What's new

Wapda cancels Rs5.4bn contracts for Dasu project with a Chinese firm

Devil Soul

ELITE MEMBER
Joined
Jun 28, 2010
Messages
22,931
Reaction score
45
Country
Pakistan
Location
Pakistan
Wapda cancels Rs5.4bn contracts for Dasu project
KHALEEQ KIANI — UPDATED about 3 hours ago
WHATSAPP
46 COMMENTS
PRINT
ISLAMABAD: Even before the formal launch of $4.5 billion Dasu hydropower project, the Water and Power Development Authority (Wapda) has terminated two of its key contracts with a Chinese firm, citing ‘fundamental breaches’ of the agreement.

Moving swiftly, Wapda has not only encashed the performance guarantees of the two contracts awarded to China Railway First Group (CRFG) in November 2015 — worth Rs5.4bn — but also ordered the contractor to vacate the project area immediately, while calling for fresh tenders to make up for lost time.


The World Bank is the major financier of the 4,320MW Dasu project. The project’s terminated contracts include the ‘construction of colony and infrastructure’ worth Rs4.806bn and ‘resettlement of village Choochang and construction of Shatial Museum’ worth Rs572 million.

Chinese firm accuses authority of acting illegally, vows to seek arbitration
The completion of these two components was considered crucial to the start of construction work at the main project site.

Also read: Hydropower projects: aiding investment

CRFG project director Fan Lingang told Dawn: “The termination of the contract is un-contractual, illegal and fiercely unfair.” He claimed it was Wapda’s responsibility to complete the land acquisition process and hand over the required area to the contractor, adding that all Dasu contracts were suffering due to its default.

In reply to a set of questions sent to Wapda chairman retired Lt Gen Muzammil Hussain, the authority said it had “provided the partial possession of the site to the contractor M/s CRFG in line with the Contract Discussion Agreement/Conditions of the Contracts”.

Asked if the World Bank had indicated that it would take any action, such as loan cancellation or postponement because of project delays, Wapda said: “There is no such indication from the World Bank”.

“We are going to approach the local courts to allow us to approach an international court of arbitration to protect our rights because Wapda is not willing to resolve [the issue] amicably,” Mr Fan said, adding: “Arbitration is our right and we have to protect ourselves, not only financially but also our reputation and image.”

He maintained that his firm would “complain to the World Bank as well”. Mr Fan said the company had mobilised 30 staffers to the project site, but conceded that practically no work was done because of Wapda’s inability to settle land disputes with locals. “Wapda is the defaulter because it didn’t provide the land. The contractor actually had the right to terminate the contract, but it didn’t.”

He claimed that the contract had been terminated without prior legal notice and without being provided the opportunity to rectify any violation, if any, by the contractor. He said Wapda had blamed the CRFG for subletting the contract to a Lahore-based blacklisted company in order to terminate the contract, even though the former was not a legal contract.

The authority, however, defended its decision, saying: “The contracts were terminated due to fundamental breaches of the contract by the contractors. In these circumstances, no legal notice was required to be served on the contractor to rectify under the conditions of the contracts.”

Mr Fan explained that “a cooperation agreement” was signed with a local firm before the bidding took place as “a matter of comfort”. This, he said, was cancelled when it was pointed out by Wapda and the project consultants, long before the authority terminated the contract.

He called Wapda’s encashment of securities and refund of the mobilisation advance a case of fraudulent practice, misrepresentation and use of influence.

In response to CRFG’s claims, Wapda maintained that it “issued the notice of termination and lodged the claim for the encashment of the contractors’ advance payment and performance security guarantees to safeguard the mobilisation advance paid to the contractor and to cater other financial losses to Wapda in compliance with the requirements of the conditions of contracts”.

To secure itself legally against financial loss and project delays in the case of international arbitration, Wapda said it had lodged the claim for encashment of the contractor’s advance payment and performance security guarantees since it was the only tool available to safeguard Wapda and to avoid financial loss.

Fresh bids
Wapda has already initiated procurement for these contracts by inviting fresh bids through leading newspapers and official websites of Wapda and the Public Procurement Regulatory Authority, the World Bank and UN Development Business to avoid delays in project implementation.

“There will be no delay in project completion if the contractor opts for [international] arbitration,” Wapda said, adding: “Termination will have no adverse impact on the CPEC framework or China-Pakistan relations.”

