Updates on the Katra – Dharam Section of USBRL Project at J&K,
- twelve nos of Tunnels out of 14 nos have been made through.
- Out of total 28.614 Kms of Tunnels on the route, 22.68 Kms of tunnel excavation has been completed and balance length of 5.93 Kms is being completed.
- At Chenab Bridge, earthwork in excavation in foundation at Bakkal end has been completed and the work at Kauri end is in progress.
- The foundation level has reached at five locations.
- The excavation completed during the year is 4.3 Lac m3.
- The cumulative excavation completed is 7.61 Lac m3 as against 9.15 Lac m3.
- The launching of six numbers of viaduct segments of Chenab Bridge has been completed and
- cumulative fabrication work completed is 915 MT.
- The design and proof checking of main arch of Chenab Bridge has been completed.
- Financial Progress achieved during the last Financial Year 2014-15 is ` 329.26 Crs and cumulative financial progress is ` 2519 Crs upto July 2015. Update credit-Skyscrapercity and Konkan railway Corp. Site
AFCONS video on Chenab bridge
Jammu-Udhampur Highway
- twelve nos of Tunnels out of 14 nos have been made through.
- Out of total 28.614 Kms of Tunnels on the route, 22.68 Kms of tunnel excavation has been completed and balance length of 5.93 Kms is being completed.
- At Chenab Bridge, earthwork in excavation in foundation at Bakkal end has been completed and the work at Kauri end is in progress.
- The foundation level has reached at five locations.
- The excavation completed during the year is 4.3 Lac m3.
- The cumulative excavation completed is 7.61 Lac m3 as against 9.15 Lac m3.
- The launching of six numbers of viaduct segments of Chenab Bridge has been completed and
- cumulative fabrication work completed is 915 MT.
- The design and proof checking of main arch of Chenab Bridge has been completed.
- Financial Progress achieved during the last Financial Year 2014-15 is ` 329.26 Crs and cumulative financial progress is ` 2519 Crs upto July 2015. Update credit-Skyscrapercity and Konkan railway Corp. Site