China Pakistan Economic Corridor (CPEC) | Power Plants

Chinese Embassy Pakistan
The CGGC 884 MW Suki Kinari Hydropower Project, a CPEC clean energy project, has successfully achieved the capping of the spillway section! With joint efforts of both Chinese & Pakistani staff, the project is making steady progress amid COVID-19.


1638539960686.png




1638539987403.png




1638540008651.png
 
. . .
Under Construction Karot Hydropower Project - 720MW

Located on Jhelum river and first Hydel Project of CPEC.
The Project physicals progress is around 93% and first unit commissioning is expected in early 2022.

1638648085116.png



1638648137105.png
 
. .
ISLAMABAD – The Karot Hydropower Project will start its commercial operation by first half of the year 2022 as around 95 percent work of the project had been completed, according to official sources in the China Pakistan Economic Corridor (CPEC) Authority.

Recently, the Karot Hydropower Project, which is a major project under the China-Pakistan Economic Corridor (CPEC), successfully closed the gates of the diversion tunnels, starting reservoir impoundment. The project has been invested by the China Three Gorges Corporation (CTG) with a total value of about $1.74 billion.

The Karot hydropower project in Punjab province is the fourth level of the five cascade hydropower stations planned for the Jhelum River. The beginning of the reservoir impoundment of the first CPEC hydropower project is a milestone and will pave the way for the wet testing of the generator units.

Since the groundbreaking of the project in April, 2015, the Chinese and Pakistani engineers and workers at the project have jointly overcome different challenges including the COVID-19 pandemic, thus a series of achievements have been made such as the river closure and lifting of the first rotor.

The sources said that the start of reservoir impoundment is hard-earned fruit by the mutual support between the Pakistani and Chinese workers. The forthcoming commercial operation of the hydropower station project, which has provided over 4,000 jobs for the locals during the peak time of its constriction, will further address the electricity shortage issues in Pakistan with cheap and clean energy and improve the energy structure of the country.
 
.

Under Construction 4320 MW Dasu Hydropower Project.

Dasu Dam Stage 1 Completion..............: 2025
Power Generation of stage 1..................: 2160 MW


1638971711961.png




1638971736565.png




1638971753745.png
 
.
1639006854972.png



NA Standing Committee on PD, SI visits Mohmand Dam to review progress on project
Project’s 1st unit to be commissioned in December 2025,


The delegation was briefed that Mohmand Dam is the 5th highest concrete-face-rock-fill Dam (CFRD) in the world. Construction work on as many as 13 sites is simultaneously underway on the project. These sites include diversion tunnels, power intake and power waterway, spillway, re-regulation pond, left bank irrigation tunnel, switchyard, power house, main dam abutment, access roads and project colony etc. This is a good omen for the project at a time when the whole world is adversely affected by the Covid-19 pandemic, it was further briefed.

The delegation was informed that the first unit of the project will be commissioned in December 2025. On completion, the dam will store about 1.2-million-acre feet (MAF) of water and help mitigate floods in Peshawar, Charsadda and Naushera. Besides supplementing 160,000 acres of existing land, about 18,237 acres of new land will also be irrigated. Mohmand Dam Power House will generate 800 megawatt (MW) hydel electricity, contributing 2.86 billion units of low-cost and environment friendly hydel electricity annually to the National Grid.

In addition, 300 million gallons water per day will also be provided to Peshawar for drinking purpose. Annual benefits of the project have been estimated at Rs. 51.6 billion. It was further briefed that a hefty amount of Rs. 4.5 billion will be spent on Confidence Building Measures (CBM) in the project area for socio-economic development of the locals.


1639006889423.png
 
.
Mohmand Dam Hydropower Project - 800 MW
Under Construction since September 2019
Gross Storage 1.2 MAF
Annual Energy Production 2,862 GWh
Completion date: 2025…

1639143953539.png




1639143994576.png




1639144069683.png
 
.

800MW Mohmand Dam – Construction of Diversion Tunnels


An important structure for construction of main dam, the total length of the Diversion Tunnel 1&2 is more than 3000m. Due to large diameter (15m), the excavation was divided into three layers (heading, benching & invert).

Both tunnels are being excavated from multiple work fronts and some sections breakthrough with each other.
An important structure for the construction of main dam, the total length of the Diversion Tunnel 1&2 is more than 3000m. Due to large diameter (15m), the excavation was divided into three layers (heading, benching & invert).

Both tunnels are being excavated from multiple work fronts and some sections breakthrough with each other.



1639236292610.png




1639236318075.png
 
. .
Suki Kinari Hydropower Project

5th breakthrough of Headrace Tunnel at Suki Kinari Hydropower Project took place on 13th December, 2021.
23.2Km long headrace tunnel is being excavated through different access Adits/Tunnels. More than 4 km long tunnel sections (A6b-A7a) breakthrough with high-accuracy alignment.


1639491520523.png




1639491547159.png




1639491596738.png
 
.
720MW Karot HPP - Re-construction & handing of the new cable bridge has been occurred recently.


In Reservoir area of Karot Hydropower Project, two bridges have been reconstructed which were officially handed over to the AJ&K Administration.

The main traffic pedestrian bridge connecting the Punjab Province on the right bank and the AJK on the left bank. It is located about 6.6km downstream of the Azad Pattan Bridge and 13km away from the dam site. The total length of the bridge is 277m, the main span is 189m, the full width of the bridge is 3.2m, and the clear width is 2.5m. The S7 road is a pedestrian bridge connected to the local road at the left bank bridge.
 
. .
Another Milestone marked at 800MW Mohmand Dam

On December 18, The Diversion Tunnel no. 1 breakthrough between upstream and Inlet section. To celebrate the all-section breakthrough of Diversion tunnel, a short ceremony was held at construction site. The total length of Diversion tunnel no.1 is 1681.14m.

There are two diversion Tunnels (1&2) and accumulated length is more than 3000m. Due to large diameter (15m), the excavation is being done in three layers (heading, benching & invert).


1639929364991.png




1639929392221.png
 
.