China Pakistan Economic Corridor (CPEC) | Power Plants

2x330MW Power Plant Projects at Thar Block-II Under Construction

They have provided jobs to 1838 local people and will provide more jobs to locals for the peak period of construction. CPEC projects are benefiting local communites!



1633961160769.png




1633961220169.png




1633961256713.png
 
.
BEIJING, Oct 10 (APP):The 330 MW Thar Energy Limited (TEL) Power Project in Thar Block-II being completed under China-Pakistan Economic Corridor (CPEC) in Sindh province was making steady progress, said a senior Chinese official.

The TEL power plant was a 330MW mine-mouth lignite-fired power project being built by Thar Energy, which was owned by Hub Power Company (Hubco), China Machinery Engineering Corporation (CMEC), and Fauji Fertilizer Company (FFC).

The TEL power plant would supply electricity to the national grid under a 30-year Power Purchase Agreement (PPA). Two more coal-fired power plants named Engro Thar Block II power plant and ThalNova were also being developed in Thar Block II, CEN reported.

The Engro Thar Block II power plant was a coal-fired power station in the Tharparkar district, Sindh. It was Pakistan’s first power plant to use the indigenous coal reserves of Thar.

The 660MW power plant, which was part of CPEC, was developed by Engro Powergen Thar (EPTL), a joint venture of Engro Powergen (EPL), China Machinery Engineering Corporation (CMEC), Habib Bank, and Liberty Mills. Construction on the Engro Thar Block II power plant was commenced in April 2016. Trial operations at the plant began in July 2018 while commercial operations began in July 2019.

The coal-fired subcritical power plant was located five kilometres away from Thar Block II near Thar coalfields in Sindh province. It consisted of two 330MW subcritical units, which integrated circulating fluidised bed (CFB) boilers, tandem compound steam turbine units, and generators. CFB was an ideal option for the low-calorific-value Thar lignite coal.

It helped to regulate the plant’s environmental footprint by reducing nitrogen oxide emissions and capturing sulphur oxides. The 20kV, 50Hz, three-phase intercooled generators featured a hydrogen-cooled rotor and stator core, as well as water-cooled rotor windings.

The power plant was also equipped with associated equipment and systems such as cyclones, air pre-heaters, and water walls. Sindh Engro Coal Mining Company (SECMC) supplied approximately 3.8 million tonnes per annum (Mtpa) of coal for the coal-fired power plant from a new opencast mine.

SECMC was a joint venture (JV) by the Government of Sindh (GoS) and Engro Powergen (EPGL). The JV was formed to extract the coal reserves available at the seventh biggest coal mine site in the Thar Desert in Sindh province.

The new coal-fired power plant fed electricity to a 500kV double-circuit transmission line of the grid network between Thar and the Hesco grid station in Jamshoro. The estimated cost of the Engro Thar power plant was US $995.4 million – funded by a syndicate led by China Development Bank (CDB) with the support from China Export and Credit Insurance Corporation (Sinosure).

The syndicate included Habib Bank, United Bank, Bank Alfalah, National Bank Pakistan, Faysal Bank, Construction Bank of China, and Industrial and Commercial Bank of China (ICBC). ThalNova was a second similar 330MW power plant being developed in the same block. The financial closing for the power plant was achieved in September 2020 and the commercial operations are scheduled for 2022.
 
.
884MW Suki Kinai Hydropower Project - CPEC Project

A Straight-of-the-art steel factory has been established within the construction site to produce Steel liner for the Headrace tunnel and Penstock system.


1634043243578.png




1634043330670.png




1634043369128.png
 
.
Damsite of Suki Kinari Hydropower Project -884MW

- Location: on Kunhar River, Kaghan Valley, Manshera, KPK
- Project Cost: 1.9 billion USD
- Under strategic CPEC framework.
- Construction Started: early 2017

1634043970090.png




1634043992722.png




1634044020659.png
 
. .
Dasu Hydropower Project: China links resumption of work to payment of compensation?

Mushtaq Ghumman
15 Oct 2021


ISLAMABAD: China has reportedly sought compensation of $38 million (Rs 6.5 billion) from Pakistan for the dead and injured Chinese engineers working on Dasu Hydropower Project, prior to resuming work on the stalled project, well informed sources told Business Recorder.

On July 14, 2021, thirteen people, including nine Chinese engineers, two locals and two personnel of the Frontier Constabulary (FC) died and over two dozen other people sustained injuries when a bus carrying the team working on the project fell into a ravine after it was hit by a car laden with explosives.

Pakistani authorities say that Indian Spy Agency, RAW, was directly involved in the attack on the Chinese team working on construction of tunnel site of 4,300MW Dasu project.

According to Secretary Water Resources, Dr Shahzeb Khan Bangash, the civil work in the project has been stalled since the attack on Chinese engineers in July.

The sources said the issue of compensation to the Chinese nationals is being discussed at a high level. Ministry of Foreign Affairs, Ministry of Finance, Ministry of Interior, Ministry of Water Resources and Chinese embassy were working closely on the compensation package, as well as, resumption of work on the project.

According to sources, the Steering Committee, comprising Secretaries of concerned Ministries had constituted another Committee which deliberated on the issues linked to Dasu project, especially volume of compensation being demanded by the Chinese government.

The Committee has constituted a Subcommittee, comprising all the relevant Ministries to discuss compensation package by taking the Chinese embassy on board as the proposed package is being termed as “irrational”.

The sources said, the Subcommittee of all Ministries will deliberate on the compensation package demanded by the Chinese government and will share its working with the main committee, which will give its approval. “The Subcommittee will develop a benchmark for compensation considering that if the demand of Chinese government is met as it is it will create issues for the government in future,” the sources maintained. Secretary Water Resources, the sources said, is hopeful that compensation issue will be sorted out within a couple of weeks, after which civil work on the site will resume.