In August last year, the Economic Affairs Division had warned the government that the World Bank could cancel its $1.1bn loan agreement owing to inability of the stakeholders — the federal and Khyber Pakhtunkhwa governments as well as Wapda — to complete land acquisition. The acquisition of about 80,000 kanals of land is a fully funded component of the World Bank.

Dasu is one of the top-priority hydropower projects of the government under its 2013 power policy and Vision-2025. The World Bank is providing a $590m loan, along with a $460m credit limit as partial risk guarantee for external commercial financing. Separately, Wapda has contracted about Rs144bn from commercial banks to make available matching financing to meet local expenses.

After the completion of the first stage, the project will generate about 33.5 gigawatt hours per day, translating into Rs335m per day (at Rs10 per kilowatt hour).

The first phase of the project being executed by Wapda is scheduled for completion by 2019. The second phase to commission another 2,160MW has an expected completion date of 2022.

Published in Dawn, January 23rd, 2017


WHATSAPP
46 COMMENTS
PRINT
 
.
Wapda cancels Rs5.4bn contracts for Dasu project
KHALEEQ KIANI — UPDATED about 3 hours ago
WHATSAPP
46 COMMENTS
PRINT
ISLAMABAD: Even before the formal launch of $4.5 billion Dasu hydropower project, the Water and Power Development Authority (Wapda) has terminated two of its key contracts with a Chinese firm, citing ‘fundamental breaches’ of the agreement.

Moving swiftly, Wapda has not only encashed the performance guarantees of the two contracts awarded to China Railway First Group (CRFG) in November 2015 — worth Rs5.4bn — but also ordered the contractor to vacate the project area immediately, while calling for fresh tenders to make up for lost time.


The World Bank is the major financier of the 4,320MW Dasu project. The project’s terminated contracts include the ‘construction of colony and infrastructure’ worth Rs4.806bn and ‘resettlement of village Choochang and construction of Shatial Museum’ worth Rs572 million.

Chinese firm accuses authority of acting illegally, vows to seek arbitration
The completion of these two components was considered crucial to the start of construction work at the main project site.

Also read: Hydropower projects: aiding investment

CRFG project director Fan Lingang told Dawn: “The termination of the contract is un-contractual, illegal and fiercely unfair.” He claimed it was Wapda’s responsibility to complete the land acquisition process and hand over the required area to the contractor, adding that all Dasu contracts were suffering due to its default.

In reply to a set of questions sent to Wapda chairman retired Lt Gen Muzammil Hussain, the authority said it had “provided the partial possession of the site to the contractor M/s CRFG in line with the Contract Discussion Agreement/Conditions of the Contracts”.

Asked if the World Bank had indicated that it would take any action, such as loan cancellation or postponement because of project delays, Wapda said: “There is no such indication from the World Bank”.

“We are going to approach the local courts to allow us to approach an international court of arbitration to protect our rights because Wapda is not willing to resolve [the issue] amicably,” Mr Fan said, adding: “Arbitration is our right and we have to protect ourselves, not only financially but also our reputation and image.”

He maintained that his firm would “complain to the World Bank as well”. Mr Fan said the company had mobilised 30 staffers to the project site, but conceded that practically no work was done because of Wapda’s inability to settle land disputes with locals. “Wapda is the defaulter because it didn’t provide the land. The contractor actually had the right to terminate the contract, but it didn’t.”

He claimed that the contract had been terminated without prior legal notice and without being provided the opportunity to rectify any violation, if any, by the contractor. He said Wapda had blamed the CRFG for subletting the contract to a Lahore-based blacklisted company in order to terminate the contract, even though the former was not a legal contract.

The authority, however, defended its decision, saying: “The contracts were terminated due to fundamental breaches of the contract by the contractors. In these circumstances, no legal notice was required to be served on the contractor to rectify under the conditions of the contracts.”

Mr Fan explained that “a cooperation agreement” was signed with a local firm before the bidding took place as “a matter of comfort”. This, he said, was cancelled when it was pointed out by Wapda and the project consultants, long before the authority terminated the contract.

He called Wapda’s encashment of securities and refund of the mobilisation advance a case of fraudulent practice, misrepresentation and use of influence.

In response to CRFG’s claims, Wapda maintained that it “issued the notice of termination and lodged the claim for the encashment of the contractors’ advance payment and performance security guarantees to safeguard the mobilisation advance paid to the contractor and to cater other financial losses to Wapda in compliance with the requirements of the conditions of contracts”.

