*Let us look at the Nandipur power project objectively based on what I know about it.
It is a 425 MW power project with a cost of about $574-million when it was announced in 2008. About $1.35-millin per MW, not too excessive for a combined cycle thermal power plant. Completion was expected to be in 2011; 3 years being quite normal for power plants lead in time.
It can only be the complete ineptitude of the PPP gov’t that no one cared to keep an eye on the progress of the project. Hence much of the project machinery was stuck at Karachi Port for 2 years for unknown reasons. By that time natural gas was no longer available for this plant. Cost is therefore now double the original estimate.
Understand main reason of the increased cost is that plant is a gas turbine designed to burn natural gas. It can also be run on jet (kerosene) & gas oil (diesel) without a problem but because of the sulphur & metals limits; imported high Sulphur fuel oil (Furnace oil) can not be burnt. Therefore additional investment in a fuel oil treatment plant was required. In comedy of errors; capacity of fuel oil treatment plant being installed is less than the requirements; thus if & when everything is up and running; output will be limited to 250 MW.
The plant was inaugurated with much fanfare in May 31, 2014 by the Sharif brothers but it couldn't run beyond 5 days because it was burning gas oil with the production cost at Rs 85 per KWH (Then gas oil was $1000 per ton).
I am just a minor energy consultant, but if I were to make such errors, I wouldn’t get another assignment in a million years. However, despite the fact that MD & other plant engineers must have known what they were doing, they were awarded pride of performance medals for bringing the project on line!!!!
It is not that Pakistan lacks good engineers; it is only that we are so used to defrauding others that we have started to deceive ourselves. Such gross errors will continue until we start giving priority to merit & diligence instead of the current preference for political patronage & nepotism..
*
at last a sensible post ..thumbs up for that..... storage cost at port, holding time for contract n then again mobilizing , n ppl who are talking about the cost then hv *#$% idea how much turbine cost with is M&O, spares n what are the delivery schedule ...every " matric spply holder becomes a engineering analyst jst from news ticker by noble media n "SIYASI BIYAN aka 35 punctures" of IK
however there is no doubt that in hurry to complete engineering matters were messed up, n now its time to rectify those ..