What's new

India's bureaucratic red tape holds up transmission projects for Rooppur Nuclear Plant

Black_cats

ELITE MEMBER
Joined
Dec 31, 2010
Messages
10,031
Reaction score
-5
India's bureaucratic red tape holds up transmission projects for Rooppur Nuclear Plant

India's bureaucratic red tape holds up transmission projects for Rooppur Nuclear Plant

Dhaka October 13, 08:12 AM Sadrul Hasan - UNB Staff Writer


Uncertainty looms large over the timely execution of a slew of power transmission projects aimed at facilitating electricity evacuation from the upcoming 2,400 MW Rooppur Nuclear Power Plant (RNPP). The reason — the Indian financing agency is taking "excessive time" to give a go-ahead for the bidding process, UNB has learnt.

Official sources at Power Grid Company of Bangladesh (PGCB) said the state-owned power transmission body took up the projects to facilitate power evacuation from RNPP, the country’s maiden under-construction nuclear power project, with support from the Indian Line of Credit (LoC).

Dhaka signed a $1.06 billion loan agreement with New Delhi in 2017 over financing of these projects, with a target to implement them within 2022, as the 1,200 MW first unit of RNPP aims at starting commercial production from the first half of 2023.

The five transmission projects are — the 464 km 400 kV Transmission Lines, including 13km river crossing, the 205 km 230 kV Transmission Lines, including 7 km river crossing, the 400 kV 5 Bay Extensions, the 230 kV 4 Bay Extensions, and qualitative upgradation of Bangladesh Power System for frequency control ,emergency control and related tasks.

Official sources said the 464 km 400 kV Transmission Lines project has been divided into four packages for easy and quick implementation. These are the 102 km Rooppur-Bogra line, the 144 km Rooppur-Gopalganj line, the 147 km Rooppur-Dhaka line, and the 51 km Aminbazar-Kaliakoir line.

The 13 km river crossing work also consists of packages — the 6 km Padma River crossing line and the 7 km Jamuna River crossing line.

Similarly, the 230 kV Transmission Lines project is divided into three packages — the 60 km Rooppur-Baghabari line, the 145 km Rooppur-Dhamrai line, and the 7 km Jamuna River crossing line.

Official sources at PGCB said though they have completed the bidding process for some packages of the transmission projects, the remaining are stalled due to the delay in getting clearance from the Indian financing agency.

“Of these packages, the bidding for the most critical river crossing work and bay extensions are suffering due to India's bureaucratic red tape. The necessary approval from India Exim Bank is still awaited," said a top official of PGCB, who did not wish to be named.

He, however, said that timely commencement of operation of the RNPP project will depend on the timely implementation of the power transmission project. “If power transmission infrastructure is not ready, the Rooppur plant will not be able to start operation even after its timely completion," said the PGCB official.

When contacted, PGCB managing director Golam Kibria admitted the delay in the projects' bidding processes. "But I am hopeful of quick clearance from the Indian financing agency," he said.

 
. . .
India's bureaucratic red tape holds up transmission projects for Rooppur Nuclear Plant

India's bureaucratic red tape holds up transmission projects for Rooppur Nuclear Plant's bureaucratic red tape holds up transmission projects for Rooppur Nuclear Plant

Dhaka October 13, 08:12 AM Sadrul Hasan - UNB Staff Writer


Uncertainty looms large over the timely execution of a slew of power transmission projects aimed at facilitating electricity evacuation from the upcoming 2,400 MW Rooppur Nuclear Power Plant (RNPP). The reason — the Indian financing agency is taking "excessive time" to give a go-ahead for the bidding process, UNB has learnt.

Official sources at Power Grid Company of Bangladesh (PGCB) said the state-owned power transmission body took up the projects to facilitate power evacuation from RNPP, the country’s maiden under-construction nuclear power project, with support from the Indian Line of Credit (LoC).

Dhaka signed a $1.06 billion loan agreement with New Delhi in 2017 over financing of these projects, with a target to implement them within 2022, as the 1,200 MW first unit of RNPP aims at starting commercial production from the first half of 2023.

The five transmission projects are — the 464 km 400 kV Transmission Lines, including 13km river crossing, the 205 km 230 kV Transmission Lines, including 7 km river crossing, the 400 kV 5 Bay Extensions, the 230 kV 4 Bay Extensions, and qualitative upgradation of Bangladesh Power System for frequency control ,emergency control and related tasks.

