In the history of Indian railway budgets, Suresh Prabhu will perhaps be the first railway minister not to have announced either a single new train or a new railway line, notes A K Bhattacharya.
25suresh1.jpg
Suresh Prabhu, a recent entrant to the Bharatiya Janata Party (BJP), is yet to complete a year as the railway minister in the Narendra Modi government.

But in the period he has been at the helm at Rail Bhavan, he has managed to stay in the news - mostly for good reasons and of late for reasons he may not be very happy about.
His maiden railway budget had a string of creditable firsts to it. In the history of Indian railway budgets, he will perhaps be the first railway minister not to have announced either a single new train or a new railway line.
That must have taken a lot of courage. What he spurned as the railway minister was a political opportunity to nurture his or his party’s vote bank by showering goodies — one new train to connect his own constituency or a new railway track for the constituency of his boss.
He did nothing of that sort either for himself or for his boss and none for anybody else.
What he did instead was vitally important for the long-term health and viability of the Indian Railways.
26rail8.jpg

For far too many years has the Indian Railways been starved of the much-needed investments to enhance its capacity to grow as the country’s largest transporter of goods and people. In one stroke, he increased the capital expenditure plan for the Indian Railways by over 71 per cent to over Rs 1 lakh crore.
Not only that, he laid out a five-year capital investment plan of Rs 8.6 lakh crore, once again a first for a railway minister.
An innovative financing mechanism route was followed by Mr Prabhu to meet the target of investing Rs 1 lakh crore in projects to enhance the railways’ capacity in different areas.
This included a mix of higher budgetary support, internal resources generation, leveraging of balance sheets of public sector units under the Indian Railways, setting up of joint ventures with state governments and major customers and tying up with financial institutions to tap their resources
.
Even as India Inc wailed about the high cost of domestic funds, Mr Prabhu was not hobbled by such concerns.
28budget10.jpg

He tied up with the Life Insurance Corporation of India for low-cost institutional finance of Rs 1.5 lakh crore. This too was a first for Mr Prabhu.
The ambitious freight corridor project, critical for decongesting the tracks for faster movement of both passenger and goods trains, was moving at its own slow pace.
Under Mr Prabhu, this critical project got a big push. Between November 2014 and now, contracts for Rs 17,500 crore were finalised, compared to Rs 12,500-crore worth of cumulative contracts awarded between the project’s inception in 2006 and November 2014
. What’s more, contracts worth another Rs 17,000 crore are to be finalised by March 2016 and the phased commissioning of the project would start from 2018.
And yet there are suggestions that Mr Prabhu may not have met his quarterly targets for implementing projects, even though the achievements may be better than those in the same period of last year. The ground reality, however, is quite different.
According to the capital expenditure plan for the first two quarters of 2015-16, the Indian Railways was to spend a little over Rs 28,000 crore.
25suresh3.jpg

By end-August, it had already spent over Rs 27,000 crore. In the first quarter, the capital expenditure target was Rs 13,231 crore, which too was exceeded. It is widely acknowledged that capital expenditure plans are back-loaded because more money has to be spent in the latter half of the year as orders for procurement and commissioning of projects are placed in the first two quarters.
Not surprisingly, an estimated Rs 71,846 crore is budgeted to be spent in the last two quarters of the current financial year. The cycle of capital expenditure is such that efforts to show speedier disbursement of funds in the first two quarters may actually be counterproductive.
Indeed, the action on the ground seems to suggest that the Indian Railways is set to achieve the capital expenditure targets that were set at the start of the current financial year.
Major initiatives have already been taken to enhance the railways’ freight carrying capacity through modern and more efficient rolling stock. New wagons have been developed to provide 68 per cent higher throughput.
Additionally, coal-carrying wagons with indigenously designed axle load of 25 tonnes (against the current approved load of 20.3 tonnes) have been developed. This can result in even higher freight revenue than the 11 per cent growth seen in the first five months of 2015-16.
Two projects for manufacturing locomotives, languishing for over seven years, have seen renewed action in the last month or two.
The two factories in Bihar - one at Madhepura and other at Marhowrah - have been successfully bid out, entailing capital investments of Rs 3,500 crore, a bulk of which should be coming from the identified foreign investors by way of equity.


