What's new

Biggest Pakistan Fuel Importer Plans $6 Billion Crude Refinery

Saifullah Sani

SENIOR MEMBER
Joined
Apr 15, 2011
Messages
3,339
Reaction score
2
Country
Pakistan
Location
Pakistan



    • Seeks partners for nation's largest oil processing facility
    • South Asia's No. 2 economy imports half the fuel it needs
Pakistan State Oil Co., the nation’s biggest importer of petroleum products, plans to build a refinery for as much as $6 billion to expand into processing crude.
The nation’s biggest company by revenue is looking for partners to help build a plant to process 200,000 to 250,000 barrels a day of oil, Chief Executive Officer Sheikh Imran ul Haque said in an interview in Karachi, making this the nation’s largest refinery. He didn’t elaborate on how the company will finance the plant or give a timeline for the project as it is at an initial stage.



    • Pakistan State Oil would like to “reverse the role,” and refine crude rather than import fuel, Haque said. “We are nowhere. We need to diversify.”
The size of the refinery means Pakistan State Oil will produce about 12 million tons of fuel, similar to the amount the nation imported in the year ended July 31, and will mark a drastic change in the company’s business model. The plan will also help the country, that’s trying to meet revenue targets tied to an International Monetary Fund loan, save on foreign exchange.
488x-1.png

“It’s a gigantic task to set up such a large refinery in Pakistan,” Fatiq Bin Khursheed, analyst at Optimus Capital Management Pvt. said by phone. “Usually such big refineries are found in countries where there is local supply of crude but this will rely on imports and raising funds will not be easy.”
Pakistan spent about a third of its foreign reserves on fuel imports in the year that started July 1, according to government data.
This is not the first time Pakistan State Oil has proposed building a refinery. In 2012, Pakistan State Oil said it planned to build a $750 million crude processor in Khyber-Pakhtunkhwa province by 2016.
The company’s shares have risen 16.5 percent this year. They rose 1.2 percent to 378.84 rupees on Thursday. Pakistan State Oil reported a loss of 2.1 billion rupees ($20 million) in the three months ended March 31, it’s biggest in almost nine years.
Pakistan has five refineries including those run by Byco Industries Inc., which has a capacity to process 155,000 barrels a day of crude and Pak-Arab Refinery Ltd. with 100,000 barrels a day, according to the companies’ websites. China National Petroleum Corp.’s subsidiary is also keen to set up one, according to The Express Tribune.
Storage Capacity


Pakistan State Oil also plans to invest $100 million to double storage capacity of petrol and diesel reserves in a bid to avert the kind of fuel shortages witnessed last year. It also plans to import directly from Middle East state-owned refineries rather than open tenders, and seeks to find a partner before year-end to revive its lubricant business.
“My job is to lay the foundation” for these projects, Haque said. “I have a three-year contract and can only do so much,” said Haque, who joined the company in September.
Pakistan’s Prime Minister Nawaz Sharif started importing liquefied natural gas last year and plans to add coal power plants to end a power crisis by 2018, before the next election cycle. The government expects the nation’s economy to grow 5 percent in the year ending July, the fastest pace in eight years, and accelerating to 7 percent in 2018.
http://www.bloomberg.com/news/artic...-fuel-importer-plans-6-billion-crude-refinery
 
.
Another big refinery will be a positive development for our nation. It makes sense to import only crude oil and refine it ourselves. I hope it will certainly save some foreign exchange for other uses.
 
.
It makes sense to import only crude oil and refine it ourselves.

True, but what make more sense is to build dams and convert everything on electricity. From Trains, cars to household things like heaters and cooking ranges.We are giving away 1/3 of our total money to foreign countries. Other than Airlines and military equipment, nothing should be on oil and gas that we can't produce.


Pakistan spent about a third of its foreign reserves on fuel imports
 
.
True, but what make more sense is to build dams and convert everything on electricity. From Trains, cars to household things like heaters and cooking ranges.We are giving away 1/3 of our total money to foreign countries. Other than Airlines and military equipment, nothing should be on oil and gas that we can't produce.
Well said. Dams have been neglected by our government. Allah has given us rivers, mountains and plenty of places to build dams. Dams do require a high initial construction cost but they pay for themselves in a few years and the rest is bonus. It is up to people in power to take the decision.
 
.
200K bbl. per day equals 10-million tons per year. To produce 12-millions of fuel products refinery has to be of at least 250 K bbl. per day (12.5-million tons) nameplate capacity.

It would take a 3 to 5 years lead time for the project to complete. Oil demand normally grows at half of the GDP. Assuming a modest annual growth of 5% in GDP, 2.5% growth would push product deficit close to 13.5 -million tons by the time refinery is complete. Don’t you think it is incorrect ignore future growth at the plant planning stage? Life span of a refinery is 20 to 30 years. One would expect the projected refinery to be of about 400 K bbl. per day (20-million tons) to take care of Pakistan imports needs for the next 10 years or so. However estimated cost of $6-billion suggests capacity to be around 250K bbl. per day.

For the general info; standard size of a new refinery these days is about 400 K bbl. per day and a complex refinery with upgrading facilities such as Yasref (Yanbu Aramco Sinopec refining Co.) which just came on stream was originally forecast at $8.5-billion, however actual cost came close $10-billion.
 
.

Pakistan Defence Latest Posts

Pakistan Affairs Latest Posts

Back
Top Bottom