What's new

Energy Projects...Updates

Sahiwal coal plant

18581644_1418299054890268_3122224500810003272_n.jpg




18581958_1418299074890266_761968688427657771_n.jpg




18620122_1418299101556930_4219186640534333308_n.jpg

_
 
. . . .
Balloki Power Plant ..... 1223 MW


18767430_1187881264672903_5810940509148482272_n.jpg



18740282_1187881228006240_4838937067308164695_n.jpg




18740568_1187881134672916_9066822417907962147_n.jpg




18813147_1187881131339583_6859084853988414167_n.jpg




18814040_1187881238006239_2992396401577842448_n.jpg




18740447_1187881304672899_4185159429066590473_n.jpg




18813351_1187881271339569_3778933336958306075_n.jpg



9HA Gas Turbine being installed at the Balloki Power Plant near Pattoki, Punjab.



DBJSqyBXkAAXTr2.jpg





DBJropOWsAEBsWk.jpg




DBJSquGXgAE12lp.jpg


DBJSqxwXUAAecNJ.jpg

_
 
. . . . .
Brother, Can you tell me what is in those 2 tanks?! is it Diesel for backup if LNG runs low?

Diesel tanks.

The World’s Largest Gas Turbines Will Light Up Pakistan

Each one weighs nearly 400 tons, as much as two really big blue whales. Each one will cover thousands of miles by sea and land from the place of their birth in Belfort, France, to the farming town of Bhikki in Pakistan’s Punjab province. They are still fairly unknown, but once they reach their destination, they will affect millions of lives.

The giants that will be making their way to Asia are a pair of GE’s air-cooled 9HA gas turbines, the largest and most efficient gas turbines on the planet today. They’re capable of delivering greater than 61 percent efficiency – once the power-generation equivalent of running a four-minute mile – when used in a combined cycle configuration with steam turbines. They will become the beating heart of the Bhikki Combined Cycle Power electricity generation plant that’s being built by China’s Harbin Electric International for Punjab government’s Quaid-e-Azam Thermal Power Ltd. utility.

9HA_Gas_Turbine_connected_to_drive_train_inside_GE-s_validation_test_stand-1-1024x683.jpg

Top: Workers are assembling the first 9HA turbine at the GE plant in Belfort, France. Above: The first 9HA gas turbine started powering through tests last year in Greenville, S.C. Images credit: GE Power & Water


9HA_Gas_Turbine_HArriet_being_aligned_into_its_final_position-11-1024x683.jpg

The first 9HA turbine arrived in Greenville, S.C., for testing in 2014. Image credit: GE Power & Water


GE-9H-Gas-Turbine_PSP31369-1492-682x1024.jpg


A 9HA.01 gas turbine with its rotor on “half-shell” in Belfort, France.


It uses technology originally developed for supersonic jet engines. GE refers to this practice of sharing knowledge among different businesses the GE Store.

The turbine can reach full load in a mere 10 minutes – just a little longer than a plane getting ready to take off – and also offers the flexibility to run on a range of gas and liquid fuels. This is critical for fuel-importing countries such as Pakistan.

The two units at Bhikki will be operated on imported “re-gasified” liquefied natural gas (RLNG), but will be able to use substitute fuels if price or availability of RLNG starts to fluctuate.
 
.
Diesel tanks.

The World’s Largest Gas Turbines Will Light Up Pakistan

Each one weighs nearly 400 tons, as much as two really big blue whales. Each one will cover thousands of miles by sea and land from the place of their birth in Belfort, France, to the farming town of Bhikki in Pakistan’s Punjab province. They are still fairly unknown, but once they reach their destination, they will affect millions of lives.

The giants that will be making their way to Asia are a pair of GE’s air-cooled 9HA gas turbines, the largest and most efficient gas turbines on the planet today. They’re capable of delivering greater than 61 percent efficiency – once the power-generation equivalent of running a four-minute mile – when used in a combined cycle configuration with steam turbines. They will become the beating heart of the Bhikki Combined Cycle Power electricity generation plant that’s being built by China’s Harbin Electric International for Punjab government’s Quaid-e-Azam Thermal Power Ltd. utility.

9HA_Gas_Turbine_connected_to_drive_train_inside_GE-s_validation_test_stand-1-1024x683.jpg

Top: Workers are assembling the first 9HA turbine at the GE plant in Belfort, France. Above: The first 9HA gas turbine started powering through tests last year in Greenville, S.C. Images credit: GE Power & Water


9HA_Gas_Turbine_HArriet_being_aligned_into_its_final_position-11-1024x683.jpg

The first 9HA turbine arrived in Greenville, S.C., for testing in 2014. Image credit: GE Power & Water


GE-9H-Gas-Turbine_PSP31369-1492-682x1024.jpg


A 9HA.01 gas turbine with its rotor on “half-shell” in Belfort, France.


It uses technology originally developed for supersonic jet engines. GE refers to this practice of sharing knowledge among different businesses the GE Store.

The turbine can reach full load in a mere 10 minutes – just a little longer than a plane getting ready to take off – and also offers the flexibility to run on a range of gas and liquid fuels. This is critical for fuel-importing countries such as Pakistan.

The two units at Bhikki will be operated on imported “re-gasified” liquefied natural gas (RLNG), but will be able to use substitute fuels if price or availability of RLNG starts to fluctuate.

thank you ghazi for always updating theses threads ..:-)
 
.
Generation 19244MW but 0MW from solar and 0 from Bhikki. What about Bahawalpur solar park? Is government fooling Pakistani people? And what about Bhikki plant which was inaugurated last month?


DBaBshgXUAATFp5.jpg:large
 
.
Generation 19244MW but 0MW from solar and 0 from Bhikki. What about Bahawalpur solar park? Is government fooling Pakistani people? And what about Bhikki plant which was inaugurated last month?


DBaBshgXUAATFp5.jpg:large
Bhaiya, how can solar generate at night time? please have a look at the screen shot it say's "19:47".

Rest of your questions should be addressed by the person with the latest upto date news.
 
. . .

Latest posts