National Electric Power Regulatory Authority (Nepra) which had allowed one per cent of capital cost as security to be built in the consumers’ end tariff, has not yet inquired from the Water and Power Development Authority (Wapda) as to the reasons for the insufficient security to those who are working on power projects.

The Chinese firm, China Gezhouba Group Corp, which suspended work on the Dasu project after the bus incident, had announced negation of its decision to resume work and terminate Pakistani workers, on the request of the Pakistani government. However, the company has not yet resumed work and is saying that it will not proceed ahead until compensation package and more security of Chinese nationals is provided.

Recently, Chairman Water and Power Development Authority, Lt. Gen. Muzammal Hussain (retired) who has secured another term met Prime Minister Imran Khan and briefed him about hydropower projects including the Dasu project.

“We are in close contact with the Chinese embassy in Islamabad, as well as, China Gezhouba Group Corp so that work resumes on the project within the next 15 days,” said an official on condition of anonymity.

Copyright Business Recorder, 2021
 
.
ISLAMABAD: The Ministry of Planning, Development and Special Initiates, Friday, revealed that the construction work on 2,160 MW Dasu Hydro Power Project has been resumed, which was stopped after the July 14 terrorist attack in which 13 people, including nine Chinese nationals were killed.

The ministry stressed for reviewing the Public Sector Development Programme (PSDP) priorities as due to major focus on regional or smaller projects, mega projects of national importance are affected.

Asad Rafi Chandna, additional secretary of the ministry, while briefing the Senate Standing Committee on Planning, Development and Special Initiates said that work has started on the project, which is expected to be completed by February 2025.

The committee meeting was chaired by Senator Saleem Mandviwalla, where briefing was given on the current status of all the undergoing PSDP projects, along with their completion plan.

According to the briefing, 15 percent physical progress on the Dasu power project has been achieved so far.

Dasu Hydropower Project: China links resumption of work to payment of compensation?

The total cost of the project is Rs510.980 billion, while Rs56.514 billion was allocated in the budget for 2021-22.

Throw-forward of the project as of July 1, 2021 stood at Rs359.283 billion.

The Planning Ministry officials informed the committee that 1,155 PSDP projects are amounting to Rs9,422 billion, in which, 710 projects are ongoing, while 445 are new.

The estimated cost of the ongoing and new projects is Rs7,278 billion and Rs2,144 billion, respectively.

The committee was informed that a total of Rs900 billion including Rs800 billion local and Rs100 billion were allocated in the budget 2021-22 for the PSDP.

As of October 12, 2021 utilisation stood at Rs106 billion against the authorisation of Rs379 billion.

To know the exact breakup of these projects, the chairman committee asked for the ageing of the allocated budget and overall projects.

While briefing the committee regarding the sectorial breakup of the PSDP 2021-22, the officials apprised that 62 percent of the budget is allocated for the infrastructure sector and 20 percent for the social sector.

On the completion plan of most important projects, it was said that the Ten Billion Tree Tsunami programme had a physical progress of 31 percent (expected completion 30 June 2023), Dasu hydropower project stage-1 (2160MW) had a progress of 15 percent (expected completion February 2025), Mangla Power station Refurbishment (310MW) had a physical progress of 48 percent (expected completion June 2024), Tarbela fifth extension (1410MW) had a physical progress of two percent (expected completion June 2025), Tarbela fourth extension had a physical progress of 99 percent (expected completion December 2022), Diamer-Bhasha Dam Project (Dam part) had a physical progress of four percent (expected completion June 2029), Diamer-Bhasha Dam Project (land acquisition and re-settlement) had a physical progress of 72 percent and Mohmand Multipurpose Dam project had a physical progress of nine percent (expected completion December 2025).

The officials, while further divulging about the projects said that 10 percent of work had been completed on 50 percent of projects, and 30 percent of projects are new and of the remaining 70 percent projects, 100 percent work had been completed on 50 percent of the projects.

Copyright Business Recorder, 2021
 
. .
MULTI-PURPOSE DIAMER BHASHA DAM – 4500MW

o Gross water storage capacity of 8.1 MAF
o 1.23 million acres of additional land for irrigation
o Installed power generation capacity of 4,500 MW
o 18 billion units per annum to the National Grid


1634484217726.png





1634484240725.png





1634484270581.png
 
.

884MW Suki Kinari Hydro Power Project


- Location: on Kunhar River, Kaghan Valley, Manshera, KPK
- Project Cost: 1.9 billion USD
- Under strategic CPEC framework.
- Construction Started: early of 2017



1634684896908.png




1634684918491.png




1634684944773.png
 
. .
4500 MW Diamer Bhasha Hydropower Project Under Construction..
Working is going on in full swing at divergent tunnel's inlet side.



1635082926507.png
 
. .
By the Grace of ALLAH and the efforts of all stakeholders, the construction works have started work on Dasu Hydropower Project.
The great security arrangements are being ensured by the authorities.
 
.
Energy China Gezhouba Group has built the most advanced Steel Processing Plant in Pakistan with an area of 4200m2 for the construction of Suki Kinari (SK) Project Hydropower, a key project listed among the first batch of priority projects in the CPEC.

The main structure of the plant is a portal frame, equipped with a 4,000t frame hydraulic press, gantry crane, CNC cutting machine, welding cross arm, and a batch of advanced equipment. The plant is designed with a peak monthly production capacity of 950 tons.

The construction and operation of the plant have effectively promoted local employment. Chinese Contractor has "tailored" training programs for Pakistani employees, managing to improve their working skills and assist them in achieving a desired professional future.



1635423929484.png





1635423958573.png