What's new

Energy Projects...Updates

1223 MW Balloki Power Plant Under Construction near Pattoki. This power plant is based on RLNG (Natural Gas) expected to be completed at the end of the current year.

17499079_1127698334024530_8338699077742133892_n.jpg



17426155_1127698507357846_1851663876583578309_n.jpg


Pakistan's Khyber Pakhtunkhwa Province signs Memorandum of Understanding for 610 Megawatts Hydropower Project with Chinese Sinohydro Company.


17505362_1126405404153823_3365039576678370910_o.jpg
 
.
Pakistan’s Karot Dam reaches $1.7b financial close

China Three Gorges South Asia Investment Limited said Friday (March 31), that it has achieved a financial close on the $1.7 billion 720-megawatt Karot hydroelectric power project and the second phase of a 100MW wind power project, from a group of Chinese investors and the International Finance Corporation (IFC).

This is also marked as the first infrastructure deal under China’s One Belt One Road initiative. Other investors include Export-Import Bank of China, China Development Bank and Silk Road Fund.
 
.
370MW added to national grid Bhikki power splant

LAHORE - Over 370MW has been added to the national grid after the second turbine of the 1,180MW Re-Gasified Liquefied Natural Gas fired thermal power plant at Bhikki (Sheikhupura) started generation on trial basis.

Before this, the test run of the plant’s first turbine had been started successfully on March 11, adding about 400MW to the national grid. According to the Ministry of Water and Power, the LNG based Bhikki power plant in Sheikhupura has an overall capacity of generating 1,180MW of electricity. The plant will save Rs 100 billion to the national exchequer. The Bhikki power plant is part of the government's consolidated strategy to overcome power shortage.

According to the ministry, there will be huge addition in power generation as Chashma-3, Chashma-4, Tarbela-4 and alternative energy resources power plants including wind and solar will be completed in the near future. The ministry said work on power plants and transmission lines is being done at fast pace.

The trial generation of the plant’s second turbine was started during late Thursday night. “The turbine was operated on full scale and it touched a figure of 400MW. Later, its operation was observed to be stabled at 372MW on early Friday morning and finally it was synchronised with the national grid,” Quaid-e-Azam Thermal Power (Private) Limited Chief Executive Officer Ahad Khan Cheema said.

He said that like the first turbine, the second turbine’s trial operation will be examined on technical grounds through tests and protocols etc, as it would not be run on a regular basis in coming days. And this process will continue for next couple of weeks, he added. Cheema said turbine’s trial power generation was in simple cycle mode and it would increase once it started generation in combine cycle mode after installation and trial operation of the third turbine (called steam turbine).

He said the regular operation of the two turbines would initially generate 750MW and it will gradually increase to 780MW or so. And after installation and operation of the third turbine, the combine cycle operation of the total three turbines will be completed, enabling the plant to generate about 1180MW. “In such situation, each turbine will generate over 393MW,” he explained.

He said the Bhikki project was expected to be completed by December, this year as per deadline fixed by the government. “Since we are meeting our timeline in every aspect related to this project, it will really be a record if we succeed in accomplishing this mega project by December, this year,” he added.

Energy experts said that Water and Power Development Authority would add around 2,485 megawatts by the next year after the completion of three hydropower projects. The projects are expected to complete between this year-end and the mid of 2018. The projects include 969MW-Neelum Jhelum hydropower plants, 1,410MW-Tarbela 4th extension and 106MW-Golen Gol hydropower plants.

Wapda projects were marred with delays due to certain reasons and missed timelines of their completion. First unit of Tarbela 4th extension will be completed by end of this year, while two remaining units will be ready during the high water flow season in 2018. Likewise, first unit of Neelum Jhelum hydropower project will start electricity generation by February next year, second unit in mid March and the third and fourth units will be completed in April 2018.

Similarly, first unit of Golen Gol hydropower project will be inaugurated in December this year, while overall completion of the project is scheduled in August 2018. Kachhi canal project is being completed in phased manner. The issue of land acquisition for Dasu hydropower project, which had been lingering for the last two years, has finally been resolved with the signing of an agreement with 80-member Jirga of the local notables of Kohistan district in December 2016 for smooth and speedy land acquisition.
user_online.gif
 
. . .
Port Qasim Coal Power Plant | 1320 MW

17861708_1136300743164289_2489337437483158719_n.jpg
 
.
Boiler startup test 1320 MW Sahiwal coal power plant.

C9jtT3oUIAAX8m-.jpg


Reliability Run Test (RTR) and Initial Capacity Test of Gas Turbine #2 Completed successfully.Great milestone achieved ... !!!

First phase of the 1200 MW Bhikki power plant would be completed in two weeks that would produce 800 MW electricity.


1672044724b3aa6002d0f2224744f6ab.jpg
 
.
Following major projects (8,991 MW) will come online by election next year:
2018...

1) Sahiwal 1,320 MW
2) Port Qasim 1,320 MW
3) Bhikki 1,180 MW
4) Balloki 1,223 MW
5) Haveli Bahadur Shah 1,230 MW
6) Tarbela-IV 1,410 MW
7) Neelum–Jhelum 968 MW
8) C-4 340 MW

Total................ 8,991 MW

..............................................................

Following projects will come online during 2018-23:


1) Dasu-1 2,160 MW
2) Suki Kinari 870 MW
3) Kohala 1,124 MW
4) KANUPP-2 & 3 2,200 MW
5) Muzaffargarh RLNG 1,200 MW
6) RYK Coal Power Plant 1,320 MW
7) HUBCO 1,320 MW
8) CASA 1,000 MW
9) Sindh Engro 1,320 MW
10) Thalnova 330 MW
11) Siddiqsons 350 MW
12) K-Electric 700 MW
13) Jamshoro 600 MW
14) Oracle (Thar) 1,320 MW
15) Thar Coal 1,320 MW
16) Tarbela-V 1,320 MW
17) HUBCO Thar 330 MW


Total 18,784 MW

By 2030:

1) A total of 20,000 MW will be eventually produced in Thar Coal fields alone.
2) Nuclear capacity would be increased to 8,800 MW.
3) In hydro, following projects would be done:

- Thakot 4,000 MW
- Bunji 7,100 MW
- Basha 4,500 MW
- Dasu-II 2,160 MW
- Patan 2,400 MW

Total 20,160 MW
 
. .
PM Nawaz to inaugurate Bhikki Power Plant today

The Prime Minister will inaugurate Bhikki Power Plant at 3:00pm today.

ISLAMABAD (Dunya News) - Prime Minister Nawaz Sharif will inaugurate Bhikki Power Plant today (Wednesday) for which preparations have been started, Dunya News reported.

The Bhikki Power Plant’ inauguration had been scheduled for April 20 (Friday) but now work in underway on emergency basis for the inauguration of the power plant today.

The Prime Minister is scheduled to inaugurate Bhikki Power Plant at 3:00pm today.
 
.
So by 2030 Pakistan will be producing 49,935 MW of electricity (that is almost 50,000 MW), that is in merely 13 years from now.. Way to go Pakistan..
 
.
is there any updates regarding Jamshoro Coal power plant?
 
. . . .

Pakistan Affairs Latest Posts

Back
Top Bottom