China Pakistan Economic Corridor (CPEC) | Power Plants

It is a royal shame that a lot of the leadership functions for the CPEC projects are chinese companies, with Chinese managers ,etc.. This opportunity represented to train a new leadership class of managers and create new organisations who can initiate, manage, and deliver projects of this size and scale, internally, within Pakistan. I do fear, Pakistan has missed out on this alot..

CPEC should not have been treated as a means of getting specific projects done in Pakistan, but also a chance to create new organisations in Pakistan that are capable enough to do these projects in Pakistan.

This would mean, that newer projects of this size can be done in Pakistan that are much cheaper to do, then doing them via China ....
 
.
DG FWO visited and inspected the progress and pace of the work of Diamer Basha Dam on 30 December 2020. Base camp and site offices have been established at the site recently. Work on connecting roads to dam site and construction of temporary / permanent bridges is ongoing.
Courtesy: FWO



1609513057648.png
 
. .
New Day, New year & another New Milestone Marked at 884MW Suki Kinari Hydropower Project.
Out of six pressure shafts, 3rd pressure shaft drilling has been commenced today.



1609527706916.png




1609527756778.png





1609527803955.png
 
. . .
The first breakthrough of Suki Kinari Hydropower Project Headrace tunnel took place today.

More than 23 Km long headrace tunnel is being excavated through different access Adits/Tunnels. Both tunnel sections breakthrough with high-accuracy alignment. To celebrate this important milestone, a ceremony was held at construction site and all stakeholders participated.



1610122339228.png






1610122378431.png
 
.
Suki Kinari Hydropower Project | Construction Progress | Jan, 2021

•Jan 11, 2021



 
.
Gas Turbine Arrived at Under Construction Bin Qasim Power Station 3 (BQPS3) 900 Megawatts RLNG power plant By K Electric and Harbin Electric at Port Qasim Karachi
 
. . . .
Dasu-KKH-01, is worth Rs 14.538 billion and relates to the relocation of the 25-km stretch of the KKH.
Uchar Bridge access road from both abutment is in progress.
It is one of the longest bridge (350+ m).



1611064140738.png




1611064187114.png
 
.
Lahore-Matiari transmission line to be ready by April

https://nation.com.pk/NewsSource/app
APP
January 24, 2021


ISLAMABAD - Pakistan’s first and mega High Voltage Direct Current (HVDC) project, Lahore-Matiari transmission line, will be ready by April.

According to official sources, the project, launched under the China-Pakistan Economic Corridor (CPEC), would cost $ 1.68 billion and was the first HVDC project in the country and the second in the entire world.

They said the project would help evacuate 4,000MW power from plants in south to urban load centres in Punjab.

Work on the project was launched in December, 2018 across Sindh and Punjab, they said.

The transmission line was divided into eight lots, crossing desert, farmland, rivers, military area, national park, wildlife reserves gas pipelines, railways, highways, and several 500kV, 220kV, 132kV transmission lines on the way.

Regarding other investment in the transmission lines, they said no investment was made on up-gradation of transmission lines in past.

The government has invested over Rs 49 billion on upgradation of the transmission lines in last 2 years.
The sources said owing to the huge investment in last two years, the transmission lines could transmit over 23000 MW in last summer for the first time.

Similarly, they said investment was also being carried out on up-gradation of 220 kV and 132 kV transmission lines. Anti-fog insulators were installed on the transmission system during the last two years, they added.
 
.
Under Construction

Dasu Hydropower Project ......(4320MW)

1611600896828.png






1611600878738.png
 
.