What's new

Iran-Pakistan Gas Pipeline (IPP) News & Updates.

The final contract is still not signed. That is the ground reality so far.

You are correct. I was so happy for Pakistan when the pipeline was inaugurated on March 11, 2013 but more than two months later, they've still not signed the final contract to start the construction of the pipeline on the Pakistani side.

So far I am very disappointed but I am still hopeful.
 
You are correct. I was so happy for Pakistan when the pipeline was inaugurated on March 11, 2013 but more than two months later, they've still not signed the final contract to start the construction of the pipeline on the Pakistani side.

So far I am very disappointed but I am still hopeful.

Hope is good, but I just don't see this pipeline being built anytime soon.
 
Curbing energy shortage
Senate body for early completion of IP, TAPI gas projects

Wednesday, May 29, 2013

By Ijaz Kakakhel


ISLAMABAD: Keeping in view the severe energy shortage, the Senate’s Standing Committee on Petroleum and Natural Resources on Tuesday directed the ministry and Inter State Gas (Pvt) Ltd (ISGS) to speed up the work on Iran-Pakistan (IP) Gas Pipeline and Turkmenistan-Afghanistan-Pakistan-India (TAPI) Gas Pipeline projects.

The country is confronting severe power and gas shortfall and completing the above two projects on time will be great achievement. The meeting was held in the Parliament House under chairmanship of Senator Muhammad Yousuf. Over IP Gas Pipeline Project, the parliamentarians expressed serious reservations over delay in distribution of gas pipeline while on Iranian side more work had been completed. The committee chairman said Pakistan urgently needed its completion but delaying tactics were being used. Pakistan is just dealing in paper work while physically nothing has been done so far.

ISGS managing director told the committee that under the IP Gas Pipeline Project, the gas is to be supplied from Iran’s South Pars gas field and delivered at Pak-Iran border, near Gwadar. The project is being implemented on a segmented approach whereby each country shall be responsible for construction of the pipeline in the respective territory. He said that total length of the gas pipeline is 1,931 kilometres (kms) in which 1,150km is within Iran and 781km in Pakistan. From Iran side, he said only 250km gas pipeline is left to provide gas to the border of Pakistan. While on Pakistan’s side, the physical work is yet to be started, he maintained. Iran will also provide $500 million in kinds to Pakistan for laying the gas pipeline. The completion date of the project is Dec 2014, which will provide 750 million cubic feet per day gas to Pakistan, the MD added.

He further said that the estimated cost of Pakistan segment of pipeline is about $1.8 billion and Pakistan has adopted a multi-pronged strategy to meet the challenges of project financing, which included government to government agreement, Gas Infrastructure Development Cess as well as commitments from public sector entities.

The petroleum secretary told the committee that Pakistan could not initiate the work due to some financial problem but Pakistan has signed several agreements with Iranians delegations. In order to begin the work, it requires more legislation on part of government of Pakistan, he maintained. He also assured the committee that approval would be made from concerned authority in Pakistan.

The TAPI Gas Pipeline Project aims to bring natural gas from Turkmenistan to Afghanistan, Pakistan and India. Several international consortiums will finance this project, which will provide 3.2 billion cubic feet per day of natural gas. The ISGS MD told the committee it will be completed by 2017 and the gas sale purchase agreement was already done.

The committee was informed that Inter-governmental Agreement was signed by the head of states of all the member countries during TAPI Summit held at Ashgabat on Dec 11, 2010. The Gas Pipeline Framework Agreement was signed by the respective petroleum ministers of the four countries.

The committee in written was informed that TAPI parties already agreed n principle to appoint Asian Development Bank (ADB) as transaction adviser to broadly update the pre-feasibility study, market the project, take the transaction to financial close and assist parties in finalisation of pipeline consortium. In this regard draft transaction advisory services agreement has been circulated by the ADB to TAPI parties, which is currently under review.

Daily Times - Leading News Resource of Pakistan
 
.............

He further said that the estimated cost of Pakistan segment of pipeline is about $1.8 billion and Pakistan has adopted a multi-pronged strategy to meet the challenges of project financing, which included government to government agreement, Gas Infrastructure Development Cess as well as commitments from public sector entities.................