26train20.jpg

Already, nine port-connectivity projects have been implemented, thereby linking these ports with a railhead over a total distance of 1,030 kilometres.

Nine more such projects connecting railheads with other ports and coal mines are under implementation. The total investment in these 18 projects is estimated at Rs 12,600 crore.
Then there are plans for developing railway stations. Three stations — at Habibganj near Bhopal and Anand Vihar and Bijwasan (both in Delhi) are being bid out for development by private investors.


Four more are slated for next year. The new policy for redeveloping 400 major stations has also been finalised. The list can be much longer.

Yes, a few recent rail accidents have sullied his performance a bit. But the puzzle remains. Why, in spite of all these achievements, should Suresh Prabhu come under any scrutiny leading to suggestions that he may not have met some targets or he needs to move faster?

Is his non-BJP past playing a role here? Or is it his unconventional approach to steering the Indian Railways?

Railway Minister deserves credit for a stellar performance - Rediff.com Business
 
.
Great going prabhu. If he manages to invest 8.5lack cr in 5year ,it would transform railway completely.although the figures are to pessimistic I hope he he completed even 80 % of his promises.also I think gadkari is doing fine.
 
.
In the history of Indian railway budgets, Suresh Prabhu will perhaps be the first railway minister not to have announced either a single new train or a new railway line, notes A K Bhattacharya.
25suresh1.jpg
Suresh Prabhu, a recent entrant to the Bharatiya Janata Party (BJP), is yet to complete a year as the railway minister in the Narendra Modi government.

But in the period he has been at the helm at Rail Bhavan, he has managed to stay in the news - mostly for good reasons and of late for reasons he may not be very happy about.
His maiden railway budget had a string of creditable firsts to it. In the history of Indian railway budgets, he will perhaps be the first railway minister not to have announced either a single new train or a new railway line.
That must have taken a lot of courage. What he spurned as the railway minister was a political opportunity to nurture his or his party’s vote bank by showering goodies — one new train to connect his own constituency or a new railway track for the constituency of his boss.
He did nothing of that sort either for himself or for his boss and none for anybody else.
What he did instead was vitally important for the long-term health and viability of the Indian Railways.
26rail8.jpg

For far too many years has the Indian Railways been starved of the much-needed investments to enhance its capacity to grow as the country’s largest transporter of goods and people. In one stroke, he increased the capital expenditure plan for the Indian Railways by over 71 per cent to over Rs 1 lakh crore.
Not only that, he laid out a five-year capital investment plan of Rs 8.6 lakh crore, once again a first for a railway minister.
An innovative financing mechanism route was followed by Mr Prabhu to meet the target of investing Rs 1 lakh crore in projects to enhance the railways’ capacity in different areas.
This included a mix of higher budgetary support, internal resources generation, leveraging of balance sheets of public sector units under the Indian Railways, setting up of joint ventures with state governments and major customers and tying up with financial institutions to tap their resources
.
Even as India Inc wailed about the high cost of domestic funds, Mr Prabhu was not hobbled by such concerns.
28budget10.jpg

He tied up with the Life Insurance Corporation of India for low-cost institutional finance of Rs 1.5 lakh crore. This too was a first for Mr Prabhu.
The ambitious freight corridor project, critical for decongesting the tracks for faster movement of both passenger and goods trains, was moving at its own slow pace.
Under Mr Prabhu, this critical project got a big push. Between November 2014 and now, contracts for Rs 17,500 crore were finalised, compared to Rs 12,500-crore worth of cumulative contracts awarded between the project’s inception in 2006 and November 2014
. What’s more, contracts worth another Rs 17,000 crore are to be finalised by March 2016 and the phased commissioning of the project would start from 2018.
And yet there are suggestions that Mr Prabhu may not have met his quarterly targets for implementing projects, even though the achievements may be better than those in the same period of last year. The ground reality, however, is quite different.
According to the capital expenditure plan for the first two quarters of 2015-16, the Indian Railways was to spend a little over Rs 28,000 crore.
25suresh3.jpg

