KP Govt releases over Rs 8 billion for six hydel power stations

On completion will produce 300 MW




1431775615_Hydel%20Power.jpg




The Khyber Pakhtunkhwa government has released over eight billion rupees for construction of six hydel power stations in different areas of the province.


Official sources told our Peshawar correspondent that these power stations are located in Chitral, Lower Dir, Swat, Mansehra and Shangla districts.


After completion within five years the projects will add about three hundred MW electricity to the national grid.





Source:



Radio Pakistan



Radio Pakistan
 
.
two things

when will they be completed?

will the pmln govt create any trouble in completion of these projects?
 
. .
two things

when will they be completed?

will the pmln govt create any trouble in completion of these projects?

mostly by 2019-2020 and yes swat hydro project and munda dam loans were blocked by federal govt

The government of Khyber-Pakhtunkhwa has approved the construction of 356 micro hydel stations with a power generation capacity of 35 megawatts (MW) with the help of non-government organisations (NGOs) in various parts of the province.

these project will supply power to huge amount of rural population

he provincial government of Khyber Pakhtunkhwa has approved Rs 8.898 billion for construction of some major and other small hydel power stations in various parts of the province under the supervision of the Department of Energy & Power.

The decision was taken in the 6th meeting of the Board of Hydel Development under Khyber Pakhtunkhwa department of Power & Energy held here with Chief Minister Pervez Khattak in the chair at Chief Minister’s Secretariat Peshawar.

Those who attended included Minister Energy & Power Mohammad Atif Khan, Minister Finance Muzaffar Said, Chief Secretary Amjad Ali Khan, Additional Chief Secretary Khalid Pervez, Principal Secretary to Chief Minister Mohammad Ishfaq Khan Secretary Energy & Power Sahibzada Saeed Ahmad, CEO PEDO Bahadar Shah, representatives of the Bank of Khyber, State Bank of Pakistan and other concerned sectors.

The energy sector projects are included the construction of Koto Hydel Power Project in district Dir Lower with power generation capacity of 40.8 MW for which Rs 1.453 billion has been released. It will be completed with estimated cost of 12 billion while its tender bids have been opened last month.

The rest of the projects included Construction of Matiltan Hydro Power Project in Swat district having the capacity of 84 MW for which Rs 1,020.968m have been released. Similarly Rs 757.905 million have been released for construction of Karora HPP in Shangla district, Rs 735.198m for Jabori HPP in district Mansehra, Rs 1,706.810m for Daral Khwar HPP in Swat district and Rs 199.997m for Lawi HPP 69 MW in Chitral district Rs 303.560m have also been released for feasibility studies of small power generation sites Phase-I that will yield total electricity of 2000 MW of up to 15 MW small units while Rs 341.560m released for feasibility studies of raw sites Phase-II wherein small power houses up to 10 MW will be set-up in 12 districts of the province and it would produce a total volume of 1000 MW electricity. The 9th important project is about construction of 356 mini/micro hydel stations for which Rs 2,379.000m have been released. This plan was inaugurated through PTI chairman Imran Khan by laying foundation stone of 56KW Sakhra Lalkahoo micro hydel station in Tehsil Matta Swat on August 7 this year.

The KP government has already decided that under first phase of the energy plan, the provincial government would establish 356 small hydel power stations at village and town levels in remote areas of the province with cost of Rs 12 b whereas Rs 6.70 billion have been allocated for it.

Addressing the participants of the meeting the Chief Minister directed the authorities of the Pakhtunkhwa Energy Development Organisation (PEDO) for the best utilisation of the allocated resources to arrest the prevailing energy crisis, initiating hydropower projects and taking emergency measures for its timely completion. Upcoming projects in KP include Mahandri 13-MW, Tangar 13-MW and Machai-2nd phase of less than 3-MW

The meeting also approved multi audit mechanism for judicious and transparent expenditures of the allocated funds. Pervez Khattak said that expeditious measures would not only help in speedy control over energy shortage in the province, but would also generate maximum economic and employment opportunities to put the people on the track of progress and prosperity.

He said that besides hydel resources, the province is blessed with precious oil, gas, coal and solar resources. He said that maximum exploration of these resources for the development of the province is among the top most priorities of the present PTI-led provincial government and for this purpose, he said, his government is burning mid nights and to achieve the set targets.

KP government to start construction of Rs 8.89 billion worth hydel power stations
 
.
ہوشیار خبردار شھباز شریف کے چھوٹے بیٹے سلمان شھباز کا درد ناک و دلخراش سکینڈل منظر عام پہ آگیا ۔ ان واہیات ناسور سیاستدانوں سے اگر ریاست پاکستان کو بچانا ہے تو سیاست چھین لو ان سے یہ سمجھتے ہیں یہ اے آر وائی پہ پابندی لگائیں گے تو ان کے خلاف ثبوت آنے بند ہو جائیں گے ۔ شئیر کرتے جاو اور آگہی بانٹے جاو


04:47
 
.
So what is the total investment required to generate this 300 mw as 8 billion rupees are not enough to complete 10% of the total capacity... Can we have some more details please?

Thanks
 
.
So what is the total investment required to generate this 300 mw as 8 billion rupees are not enough to complete 10% of the total capacity... Can we have some more details please?

Thanks
This amount released detail has been posted above. I couldn't find cost of each project but it should be at least 120-140billion rupees the cost of 40mw is estimated at 12 billion
 
Last edited:
.
The cost for providing off grid power to large amount of people in northern population through hydro is estimated at 12 billion rupees through 365 micro hydro plants with total capacity of 35mw . 6 billion is released
 
.
So what is the total investment required to generate this 300 mw as 8 billion rupees are not enough to complete 10% of the total capacity... Can we have some more details please?

Thanks

These projects on average cost 330 to 360 Million Rs per MW... So for 300 MW it would cost around 105 Billion Rs.
Koto HPP will take 4 years to construct, Lawi 5 Years, Matiltan 6 Years.. Karora 3.5 years, Jabori 3.5 years...
The construction phase of all these projects have alreadly begun....
 
.