Bilal9
ELITE MEMBER
- Joined
- Feb 4, 2014
- Messages
- 26,569
- Reaction score
- 9
- Country
- Location
Hami Bangla Bhuliya Geche
Orey Hamarey afnera keu dhoira maira laan....May Allah save the Bangla language from these cultural fakes....
Follow along with the video below to see how to install our site as a web app on your home screen.
Note: This feature may not be available in some browsers.
Hami Bangla Bhuliya Geche
Do not worry, @Bilal9. I was just quoting Khwaja Nazimuddin of Dhaka. He became the Governor General (President) of Pakistan in 1948 after the death of Quaid-e-Azam Muhammad Ali Jinnah. At one time he came to Dhaka from Karachi, the federal Capital of the then Pakistan. When the newspapermen started talking with him in Bengali, he uttered, 'Hami Bangla Bhuliya Gechi". He was probably worried about his position with the west Pakistani politicians.Orey Hamarey afnera keu dhoira maira laan....May Allah save the Bangla language from these cultural fakes....
New Recruit
Most of the development in Chittagong is either in it's early stages or hasn't even begun yet. What substantial development has the city made in the past decade? The roads and waterlogging in CTG is even worse than it is Dhaka and I don't see the city expanding like what Dhaka is doing in Uttara and Basundhara.
By watching the video footings I almost thought, all these projects have been completed and commissioned for traffics. But, anyway, let the people celebrate on the animations and renderings while the real construction works continue for a few more years, if not decades.Most of the development in Chittagong is either in it's early stages or hasn't even begun yet. What substantial development has the city made in the past decade? The roads and waterlogging in CTG is even worse than it is Dhaka and I don't see the city expanding like what Dhaka is doing in Uttara and Basundhara.
By watching the video footings I almost thought, all these projects have been completed and commissioned for traffics. But, anyway, let the people celebrate on the animations and renderings while the real construction works continue for a few more years, if not decades.
@UKBengali @Bilal9
Read the news above. I am not blaming you, but Karnaphuli tunnel was supposed to start in October 2016. Now, you are telling it will start this year. If someone points the discrepancies, you shout him down by saying of negative mind.The Karnapuli tunnel boring will start in September this year once the machine arrives in BD from China. China has released the funding for this year.
Not all project got delayed for few years. Karnaphuli tunnel delayed for 2 year due to late arrival of Tunneling machine. Outer Ring road project did not delayed much and working progressing on full speed. By now more than 75 percent soil works completed. Before 2013, there was not a single flyover in Chittagong city, now 4 flyover are handling the traffic there including this 5.2 km long Akhtaruzzaman flyover. Note that, this long flyover traversing the most busy areas of the city significantly alleviated the traffic congestion there. But this flyover completed and opened for traffic 6 months before schedule.By watching the video footings I almost thought, all these projects have been completed and commissioned for traffics. But, anyway, let the people celebrate on the animations and renderings while the real construction works continue for a few more years, if not decades.
@UKBengali @Bilal9
Read the news above. I am not blaming you, but Karnaphuli tunnel was supposed to start in October 2016. Now, you are telling it will start this year. If someone points the discrepancies, you shout him down by saying of negative mind.
BD authorities publicize something surreal things about project implementation. Many other projects are similarly delayed because of their inefficiency. You do not have to cry foul for tiny reasons. About road widening, tens of such Zilla roads need widening work. But, you are chaste thumping only on one or two roads. Please talk to Mr. Quader, your minister uncle, to fix the Dhaka-Aricha road.
By April 2018, Tunnel's 14% works has been completed, after arrival of tunneling machine by June/July, the main works will start. So, it is not true that, works on Tunnel yet not started.It is happening now.Read the news above. I am not blaming you, but Karnaphuli tunnel was supposed to start in October 2016. Now, you are telling it will start this year. If someone points the discrepancies, you shout him down by saying of negative mind.
BD authorities publicize something surreal things about project implementation. Many other projects are similarly delayed because of their inefficiency. You do not have to cry foul for tiny reasons. About road widening, tens of such Zilla roads need widening work. But, you are chaste thumping only on one or two roads. Please talk to Mr. Quader, your minister uncle, to fix the Dhaka-Aricha road.