KP Hydro Power Plants

Kurram Tangi Multipurpose Dam project coming along at a staggering pace due to relentless efforts by FWO work force. Once online in 2022 the 19 MW power generation and 41 Kms of irrigation canals capable of irrigating 16400 acres of land under stage 1. On completion of stage 2 (currently in planning) the total combined capacity of the Dam will be an astounding 83 Megawatts bringing much needed prosperity for the populace of newly merged North Waziristan District of KPK.
 
.
Mohmand dam

1601749825635.png




1601749846209.png





1601749866073.png
 
. . .
Low-cost, environment-friendly electricity

WAPDA generated 37 billion units hydel electricity in FY 2020-21


The hydel power stations of Pakistan Water and Power Development Authority (WAPDA) cumulatively generated 37.147 billion units of low-cost & environment-friendly electricity during fiscal year 2020-21, that ended on June 30. The hydel generation by WAPDA is almost equal to that of fiscal year 2019-20 and 3.08 billion units more if compared with the average annual hydel generation during the last 10 years.

According to data of WAPDA hydel power generation in 2020-21, Tarbela Hydel Power Station generated 12.61 billion units, Tarbela 4th Extension 3.42 billion units, Ghazi Barotha 6.89 billion units, Mangla 5.40 billion units, and Neelum-Jhelum Hydel Power Station generated 4.79 billion units. While, rest of the generation i.e. 4.03 billion units - was contributed by other hydel power stations of WAPDA.

It is worth mentioning here that hydel generation is the cheapest electricity, produced in the country. That is why, it plays a pivotal role for development in economic and social sectors by stabilizing the overall power tariff for the consumers.

The impact of hydel electricity on the national economy can be gauged from the fact that generation cost of hydel electricity by WAPDA stand at merely Rs.2.82 per unit, while generation cost from thermal sources remains Rs.13.14 per unit on the average during fiscal year 2020-21.

At present, WAPDA owns and operates 22 hydel power stations, including Neelum Jhelum with cumulative installed generation capacity of 9406 Mega Watt (MW). It is pertinent to mention that WAPDA is vigorously implementing a least-cost energy generation plan to enhance share of hydel electricity in the National Grid.

A number of mega projects are being constructed in hydropower sector scheduled to be completed from 2023 to 2028-29. WAPDA projects will double the installed hydel power generation capacity from 9406 MW to 20591MW


Courtesy:WAPDA



209864329_344907423831748_2367043721710612106_n.jpg


213319378_344907420498415_4538241197359835276_n.jpg
 
.
On 6th July, 2021, another achievement registered at Mohmand Dam. The Excavation faces breakthrough with each other from Diversion Tunnel no.1.

The diversion tunnels are key line of the project to timely divert the river flow and start the main dam construction. It is pertinent to mention here that to expediate the progress, the working from 4 location on twin diversion tunnels are in progress.