What's new

Hydro power plants updates

40.8 MW KOTO HYDROPOWER PROJECT , KPK...


1639002597803.png
 
. .

800MW Mohmand Dam – Construction of Diversion Tunnels


An important structure for construction of main dam, the total length of the Diversion Tunnel 1&2 is more than 3000m. Due to large diameter (15m), the excavation was divided into three layers (heading, benching & invert). Both tunnels are being excavated from multiple work fronts and some sections breakthrough with each other.

An important structure for the construction of main dam, the total length of the Diversion Tunnel 1&2 is more than 3000m. Due to large diameter (15m), the excavation was divided into three layers (heading, benching & invert). Both tunnels are being excavated from multiple work fronts and some sections breakthrough with each other.



1639437348133.png





1639437368203.png




1639437388880.png
 
. .
1640302420285.png




On December 21, the signing ceremony of the Take-over Certificate (TOC-10) for the Neelum-Jhelum Hydropower Station Project was held in Islamabad.

As the contractor of the civil construction part, #EnergyChina’s China Gezhouba Group overcame a series of world-class difficulties such as constructing in the deepest surge shaft in Asia, crossing the Himalayan fault zone, etc. After more than ten years of construction, the company had completed its mission perfectly.

total installed capacity of the NJ project is 969 MW, and the annual electricity generation is 5.15 billion kWh, which accounted for 12% of the hydropower generation in Pakistan and it will solve the problem of electricity shortage for 15% of Pakistan’s population, providing the clean energy at a low price to the local people.


1640302444467.png





1640302465846.png
 
.

Tarbela 5th Extension project - 1,530MW


• 03 generating units of 510MW each
• Commenced in August, 2021
• Completion Date: Mid-2024
• 1.347 billion units of low-cost hydel electricity
• Commenced in August 2021capacity at Tarbela Dam will increase
 
.
Suki Kinari Hydropower Project, a CPEC clean energy project, achieved the breakthrough from A6b to A7a in Headrace Tunnel.


1640875786916.png





1640875823483.png
 
.
Jagran-II Hydropower Project (JHPP-II)

View of Powerhouse after the snowfall.

1640962130271.png


Under Construction civil works including weir, 5 km long tunnels, Surge Tank, Vertical Shafts and a Power house.

The project is expected to be completed by 2022.
 
. .
Khyber Pakhtunkhwa (KP) government has decided to construct three new dams in Tank and Dera Ismail Khan districts to refill the ground water level.


1641303587217.png
 
. . .
The 267-meter long temporary Cableway Bridge, with weight bearing capacity of 80 tons, completed yesterday on River Indus downstream of Main Dam site of Diamer Basha Dam Project for transportation of heavy machinery and construction material from the left bank to the right bank for acceleration of construction activities on the Project.

The three Cableway Bridges, upstream of the Main Dam site, are already operational to expedite the construction work.

Credits: Engr. Awais


1643497082666.png




1643497121392.png
 
. . .

Latest posts

Back
Top Bottom