What strategy? Money is money, and 1.8 billion dollars is a LOT of money to come up with for this pipeline, no matter how many "prongs" are used. More importantly, I do not see the PM-elect's patrons in the Holy Land being generous to fund this project anytime soon either.
 
Political transition may delay IP gas project
Wednesday May 29, 2013

Proj-480x238.jpg


The multi-million-dollar Iran-Pakistan (IP) gas pipeline project is unlikely to be completed by the contractual deadline of December 2014 because of the political transition in Islamabad, officials stated on Wednesday.

The project was delayed because important approvals for beginning construction of the pipeline could not be obtained from the caretaker government, petroleum secretary Abid Saeed was quoted as saying, by Khaleej Times.

This delay is expected to aggravate Pakistan’s energy crisis. Work on the project inside Pakistan has been suspended because of polls and transfer of power, he said. “On certain issues related to the IP project, the Petroleum Ministry needs to get approval from the next government,” he added.

Inter-State Gas Company Managing Director Mobin Solat said Iran had completed 900 km of a 1,150-km pipeline from a gas field to Iranshehr.

Iran is working on another 250-km section from Iranshehr to the border at Gabd and about 60 percent of the work had been completed.

Construction on the Pakistani side could not begin because the engineering, procurement and construction firms required sovereign guarantees for mobilising machinery and workforce, Solat said. The Pakistan government needs to issue a sovereign guarantee to Iran’s Tadbir Energy, the engineering and construction contractor, and this has been delayed till the new elected government takes over, Saeed said.

Political transition may delay IP gas project | Pakistan Today

Pehla bahana!
 
I think that Pakistan just might be able to pull strings to get the project underway and done. We have a silent partner, namely India, whose interest is served by an extension of this (& TAP) pipeline. Its influence would be welcome.

Do not cross out the project yet. There is plenty of hope. IP pipeline is not a question of IF, but WHEN.
 
Interesting Article about Pak-Iran Gas Pipeline
ISLAMABAD: The government has asked Iran to reduce gas price for Iran-Pakistan pipeline under price renegotiation clause of the bilateral sales and purchase agreement (GSPA) to bring it at par with the rates finalised with Turkmenistan.

“We are activating the price renegotiation clause of the agreement,” Prime Minister’s Adviser on Petroleum Dr Asim Hussain told Dawn on Friday. “Iran has to reduce gas prices and come down to TAPI ((Turkmenistan-Afghanistan-Pakistan-India pipeline) rate.”

An official said if the price of Iranian gas was lowered to that of TAPI pipeline level, Pakistan would save about $1.5 billion over the life of the project as compared with the price finalised under the IP-GSPA.

“The price renegotiation will be an ongoing process,” said Dr Hussain, explaining that under the agreement, the prices could be renegotiated on the basis of comparable gas prices one year before the gas flow begins in Dec 2014.

“We may be able to secure even lower prices than TAPI rates if gas prices plunge in the international market, in Europe and the US. We are closely monitoring world gas prices,” he said.

He confirmed that Iran’s Tadbir Energy and Pakistan’s Interstate Gas Company could not sign an agreement for the construction of 781-km pipeline by the Iranian firm inside Pakistan because discussions required further consultations. “The agreement will be signed before Feb 27,” Dr Hussain said.

An official said a draft agreement had been handed over to a visiting Iranian delegation for getting it vetted in Tehran.

The cost of construction of the pipeline from Gabd-zero point, on Pakistan-Iran border, to Nawabshah for the delivery of 750 million cubic feet of gas per day has been tentatively agreed upon at $1.5 billion but Iran has been asked to reduce the per kilometre construction cost.

After Iran vets the draft agreement, the mode of payment for gas sales will need a delicate examination in view of US sanctions against that country. Barter trade between the two countries can be an option.

Under the proposed agreement, Tadbir Energy has to lay the pipeline inside Pakistan and provide $500m loan, which is repaid as part of gas price, involving an interest rate of about two per cent plus London Interbank Offered Rate. Pakistan’s engineering and pipeline companies will provide advisory service and the Frontier Works Organisation will handle the civil works.

An official said the Iranian technical team was expected to return to Islamabad next week for consultations. Then a Pakistani team will go to Tehran to sign the agreement.

