Dasu Hydropower Project (DHP), .... 4,320 MW

March 25, 2021: Pakistan Water and Power Development Authority (WAPDA) Chairman Lt Gen Muzammil Hussain (Retd) today visited Diamer Basha Dam and Dasu Hydropower Project to review construction work on the two mega projects.

During his visit to Diamer Basha Dam being constructed on River Indus downstream of Chilas town in Gilgit Baltistan, the Chairman was briefed that construction work on as many as 8 different sites in project area is underway. The construction sites included access tunnel, access roads, upstream and downstream cable bridges. The construction work on 21 MW Tangir Hydropower Project, meant for providing electricity during construction phase of Diamer Basha Dam, has also commenced, it was further briefed.

The Chairman also opened the newly constructed cable way bridge across River Indus. Rest of three such bridges are scheduled to be completed in April and May one after the other for swift mobilization on both banks of the River during high flow season. Pontoon bridge across the River Indus had already been completed ahead of schedule in December last year to facilitate mobilization of machinery and workforce during the current low flow season.

Diamer Basha Dam will have a gross water storage capacity of 8.1 MAF to irrigate 1.23 million acres of additional land. With installed power generation capacity of 4500 MW, the project will provide more than 18 billion units per annum to the National Grid.

Earlier, WAPDA Chairman also witnessed construction activities on Dasu Hydropower Project Stage-I, being built across River Indus upstream Dasu town in Kohistan District of Khyber Pakhtunkhwa. During a briefing about progress on the project, the Chairman was apprised that construction work on 9 different sites is in progress. It was briefed that river diversion works are expected to be completed by end of this year.

Afterwards, the mighty Indus would pass through the two diversion tunnels paving the way to constructing the Main Dam. The Chairman reviewed construction work on diversion tunnels and power house during the visit.

The 4320 MW-Dasu Hydropower Project will be completed in two stages. At present, WAPDA is working on 2160 MW-Stage-I, likely to be completed in 2025. The Stage-I will provide 12 billion green and low-cost electricity to the National Grid annually while the Stage-II will also contribute another 9 billion units to the system per annum.


1616693243861.png
 
1619359470396.png




Under Construction Dasu Hydropower Project - 4320MW (First Stage: 2,160MW)
Concrete works at the inlet of Diversion Tunnel B is in progress.
Credits: Engr. Asim



1619359529790.png
 
Inaugurations Ceremony of RAR-2 under Dasu Hydropower Project was held at Construction Site.

It is pertinent to mention here that 1.6km RAR-01 had already been completed and inaugurated on 13 May, 2020.


1622035143331.png




1622035194520.png
 
Dasu Hydropower Project - 4,320MW
The Excavation of Underground Powerhouse is in Progress. The dimension of cavern is 424m x 31m x 62m (LxWxH).



1622114549060.png





1622114600971.png
 
Prime Minister Imran Khan will visit Dasu Dam today.

Prime Minister will review the ongoing construction work at Dasu Dam.
Dasu Dam phase one will be completed in 2025 and start supplying 2160 mega watts to national grid. Dam phase two will be completed in 2029 and start supplying 4320 mega watts. The construction of the dam is going on while implementing the SOPs despite the Corona epidemic.

On this occasion, the Prime Minister will also talk to foreign engineers and workers working on the dam.


1624029981867.png
 
Under Construction 4320 MW Dasu Hydropower Project.

Dasu Dam Stage 1 Completion: 2025
Power Generation of stage 1: 2160 MW