CPEC Power Projects of Over 13,000MW to be Completed Soon
CPEC-coal-project.jpg



A meeting of the Parliamentary Committee on China-Pakistan Economic Corridor (CPEC) was held under the Chairmanship of Sher Ali Arbab, MNA.

Secretary Power Division briefed the Committee on the power projects under CPEC. He explained that under the CPEC framework agreement signed by China and Pakistan, there were 14 power generation projects which were categorized as prioritized projects with 10414 MW generation capacity and 7 projects were categorized as Activity Promoted with the power generation capacity of 6645 MW.



Currently, there are 20 power projects of 13048 MW at different stages of implementation. Out of which 9 projects are commissioned with a capacity of 5320 MW. While 6 projects are under construction with a generation capacity of 4484 MW. Five projects are under LOI/LOS stage with a capacity of 3244 MW.

Matiari-Lahore HVDC transmission line of 878 KM long with 4000 MW capacity is under construction which is the first transmission line in the private sector in Pakistan. In the current CPEC portfolio, there are nine coal-based power projects of 8220 MW.



Out of which 4 are imported coal-based projects of 4260 MW whereas 5 are Thar Coal based projects of 3690 MW. Four CPEC power projects based on coal have been commissioned.

There is a 36 month completion period for coal-based power projects as per international standards. The Committee appreciated the hard work of the concerned authorities for commissioning of the energy projects in minimum record time.

Provincial Secretaries of Energy from Sindh and Punjab were directed to submit their energy issues to the Committee for further consideration and redressal by the concerned departments. The Chairman directed Power Division that monthly progress reports of under-construction energy projects may be furnished to the Committee regularly.

Secretary Railways also briefed the Committee on ML-1 project. He explained that CDWP has recommended PC-1 of USD 7.2 Billion project to ECNEC which will be considered in its forthcoming meeting. Financing Committees have been constituted from Pakistan as well as China. Five exhaustive meetings have been held on this project. It was a huge investment in the history of Pakistan Railways. There is a complete business model to modernize the Railways as a corporate self-sustaining entity. The important feature of this project is that it will retire the loan itself. Railways is in search of top of a line consultant. TORs have been finalized after a well-thought exercise.

The Chairman recommended the Railways that this is the last chance for recovery of the Railways. A governance model should be introduced where the regulator has the freedom of oversight. Profitability and safety standards are maintained as a reciprocal factor.

The meeting was attended by Noor Alam Khan, MNA, Sadaqat Ali Khan Abbasi, MNA, Umar Aslam Khan, MNA, Ahsan Iqbal Chaudhary, MNA, Sardar Ayaz Sadiq, MNA, Murtaza Javed Abbasi, MNA, Mehnaz Akber Aziz, MNA, Senator Mir Kabir Ahmed Muhammad Shahi and Senator Dr. Shehzad Waseem.
 
. . . .
Because Nawaz Signed These Agreements Not Army or IK

signed with the army's blessing? of course not completely rule out that thought. What about All-weather brother who offered those horrendous terms.

cpec good news = army takes credit
cpec bad news = blame blame blame the previous government.

Now Army and Ik singed dam deal with 70% lions share is with china, Land yours, water yours, maintenance and security headache your problem, 70% lion share of profits to china.


Blaming others is excusing yourself.
 
.
signed with the army's blessing? of course not completely rule out that thought. What about All-weather brother who offered those horrendous terms.

cpec good news = army takes credit
cpec bad news = blame blame blame the previous government.

Now Army and Ik singed dam deal with 70% lions share is with china, Land yours, water yours, maintenance and security headache your problem, 70% lion share of profits to china.


Blaming others is excusing yourself.[/QUOTE
If nawaz cant see it coming he is to blame. Leader is one who has vision.
 
.
i am more concerned with what will be the end user per unit cost. currently on average we are paying from 10-18 cents. Too high for common man even for industry.
 
.
signed with the army's blessing? of course not completely rule out that thought. What about All-weather brother who offered those horrendous terms.

cpec good news = army takes credit
cpec bad news = blame blame blame the previous government.

Now Army and Ik singed dam deal with 70% lions share is with china, Land yours, water yours, maintenance and security headache your problem, 70% lion share of profits to china.


