What's new

Infrastructure Development in Pakistan

Water storage

75042_584573004890525_1364326891_n.jpg

@nuclearpak sorry ^^ That is not ATC But a Water tank, They have same structure so people get confused!
 
Last edited by a moderator:
.
This islamabad airport is starting to boggle my mind. How can you not finish a medium traffic airport? Its not like we are building an airport in shanghai or hongkong or lower manhattan, new york. This airport is being constructed on a flag ground bed. How can they not finish this thing on time? Punjab govt started hundreds of projects in the mean time and they are already done. MBS that covered half of lahore with a flyover is completed in the mean time. There is clearly a lack of motivation and dedication.
 
.
Forget the News forget the So called talk shows and forget the fake slogans of inqlaab one only has to see this page to realize who has been working in Pakistan in last 5 years and even after all the hurdles have provided the people with more then expected .

Hats off .

Any one can chose the best but choosing the bad out of worst is what makes a democratic society .
 
.
Forget the News forget the So called talk shows and forget the fake slogans of inqlaab one only has to see this page to realize who has been working in Pakistan in last 5 years and even after all the hurdles have provided the people with more then expected .

Hats off .

Any one can chose the best but choosing the bad out of worst is what makes a democratic society .
Completely agree with you. very well said.
 
.
Nooriabad wind turbine project

The project started in February of 2012 and came to an end in November 2012. The total size of the project can be gauged from the fact that it included 370 oversized pieces, weighing 7576 ton with a total cbm of 70,574.

Each wind turbine blade was 45 meters long. Each tower of a WTG consisted of three sections, top, middle and bottom. The length of each top section was 30 meters, middle section 30 meters, bottom section 18 meters, each weighing 33 ton, 50 ton and 45 ton respectively. Each nacelle of WTG weighed 72 tons.

The total distance covered between manufacturing facilities and erection site was 14,256 km.

Turbines and Wings Arriving at Bin Qasim Port

8386342828_113f04cae0_b.jpg


8386341764_c3ddc609dd_b.jpg


8385256773_67d81f284e_b.jpg


8386341324_6f729105c3_b.jpg


8386344186_ce24424f65_b.jpg


8385260529_af73fd375a_b.jpg


8386340938_6153a63897_o.jpg


8385259005_f39d80469c_b.jpg
 
.
Is the new Islamabad Airport's location right for expansion ? Is there enough space to accomodate more terminals in the future ?
 
. .
Nooriabad wind turbine project

The project started in February of 2012 and came to an end in November 2012. The total size of the project can be gauged from the fact that it included 370 oversized pieces, weighing 7576 ton with a total cbm of 70,574.

Each wind turbine blade was 45 meters long. Each tower of a WTG consisted of three sections, top, middle and bottom. The length of each top section was 30 meters, middle section 30 meters, bottom section 18 meters, each weighing 33 ton, 50 ton and 45 ton respectively. Each nacelle of WTG weighed 72 tons.

The total distance covered between manufacturing facilities and erection site was 14,256 km.

Turbines and Wings Arriving at Bin Qasim Port

8386342828_113f04cae0_b.jpg


8386341764_c3ddc609dd_b.jpg

These are not made at home are they ? Anyways its a great project ! We should have more of these in Pakistan
 
.
These are not made at home are they ? Anyways its a great project ! We should have more of these in Pakistan

These are imported by Zorlu Energy group Of Turkey From Danish firm Vestas, They were total 28 Wind mills of 1.8 MW each, Zorlu Energy signed deal of 50 MW Wind farm in Jhimpir Near Nooriabad Sindh, The Wind farm has Completed And Generating electricity.

LAHORE Metro Bus

423982_145874905569442_1815088648_n.jpg


408618_145875738902692_1636449578_n.jpg


530581_145875305569402_766771138_n.jpg


2013-01-17075308_zpsd4e5f55b.jpg


2013-01-17123616_zps78cfd600.jpg


2013-01-17122954_zpsfefcdafe.jpg
 
. . . .
Project: Pakistan Business Centre.

Architect: Shankland Cox (people behind UBL tower, Karachi.)

Client:Askari Siddiqsons Development Co.

Scope:Masterplanning Architectural & Engineering Design including Infrastructure Supervision of Construction.

About: The brief required a unique architectural concept comprising of a shopping mall, a 5 star hotel, rentable office space & amenities, all to be spread over a number of tall buildings. The tallest of the four buildings is 50 storey high. This multi-use complex will stand as one of the most prominent features of the city’s skyline and will serve as a prestigious multi-use centre for the citizens of Karachi.

Current status: Schematic Design (proposed)
c17393e01624001ffac385b14c450ecb.jpg

54f2fcfc8147ca624db42e1773c64808.jpg

a1321d271dfbc9b189e3d71f2304c4dc.jpg

b1626da609975b4df528ad80130fd04c.jpg

881f8f20a567e881191dfedfb2176c55.jpg

f89c6194e8dc490208dc4a6a1472300a.jpg
 
. . .

Pakistan Defence Latest Posts

Pakistan Affairs Latest Posts

Back
Top Bottom