Frontier Works Organization ( FWO ) ..

Following the massive number of landslides on KKH two days back,
FWO is on the job day and night, trying to clear the road for commuters to and from GB.





















 
M-16 Swat Motorway

It is, with a two lane diversion road in between, from approximately after the plai interchange till the last tunnel. It was covered and discussed extensively here. Phase 2 only got land acquisition funds released recently.

The motorway was originally supposed to be built using usual blasting of the mountain faces till the tunnels. But surveys were found to be flawed and the mountain faces too steep and high to be feasible for blasting. They did cut a lot, but soon land sliding and other issues became too frequent so designs were revised and thus the diversion got constructed. Yes, its a new road regardless and scales the mountains from the opposite side.

The new designs and agreements included two more tunneled passages and a couple of high bridges which effectively delayed the project substantially, not to mention FWO had to pay for those from its own resources. So now the project has six total tunnels which are now structurally complete as seen in the videos.

But recently, the designs were revised when landsliding became an issue yet again so now they will be adding open tunnels, further delaying phase-I.
 
Frontier Works Organization (FWO) has been advertised 43 posts for Diamer Basha Dam. Applications are invited from Pakistani Nationals.
- Interested candidates can apply online at fwo.com.pk
- All vacancies are located at Diamer Basha Dam site, Chilas
- Attractive Salary package will be offered to successful Candidates.
- FWO may reject, refuse, omit, postponed, cancel or make changes to the whole or part of any material advertisement or plan regarding this advertisement.
- No TA/DA will be admissible for test/interview


https://careers.fwo.com.pk/
 
1600650915017.png
 
Ground 𝗯𝗿𝗲𝗮𝗸𝗶𝗻𝗴 𝗖𝗲𝗿𝗲𝗺𝗼𝗻𝘆 𝗼𝗳 𝗧𝘂𝗻𝗻𝗲𝗹𝗶𝗻𝗴 𝗜𝗻𝘀𝘁𝗶𝘁𝘂𝘁𝗲 𝗼𝗳 𝗣𝗮𝗸𝗶𝘀𝘁𝗮𝗻

Chairman Pakistan Engineering Council (PEC) Mr Jawed Salim carried out groundbreaking of national level Tunneling Institute of Pakistan, conceptualised by FWO at Islamabad.

This institute is contemplated to serve as a foundation in the fields of tunneling, aerial surveying and Building Information Modeling in the country. The building is likely to be completed by June 2021.




1611001727677.png





1611001752610.png
 
FWO built the first-ever Isolation Hospital and Infections Treatment Centre in Islamabad


With the ground breaking of much needed hospital on 26 March 20, FWO immediately mobalized all the resources with sheer motivation to construct the Isolation Hospital and Infection Treatment Centre (IHITC). It was a time when on one hand, the world had halted entire import and export under fear of pandemic growth while on the other hand, intra - country lockdown had restricted movement and transportation to the critical extent.

The 250 bedded state of the art hospital having prefabricated steel structure building equipped with all sophisticated allied facilities has been constructed by FWO in just 40 days with sole use of internal resources. The sullen spells of torrential rains during limited construction period added further difficulty for the construction teams but couldn’t affect professionalism and morale of FWO engineers and workers. It is worth mentioning that the entire work was executed ensuring best health safety measures described by the Government as anti COVID-19 SOPs.

FWO made frequent visits to the site to inspect, guide and motivate FWO teams working round the clock for this national cause. To monitor live performance, FWO installed live monitoring cameras to monitor the work site.

We acknowledge the efforts and pay special gratitude to all our under mentioned partners including consultants and contractors who stood by us and worked round-the-clock with FWO to accomplish this gigantic project within stipulated time.



1633697720933.png





1633697749605.png





1633697894462.png




1633697932219.png
 
𝐇𝐚𝐧𝐳𝐞𝐥 𝐇𝐲𝐝𝐫𝐨𝐩𝐨𝐰𝐞𝐫 𝐏𝐫𝐨𝐣𝐞𝐜𝐭 (𝐇𝐏𝐏) 20 MW, 𝐆𝐢𝐥𝐠𝐢𝐭 𝐁𝐚𝐥𝐭𝐢𝐬𝐭𝐚𝐧


1633698873754.png
 
𝐇𝐞𝐯𝐞𝐥𝐥𝐢𝐚𝐧 𝐃𝐡𝐚𝐦𝐭𝐨𝐮𝐫 𝐑𝐨𝐚𝐝 (𝐇𝐃𝐑), Hazara..


1633699384598.png




1633699211807.png





1633699288460.png




1633699312230.png
 
𝐂𝐨𝐧𝐬𝐭𝐫𝐮𝐜𝐭𝐢𝐨𝐧 𝐨𝐟 𝐒𝐡𝐞𝐢𝐤𝐡 𝐊𝐡𝐚𝐥𝐢𝐟𝐚 𝐁𝐢𝐧 𝐙𝐚𝐲𝐞𝐝 𝐀𝐥 𝐍𝐚𝐡𝐲𝐚𝐧 𝐁𝐫𝐢𝐝𝐠𝐞 (𝐨𝐥𝐝 𝐆𝐚𝐦𝐦𝐨𝐧 𝐁𝐫𝐢𝐝𝐠𝐞) 𝐒𝐰𝐚𝐭, KPK


1633706007623.png
 
1633786022602.png



𝙄𝙣𝙖𝙪𝙜𝙪𝙧𝙖𝙩𝙞𝙤𝙣 𝙤𝙛 𝙏𝙤𝙧𝙠𝙝𝙖𝙢 - 𝙅𝙖𝙡𝙖𝙡𝙖𝙗𝙖𝙙 𝙍𝙤𝙖𝙙 𝙋𝙧𝙤𝙟𝙚𝙘𝙩 𝘼𝙛𝙜𝙝𝙖𝙣𝙞𝙨𝙩𝙖𝙣
13 September 2006
 
Jagran-II Hydropower Project (JHPP-II)

It is the second time in a year that two tunnels met deep inside the mountain with a tolerance of less than 2.5 centimetres. Previously, it was done on 27 Jan 2021 when two tunnels inside the mountain with a tolerance of less than 10 centimetres.

FWO has excavated 3833 metres of main Headrace Tunnel without even a single casualty in just 485 working days. So far, FWO has excavated 4.7 kilometres long tunnels at this project.

Credits: FWO