Official sources said the 464 km 400 kV Transmission Lines project has been divided into four packages for easy and quick implementation. These are the 102 km Rooppur-Bogra line, the 144 km Rooppur-Gopalganj line, the 147 km Rooppur-Dhaka line, and the 51 km Aminbazar-Kaliakoir line.

The 13 km river crossing work also consists of packages — the 6 km Padma River crossing line and the 7 km Jamuna River crossing line.

Similarly, the 230 kV Transmission Lines project is divided into three packages — the 60 km Rooppur-Baghabari line, the 145 km Rooppur-Dhamrai line, and the 7 km Jamuna River crossing line.

Official sources at PGCB said though they have completed the bidding process for some packages of the transmission projects, the remaining are stalled due to the delay in getting clearance from the Indian financing agency.

“Of these packages, the bidding for the most critical river crossing work and bay extensions are suffering due to India's bureaucratic red tape. The necessary approval from India Exim Bank is still awaited," said a top official of PGCB, who did not wish to be named.

He, however, said that timely commencement of operation of the RNPP project will depend on the timely implementation of the power transmission project. “If power transmission infrastructure is not ready, the Rooppur plant will not be able to start operation even after its timely completion," said the PGCB official.

When contacted, PGCB managing director Golam Kibria admitted the delay in the projects' bidding processes. "But I am hopeful of quick clearance from the Indian financing agency," he said.

It was the biggest mistake on part of Bangladesh govt. to involve India in this project. India lobbied hard to it's ''friendly'' govt. in Dhaka to be included only to sabotage this project. India never want Bangladesh to become well versed with Nuclear technology.
 
Last edited:
.
It was the biggest mistake on part of Bangladesh govt. to involve India in this project. India lobbied hard to it's friendly govt. in Dhaka to be included only to sabotage this project. India never want Bangladesh to become well versed with Nuclear technology.
There is no threat of you becoming nuclear. But I agree, India should not be in league with a petulant child. Go get Chinese credit.
 
. .
Oh well , you reap what you sow ! India should be as far away as possible from any infrastructur project.
Classic Indian whataboutism !
India should be dropped from the project so BD government can pay with its own money. There's no need to get this money from anybody else.
 
.
Classic Indian whataboutism !
India should be dropped from the project so BD government can pay with its own money. There's no need to get this money from anybody else.

BD regime can pay with its own money YET they choose to engage india; WHY? We all know the answer, indian subservient awami regime. Now indians are dropping axe on Bangladesh.
 
.
BD regime can pay with its own money YET they choose to engage india; WHY? We all know the answer, indian subservient awami regime. Now indians are dropping axe on Bangladesh.



Indians lobbied very hard, pressure was too great.

Plus India was like, we are your neighbours and we are a nuclear power, let us help you with your little reactor.
 
.
Indians lobbied very hard, pressure was too great.

Plus India was like, we are your neighbours and we are a nuclear power, let us help you with your little reactor.

It is expected that you will defend Awami league regime indian stooge act, no matter how lame it is . In running statecraft though there is no place for harming Bangladesh national interest just so india can benefit and exploit.

Real reason is awami league and Hasina are PURELY indian stooge installed by india and operated by india.

["NOT much noticed by outsiders, long-troubled ties between two neighbours sharing a long border have taken a substantial lurch for the better. Ever since 2008, when the Awami League, helped by bags of Indian cash and advice, triumphed in general elections in Bangladesh, relations with India have blossomed. "]

 
Last edited:
.
It is expected that you will defend Awami league regime indian stooge act, no matter how lame it is . In running statecraft though there is no place for harming Bangladesh national interest just so india can benefit and exploit.

Real reason is awami league and Hasina are PURELY indian stooge installed by india and operated by india.

["NOT much noticed by outsiders, long-troubled ties between two neighbours sharing a long border have taken a substantial lurch for the better. Ever since 2008, when the Awami League, helped by bags of Indian cash and advice, triumphed in general elections in Bangladesh, relations with India have blossomed. "]




You must be delusional, If you think I'm defending Awami League.


You're brainwashed, you only see black and white, people are either just as delusional as you or they are against you; which makes them Indian stooges.


Your words not mine.
 
.
Typical Indians, all talk no action... they forced their way in this project for name and fame after hasina’s second term... and now can’t deliver, they have been kicked from other infrastructure project... should be from this if necessary
 
.

Pakistan Defence Latest Posts

Back
Top Bottom