By end-August, it had already spent over Rs 27,000 crore. In the first quarter, the capital expenditure target was Rs 13,231 crore, which too was exceeded. It is widely acknowledged that capital expenditure plans are back-loaded because more money has to be spent in the latter half of the year as orders for procurement and commissioning of projects are placed in the first two quarters.
Not surprisingly, an estimated Rs 71,846 crore is budgeted to be spent in the last two quarters of the current financial year. The cycle of capital expenditure is such that efforts to show speedier disbursement of funds in the first two quarters may actually be counterproductive.
Indeed, the action on the ground seems to suggest that the Indian Railways is set to achieve the capital expenditure targets that were set at the start of the current financial year.
Major initiatives have already been taken to enhance the railways’ freight carrying capacity through modern and more efficient rolling stock. New wagons have been developed to provide 68 per cent higher throughput.
Additionally, coal-carrying wagons with indigenously designed axle load of 25 tonnes (against the current approved load of 20.3 tonnes) have been developed. This can result in even higher freight revenue than the 11 per cent growth seen in the first five months of 2015-16.
Two projects for manufacturing locomotives, languishing for over seven years, have seen renewed action in the last month or two.
The two factories in Bihar - one at Madhepura and other at Marhowrah - have been successfully bid out, entailing capital investments of Rs 3,500 crore, a bulk of which should be coming from the identified foreign investors by way of equity.


26train20.jpg

Already, nine port-connectivity projects have been implemented, thereby linking these ports with a railhead over a total distance of 1,030 kilometres.

Nine more such projects connecting railheads with other ports and coal mines are under implementation. The total investment in these 18 projects is estimated at Rs 12,600 crore.
Then there are plans for developing railway stations. Three stations — at Habibganj near Bhopal and Anand Vihar and Bijwasan (both in Delhi) are being bid out for development by private investors.


Four more are slated for next year. The new policy for redeveloping 400 major stations has also been finalised. The list can be much longer.

Yes, a few recent rail accidents have sullied his performance a bit. But the puzzle remains. Why, in spite of all these achievements, should Suresh Prabhu come under any scrutiny leading to suggestions that he may not have met some targets or he needs to move faster?

Is his non-BJP past playing a role here? Or is it his unconventional approach to steering the Indian Railways?

Railway Minister deserves credit for a stellar performance - Rediff.com Business

Even if he managed to achieve 50% of the target then the railways will be transformed
 
. .
He and Manoj Sinha both are great guys and doing fine. Perrikar, Gadkari, Piyush Goyal, Suresh Prabhu, Sushma swaraj and Rajnath Singh these guys are doing great with their respective ministries. Hope Jeitely and others will follow them too(though Jeitely's average performance is understandable as many reforms are blocked in parliament but then its their job to clear it)
 
. . . . .
2024-25 may be?
from economic times(cant post link)
NEW DELHI: India's maiden bullet train corridor between Mumbai and Ahmedabad will cost nearly Rs one lakh crore and the first train can run in 2024 if work begins in 2017, according to a final feasibility report on the project prepared by the Japanese governmental agency.

The Japan International Cooperation Agency(JICA) in its report submitted to the Railway Ministy today envisages a reduction in the travel time on the 505-km long corridor between the two western cities to two hours from the existing over seven hours.

The report estimates that the project where the bullet train will run at a speed of over 300 km per hour will cost Rs 98,805 crore. It also suggested that the train fare could be higher than that charged for First AC of Rajdhani Express, a senior rail ministry official involved with the project said.

Japanese Ambassador to India Takeshi Yagi led the official JICA delegation to submit the report to Railway Minister Suresh Prabhu on the bullet corridor that is considered Prime Minister Narendra Modi's pet project.

Railways will examine the report and decide the future course of action, the official said.

As a follow-up action, a Cabinet note seeking approval for the project with an outline of the project feasibility and timelines is likely to be prepared next month.

