Mohmand Dam Hydropower Project .....800 MW

.
Mohmand_Dam- 800 MW
- Under Construction since Sep, 2019
- Gross Storage: 1.2 MAF
- Annual Energy: 2,862 GWh
- Completion: May 2025



1615158555669.png





1615158578595.png
 
. . .
Mohmand Dam - 800MW
The excavation work from Inlet of Diversion Tunnel no. 1 is expected to start next month.
The Excavation from Outlet side are already in Progress.



1615829411884.png






1615829437176.png
 
. . . . .
Construction work on 800 MW Mohmand Dam swiftly progressing. The project was inaugurated by PM Khan expected year of completion is 2025.

This project will contribute heavily to the economic growth of Pakistan.

• 2 Billion 86 Crore units of electricity will be produced annually
• Peshawar, Nowshera & Charsadda will be protected from flood
• 1,80,000+ Acres will be irrigated










 
. .
WORK CONTINUES ON 9 DIFFERENT SITES, ACCESS TUNNEL COMPLETED

March 27, 2021: Access Tunnel of Mohmand Dam for swift excavation of Diversion Tunnels has been completed, while construction work is in progress simultaneously on 9 different sites of the project.

This was briefed to Pakistan Water and Power Development Authority (WAPDA) Chairman Lt Gen Muzammil Hussain (Retd) during his visit to the project. Mohmand Dam Project Director and General Manager Muhammad Javed Afridi, Security and Land Acquisition & Resettlement Director General Brigadier Imtiaz Hussain, representatives of the consultants and the contractors were also present on the occasion.

The Chairman was briefed that excavation work on main dam, spillway, power intake, diversion tunnels and re-regulation pond is under way in addition to construction work on irrigation tunnel, access roads, project colony and offices. The baily bridge across River Swat is also being constructed for mobilization of construction machinery, workforce and equipment on both banks of the river.

Reviewing construction activities at the project, WAPDA Chairman said that Mohmand Dam, like all other water and hydropower projects, is instrumental for economic stability of Pakistan and social development in the country, Khyber Pakhtunknwa in particular, therefore, timely completion of this project is of paramount importance. He directed the project management to gear up their efforts the purpose.

It is worth mentioning that Mohmand Dam is being constructed on River Swat, upstream of Munda Headworks in Tribal District Mohmand of Khyber Pakhtunkhwa. It is the 5th highest concrete-face-rock-fill Dam (CFRD) in the world. On completion, the dam will store about 1.2-million-acre feet (MAF) of water and help mitigate floods in Peshawar, Charsadda and Naushera.

Besides supplementing 160,000 acres of existing land, about 18,237 acres of new land will also be irrigated.

Mohmand Dam Power House will generate 800 megawatt (MW) hydel electricity, contributing 2.86 billion units of low-cost and environment friendly hydel electricity annually to the National Grid.

In addition, 300 million gallons water per day will also be provided to Peshawar for drinking purpose. Annual benefits of the project have been estimated at Rs. 51.6 billion.

The progress and prosperity of the locals residing in the project area is one of the top most priorities. Hence, a hefty amount of Rs. 4.53 billion will be spent on Confidence Building Measures for socio-economic development in the project area.
 
. . . .