Swat Motorway Phase-II
The Khyber Pakhtunkhwa (KP) Chief Minister Mahmood Khan will lay the foundation stone of Swat Motorway Phase-II next week.
The Chief Minister also directed the concerned quarters to expedite progress on Dir Motorway project’s PC 1 for acquisition of land so that physical work on the project could be initiated. He was chairing the meeting of the Pakhtunkhwa Highways Authority to review progress on different road projects including Swat Motorway Phase II and Dir Motorway.
Briefing the meeting about progress on Swat Motorway Phase II, it was informed that 88 km long motorway from Chakdara to Fatehpur would be constructed at a cost of Rs58 billion adding that concessionaire agreement had been signed for the execution of the project.
It was informed that Rs6.7 billion has been released for the acquisition of land for the project. Moreover, section four had been imposed for land acquisition
.-.-.-.-