supposed to mine 22.5m tonnes of coal annually from a block of Thar coalfield, and its subsidiary Thar Power Company would subsequently develop 4,000MW mine-mouth power plants, in two phases. The Sindh government had given a 30-year mining lease to Engro Powergen in October 2009 for Thar Block-II, spread over 95.5 sq km, and having about 2bn tonnes of reserves (proven 0.414bn tonnes, exploitable 1.57bn tonnes).

According to the joint venture agreement, the Sindh government is responsible for providing necessary infrastructure support, including strengthening the existing 360-km road network from Karachi to Islamakot — the nearest town to serve the coalfield — as well as connecting national railways to the mine site, constructing an airport in Islamkot, master planning of Islamkot, and arranging fresh water supply and mining-effluent disposal for Block-II. The estimated cost of these schemes on completion is Rs148bn. However, none of the important projects has achieved significant physical progress as yet, in spite of the over Rs50bn that the provincial government has already spent in the last five years.

Huge funds of Rs 10bn and Rs12bn were allocated for construction of these schemes during 2012-13 and 2013-14 respectively. Yet, the contract for mining-effluent disposal, which was scheduled for completion by June 2014, has not been awarded yet, whereas widening of roads is in progress only in the Tharparkar area.

Likewise, the construction of the airport, for which bids were received in September 2010, is still underway, when it was to be completed in two years. Work on laying down railway connections has not been started by Pakistan Railways. And the National Transmission and Distribution Company has yet to undertake any physical work on constructing the 230-km long 500-kv transmission line.

The removal of massive quantities of overburden (surface material, consisting of stable sand dunes, alluvium and sedimentary rocks), with total thickness/depth of 144-233 metres above the first coal-bed, are currently in progress on the initial mining area of 20 sq km. The phased-out construction of an open cast lignite mine will follow.

Except for some progress (made by the Sindh Engro Coal Mining Company), none of the projects has achieved the defined milestones and has fallen much behind timeline. Sino Sindh Resources were to extract coal by 2015, while the Cougar project was to start physical implementation in 2013-14. Oracle was to construct mines in 2013, enabling coal extraction by 2014, but now the removal of overburden is scheduled in 2015. The pilot power project of 8-10MW using coal gasification technology has not yet been commissioned, resulting in a long delay for a 100MW project that was approved in April 2009.

Published in Dawn, Economic & Business, July 14th, 2014


Summary:

  • Sindh Gov has so far failed to stay on track for associated project like airport, roads etc
  • PKR 50Billion spent by Sindh provincial gov have nothing to show for
  • Engro has made some progress but not as per plan
 
Sindh gov i mean PPP is most incompetent party ever. Don't expect any progress under them.
 
Sindh gov i mean PPP is most incompetent party ever. Don't expect any progress under them.

Exactly. People keep criticizing PMLN and SS for showbazi. But PPP is a complete disappointment. They don't even make an effort to at least look good. PMLN has a history of talking big, but they still manage to complete projects, a good example being motorway. But PPP, nope. Corrupt, inefficient, pathetic people.
 
Thar coal is a mirage. Running after it will not yield anything substantive.
 
PPP and Sindh Govt. is merely focusing to keep Sindh backwards and how they can fill their own pockets with govt money. I mean who are they answerable to for the 50B which they got and did nothing with it. Where is the money spent?
 
Where did the trillions of $'s worth of coal go? Were we facing "typos" since before we were born?

Exactly. People keep criticizing PMLN and SS for showbazi. But PPP is a complete disappointment. They don't even make an effort to at least look good. PMLN has a history of talking big, but they still manage to complete projects, a good example being motorway. But PPP, nope. Corrupt, inefficient, pathetic people.

Moterway is a fancy road. A developing country making a big deal about building basic infrastructure and calling it a project seems childish. Metro bus would be a project. Building power plants, reservoirs and raw material processing stations would be projects.
 
Where did the trillions of $'s worth of coal go? Were we facing "typos" since before we were born?



Moterway is a fancy road. A developing country making a big deal about building basic infrastructure and calling it a project seems childish. Metro bus would be a project. Building power plants, reservoirs and raw material processing stations would be projects.

Fancy road which will cost $8 billion and reduce time travel by several hours.
 
Where did the trillions of $'s worth of coal go? Were we facing "typos" since before we were born?



Moterway is a fancy road. A developing country making a big deal about building basic infrastructure and calling it a project seems childish. Metro bus would be a project. Building power plants, reservoirs and raw material processing stations would be projects.

For a country like Pakistan motorway is a project, a sewage line is a project, clean drinking water supply is a project.
 
For a country like Pakistan motorway is a project, a sewage line is a project, clean drinking water supply is a project.

A project in our Mind brother. In our minds. We make a mountain of an ant hill because we think like ants. However we could learn how to work like them to actually be successful.
 
Moterway is a fancy road.

Yes Pakistani motorways are fancy. Better than most countries with the same income brackets. I am not going to debate the economic benefits here.

A developing country making a big deal about building basic infrastructure and calling it a project seems childish. Metro bus would be a project. Building power plants, reservoirs and raw material processing stations would be projects.

So these "things" shouldn't be called projects? Seems like you just want to criticize something here but can't really figure it out.
 
Yes Pakistani motorways are fancy. Better than most countries with the same income brackets. I am not going to debate the economic benefits here.



So these "things" shouldn't be called projects? Seems like you just want to criticize something here but can't really figure it out.

Criticize would be the wrong word. It would be more like I do not share your over excited and over exaggerating when comparing roads to projects. I have seen roads and motorways in around 15 developing countries and have kept the developed nation "projects" out of this discussion. Building roads and motorways are not called projects. They are basic infrastructure to any developing country.
 
Where did the trillions of $'s worth of coal go? Were we facing "typos" since before we were born?
.

Coal, gold etc like resources are very hard to extract and need huge investment upfront and take several years unlike oil. So it does not matter how much 180 billion ton coal worth is overall.
 
i understand. i felt you had gone through previous articles that said there were trillions of $s worth of coal. it would feel like an inside joke to you. i apologize for that.
 
Criticize would be the wrong word. It would be more like I do not share your over excited and over exaggerating when comparing roads to projects. I have seen roads and motorways in around 15 developing countries and have kept the developed nation "projects" out of this discussion. Building roads and motorways are not called projects. They are basic infrastructure to any developing country.

I guess we a disagreement on the definition of word "project". I don't know why are you so adamant on reserving this word project for most shiny fancy things. This is basic PMP stuff. Maybe you are coming from a different angle that I can't understand.

Anyways, Pakistan may be behind in other infrastructure related things (airports, railways, ports), but roads are not one of them. I have also been around a bit.

My point in earlier post was that, NS delivers. And I am comparing him to PPP, not at EU level.
 
I guess we a disagreement on the definition of word "project". I don't know why are you so adamant on reserving this word project for most shiny fancy things. This is basic PMP stuff. Maybe you are coming from a different angle that I can't understand.

Anyways, Pakistan may be behind in other infrastructure related things (airports, railways, ports), but roads are not one of them. I have also been around a bit.

My point in earlier post was that, NS delivers. And I am comparing him to PPP, not at EU level.

I do agree with you that we are looking at this kind of different. Being a little better than PPP is not something to be proud of. We have a difference of opinion in what needs to be called a project and what needs to be called required basic infrastructure. For me projects are building a 425mw power plant. For me a project would be to boost exports so that our growth rate would be over 3.3%. I would go as far as to say that not killing women protesting would be a project seeing how things violently unfold. He has delivered, but lets keep it real. What has been delivered should also be open for criticism and discussion.
 
Back
Top Bottom