If work begins in 2017, the line can be completed in 2023 and made operational in 2024, it is projected.

After the study of the financial feasibility of the line, the final report suggests the fare of the bullet train between Mumbai and Ahmedabad may be somewhere around one and half times more than the fare of the first AC of Rajdhani Express and it would be around Rs 2,800.

It is estimated that by 2023 around 40,000 passengers are expected to avail this service everyday and accordingly it would be a financially viable service.

Besides JICA, SNFC of France has already carried out a feasibility study of the route and has submitted the business model to the ministry.

The Mumbai-Ahmedabad corridor is expected to enable trains to run at a top speed of 350 kmph.

From the initial estimated cost of Rs 65,000 crore, it has gone up after taking into account various factors like price escalation and interest.

According to the official, Japanese government has offered to fund the project at a low interest rate. However, the loan offer comes with the rider that 30 per cent of the rolling stock for the project would be sourced from Japanese firms.

The Japanese agency has suggested that the line be constructed on the internationally accepted "standard gauge", as against certain opinion in the Railways that the "broad gauge" option be considered since India's main line train operation is based on this gauge only.

JICA's final report points out that high-speed running of over 300 kmph are done on the standard gauge across the world.

In his budget speech in March, Prabhu had said that "quick and appropriate action" on executing the high-speed project would be initiated after the submission of the JICA's final report
 
.
Really Appreciable Performances but What about Strategic rail Line along the China Border. I think it is becoming more serious issue day by day!
 
.
Yes, a few recent rail accidents have sullied his performance a bit. But the puzzle remains. Why, in spite of all these achievements, should Suresh Prabhu come under any scrutiny leading to suggestions that he may not have met some targets or he needs to move faster?

Much scope for improvement though - Recently a letter from the PMO referred to a "less than satisfactory performance" in some areas. That includes -

>> Slow progress of projects such as station development (including services like WiFi) and high-speed services (HSR and Semi-HSR roll out).

>> Low budgetary spending in the April-June quarter, which reflected poorly on the railways when set against the record of other departments such as Nitin Gadkari's roads ministry and the overall record of the government. The railways had spent about a fifth of the Rs 40,000 crore allotted as budgetary support in the first quarter. That compares with 25% in the year earlier period.

Previously, the railway ministry has been queried on progress of the Dedicated Freight Corridor (DFC) and whether it had decided on the projects to be funded through a Rs 1.5 lakh crore loan from Life Insurance Corp of India (LIC) agreed to in March. The memorandum of understanding with LIC calls for a five-year funding plan with the first tranche of Rs 20,000 crore to be made available in the current fiscal year.

Failed god of railways? PMO raps Suresh Prabhu's pace of work - timesofindia-economictimes
 
.
One thing that differentiates Prabhu from his predecessors is his ability to not indulge in populism. One RM after other followed the trend of starting trains (or introducing trains classes) like Jan Shatabdis, Durontos etc etc without giving a two hoot on improving or upgrading track infra structure first. The Result today almost all routes are operate way over their saturation limits, giving little time for upkeep of tracks, OHE and signalling leading to accidents.
2 (1).png

Prabhu has had courage of trying to understand this problem and concentrate of generation of revenue streams for safety and capacity upgrades. PM has given him a free hand and his credentials as a banker make him the best person to bring railways out of this precarious position.
& to his credit he has fast tracked several decisions like HHP (6000 HP) Diesel factory tender, 12000 HP Electric loco factory (for DFC), getting in talks with LIC to invest 1,50,000 Crores (spread over next 10 years) in railways, fast tracking DFCIL tenders.
IMHO he is on right track, hopefully so shall be Indian Railways in next 5-6 years.
 
Last edited:
.
THis guy is literally awesome, turned the railways around, stations are clean, food is better, trains are clean, even the tracks are considerably cleaner( thought not entirely due to the people going to bathrooms in railway stations)
 
.
I travel regularly in trains between Roorkee-Najibabad and sorry to say but the average delay time has risen from 1 hour to 2 hour in last one year.
 
.