Blaming others is excusing yourself.

Please funds the dam

CPEC Power Projects of Over 13,000MW to be Completed Soon
CPEC-coal-project.jpg



A meeting of the Parliamentary Committee on China-Pakistan Economic Corridor (CPEC) was held under the Chairmanship of Sher Ali Arbab, MNA.

Secretary Power Division briefed the Committee on the power projects under CPEC. He explained that under the CPEC framework agreement signed by China and Pakistan, there were 14 power generation projects which were categorized as prioritized projects with 10414 MW generation capacity and 7 projects were categorized as Activity Promoted with the power generation capacity of 6645 MW.



Currently, there are 20 power projects of 13048 MW at different stages of implementation. Out of which 9 projects are commissioned with a capacity of 5320 MW. While 6 projects are under construction with a generation capacity of 4484 MW. Five projects are under LOI/LOS stage with a capacity of 3244 MW.

Matiari-Lahore HVDC transmission line of 878 KM long with 4000 MW capacity is under construction which is the first transmission line in the private sector in Pakistan. In the current CPEC portfolio, there are nine coal-based power projects of 8220 MW.



Out of which 4 are imported coal-based projects of 4260 MW whereas 5 are Thar Coal based projects of 3690 MW. Four CPEC power projects based on coal have been commissioned.

There is a 36 month completion period for coal-based power projects as per international standards. The Committee appreciated the hard work of the concerned authorities for commissioning of the energy projects in minimum record time.

Provincial Secretaries of Energy from Sindh and Punjab were directed to submit their energy issues to the Committee for further consideration and redressal by the concerned departments. The Chairman directed Power Division that monthly progress reports of under-construction energy projects may be furnished to the Committee regularly.

Secretary Railways also briefed the Committee on ML-1 project. He explained that CDWP has recommended PC-1 of USD 7.2 Billion project to ECNEC which will be considered in its forthcoming meeting. Financing Committees have been constituted from Pakistan as well as China. Five exhaustive meetings have been held on this project. It was a huge investment in the history of Pakistan Railways. There is a complete business model to modernize the Railways as a corporate self-sustaining entity. The important feature of this project is that it will retire the loan itself. Railways is in search of top of a line consultant. TORs have been finalized after a well-thought exercise.

The Chairman recommended the Railways that this is the last chance for recovery of the Railways. A governance model should be introduced where the regulator has the freedom of oversight. Profitability and safety standards are maintained as a reciprocal factor.

The meeting was attended by Noor Alam Khan, MNA, Sadaqat Ali Khan Abbasi, MNA, Umar Aslam Khan, MNA, Ahsan Iqbal Chaudhary, MNA, Sardar Ayaz Sadiq, MNA, Murtaza Javed Abbasi, MNA, Mehnaz Akber Aziz, MNA, Senator Mir Kabir Ahmed Muhammad Shahi and Senator Dr. Shehzad Waseem.

Thar coal? I thought pmln said we had bad quality of coal??
 
.
signed with the army's blessing? of course not completely rule out that thought. What about All-weather brother who offered those horrendous terms.

cpec good news = army takes credit
cpec bad news = blame blame blame the previous government.

Now Army and Ik singed dam deal with 70% lions share is with china, Land yours, water yours, maintenance and security headache your problem, 70% lion share of profits to china.


Blaming others is excusing yourself.
Yes, China is taking over Pakistan, Pakistan Army is cruel, you are right.
 
.
people who think china taking over are fools . there is Afghanistan and Pakistan these to nation in the past have beaten china time of ganjas khan

pakistan is using china like they use uncle sam.
 
.
i am more concerned with what will be the end user per unit cost. currently on average we are paying from 10-18 cents. Too high for common man even for industry.
coal is at 8 cents, while most hydro is at 7-8 cents..

the cost for coal plants is high(1-2 cents given faulty calculations & high >20% RR) but for hydro its pretty much within the range seeing 1.5 cents go to water royalty and we have 30 years transfer agreement.

solar investment however was a scam..way too expenisve

wind is also on higher side with around 11 cents vs optimum price of around 7 cents
 
.