Pakistani Roads, Motorways and Highways

5c725b2d39210.png





5c725b2d3740f.png
Stunning Balochistan. Majestic :smitten:
 
South Balochistan:

110 KMs 2 lane Khuzdar Basima N-30 highway
Construction work in full swing.
Cost-...................19 Billion
Work commenced in Oct 19.
20% physical work completed,
It will link Khuzdar with N-85 to also serve Gwadar CPEC
Completion ................end 2021.


 
Realignment of KKH under Dasu Hydropower Project.

The breakthrough (Heading Portion) of Dasu #1 tunnel has been completed successfully on 6th August, 2020. The tunnel length is 180m including a 60m open tunnel of 10.2m x 12.4m (HxW).

On completion of the 242 M high dam, the existing KKH will submerge and realigned roads at higher elevation are under construction having 07 road tunnels.


116874173_164285498560609_595191737339008201_o.jpg
 
Realignment of KKH under Dasu Hydropower Project.

The breakthrough (Heading Portion) of Dasu #1 tunnel has been completed successfully on 6th August, 2020. The tunnel length is 180m including a 60m open tunnel of 10.2m x 12.4m (HxW).

On completion of the 242 M high dam, the existing KKH will submerge and realigned roads at higher elevation are under construction having 07 road tunnels.


116874173_164285498560609_595191737339008201_o.jpg
who is contracted to build this road?
 