Meanwhile, a cabinet committee — headed by the minister of state for finance and comprising senior officials of petroleum, finance and law ministries — has approved a $1.5bn financing plan for the pipeline.

The plan envisages a $500m loan agreement with Iran on government-to-government basis and provision of $500m by the ministry of finance on account of receipts of the Gas Infrastructure Development Cess.

The remaining $500m will be arranged through a combination of loans from China and domestic banks.
Pakistan seeks to renegotiate Iran gas price - DAWN.COM

What do we get
1- Gas imported from Iran will be expensive than gas imported from Turkmenistan (TAPI) project
An official said if the price of Iranian gas was lowered to that of TAPI pipeline level, Pakistan would save about $1.5 billion over the life of the project as compared with the price finalised under the IP-GSPA.
2- No construction agreement for Pakistani side has been signed yet
He confirmed that Iran’s Tadbir Energy and Pakistan’s Interstate Gas Company could not sign an agreement for the construction of 781-km pipeline by the Iranian firm inside Pakistan because discussions required further consultations.
3- Tentative cost of construction on Pakistan side is around 1.5 Billion USD (150 Billion PKR). Plus the additional cost incured by extending pipeline to Nawabshah (they could have just connected the pipeline to Sui Gas supply line and saved a lot of money -because SUI-gas field is well connected to the rest of the country).
The cost of construction of the pipeline from Gabd-zero point, on Pakistan-Iran border, to Nawabshah for the delivery of 750 million cubic feet of gas per day has been tentatively agreed upon at $1.5 billion but Iran has been asked to reduce the per kilometre construction cost.
4-Payment settlement is still undecided (since we can't pay Iran in USD,EUR,GBP and all major currencies)
After Iran vets the draft agreement, the mode of payment for gas sales will need a delicate examination in view of US sanctions against that country. Barter trade between the two countries can be an option.
5- Risky financial terms (2%+LIBOR) so Iranian company has hedged her interest rate risks while exposing Pakistan to this (since with floating interest rate risks project costs and outflow could never be certain)
Under the proposed agreement, Tadbir Energy has to lay the pipeline inside Pakistan and provide $500m loan, which is repaid as part of gas price, involving an interest rate of about two per cent plus London Interbank Offered Rate. Pakistan’s engineering and pipeline companies will provide advisory service and the Frontier Works Organisation will handle the civil works.
 
Qamar warns of fines if gas not imported from Iran


ISLAMABAD: Former Federal Water and Power Minister, Naveed Qamar informed the National Assembly that if gas was not imported from Iran in 2014, Pakistan would have to pay billions in fines.

Qamar said that Pakistan should not rely on assistance from anyone as he questioned who would pay the fine if gas from Iran was not imported.

Meanwhile, Water and Power Minister Khawaja Asif said that the government’s energy policy would be announced in 20-22 days.

Qamar warns of fines if gas not imported from Iran - thenews.com.pk
 
Interesting Article about Pak-Iran Gas Pipeline


What do we get
1- Gas imported from Iran will be expensive than gas imported from Turkmenistan (TAPI) project

2- No construction agreement for Pakistani side has been signed yet

3- Tentative cost of construction on Pakistan side is around 1.5 Billion USD (150 Billion PKR). Plus the additional cost incured by extending pipeline to Nawabshah (they could have just connected the pipeline to Sui Gas supply line and saved a lot of money -because SUI-gas field is well connected to the rest of the country).

4-Payment settlement is still undecided (since we can't pay Iran in USD,EUR,GBP and all major currencies)

5- Risky financial terms (2%+LIBOR) so Iranian company has hedged her interest rate risks while exposing Pakistan to this (since with floating interest rate risks project costs and outflow could never be certain)

Good points; all of them esp the first. That is the reason India chose not to go along with it. In India's case; there is one more factor- that of security of the pipeline, passing as it does through the Balochistan region.
 
such price matter should be resolved asap Pakistan can't afford to delay such important project as the energy crisis getting worse day by day

there must be a master plan for next 25 years in energy sector and we must shift from thermal to coal, hydro and nuclear power in next 5 years the cost per unit of thermal is too high and by last ppp gov only installed thermal power projects

we need to explore our own newly found gas reserves in k.p.k to get out of the energy crisis and lower the unit price of electricity
 
Back
Top Bottom