Suki Kinari Hydropower Project (884MW)– Another Landmark Achieved


On 19th September, the last drilling rod of raise boring rig broke through the last barrier and successfully penetrated the headrace tunnel. The surge shaft total depth is 233m with a diameter of 7.45. The completion of pilot hole lay down a solid foundation for the smooth excavation of the surge shaft in the later period.



1600617386670.png
 
Construction Updates from Suki_Kinari_Hydropower_Project .....884MW