To secure itself legally against financial loss and project delays in the case of international arbitration, Wapda said it had lodged the claim for encashment of the contractor’s advance payment and performance security guarantees since it was the only tool available to safeguard Wapda and to avoid financial loss.

Fresh bids
Wapda has already initiated procurement for these contracts by inviting fresh bids through leading newspapers and official websites of Wapda and the Public Procurement Regulatory Authority, the World Bank and UN Development Business to avoid delays in project implementation.

“There will be no delay in project completion if the contractor opts for [international] arbitration,” Wapda said, adding: “Termination will have no adverse impact on the CPEC framework or China-Pakistan relations.”

In August last year, the Economic Affairs Division had warned the government that the World Bank could cancel its $1.1bn loan agreement owing to inability of the stakeholders — the federal and Khyber Pakhtunkhwa governments as well as Wapda — to complete land acquisition. The acquisition of about 80,000 kanals of land is a fully funded component of the World Bank.

Dasu is one of the top-priority hydropower projects of the government under its 2013 power policy and Vision-2025. The World Bank is providing a $590m loan, along with a $460m credit limit as partial risk guarantee for external commercial financing. Separately, Wapda has contracted about Rs144bn from commercial banks to make available matching financing to meet local expenses.

After the completion of the first stage, the project will generate about 33.5 gigawatt hours per day, translating into Rs335m per day (at Rs10 per kilowatt hour).

The first phase of the project being executed by Wapda is scheduled for completion by 2019. The second phase to commission another 2,160MW has an expected completion date of 2022.

Published in Dawn, January 23rd, 2017


WHATSAPP
46 COMMENTS
PRINT
:hitwall::hitwall::hitwall::hitwall::hitwall::hitwall::hitwall:
why is it that we are not serious about our water problem.
@Zibago @django @RealNapster @The Sandman @Moonlight

@H!TchHiker @Chauvinist @Well.wisher @Mentee @User
 
.
Another setback. But InshAllah, we will prevail.

BTW, is the news verified?
 
. .
1) Removal of CRFP will not effect the construction of Dam as they were contracted to execute resettlement sites and building the Shatial museum – two schemes that are part of the Dasu hydroelectric power project.Korea Electric Power Company is building the Dasu Hydropower Project on the Indus River through a consortium, with the first stage of the project to be serviceable by 2021

2) Wapda officers should be fired and interrogated for awarding a contract to company with past practice of engaging in bribery "In October 2013 that China’s anti-graft authorities punished eight people at a state-owned rail construction firm, China Railway Construction Corp. Ltd, for spending more than $100m on ‘hospitality’ in 2012.."In other case they spent $135m on receptions for guests. One of the officials received a suspended death sentence, meaning life imprisonment."

Wapda is very famous for there honesty so one needs to do detail inquiry in this case..The should be questioned why did they award contract to this company at first stage ?
 
Last edited:
.
Good move by Pakistan..... These Chinese company deserves this. :toast_sign:
 
.
Such matter that involve Billions are best , reviewed by NAB or military higher uppers.

Would be quite odd that a project is awarded and money released by Country and then WAPDA decides to backtrack

However since the project in early phases hopefuly a fresh bid can be done to find an alternative company to help with efforts to develop the project

  • However provision of Land is Responsibility of Local Group, WAPDA will lose the international court case I can tell you that right now

Seems like WAPDA officials were responsible for making land Available on time, and they could not secure the land due to inefficiencies in local bodies , which caused contractors to keep waiting for avilablity of land , and when they complained , WAPDA officials tried to hide their own failiures.

Why should a international contractor , chase local bodies for land availability - the local bodies in Pakistan have responsibilities to ensure before the project Kicks off all land is available 100%


All contractors by law, don't touch anything unless they 100% know that the land is owned or property is owned by the group they are doing the work for.

It is basic 101 Engineering

Some level of delays are generally normal , however this has to be mentioned in contract paperwork , however 100% .... no one will start work unless land is secured

Don't think it is fair that local body can't secure land , and then they take the seucurity (Money) deposited by the contractor for promise of delivery of work !!!
100% dishonest action by WAPDA officials

WAPDA officials will not only lose the case they will end up with hefty (fine by international courts)


The project start date should have been the date , on which all Land was secured and Contractor was given "OK" to commence project ; Seems to me under pressure WAPDA may be have stated
"Oh we have started the project already for buracuracy purpose however they were clearly not ready with the land " This dragged the contractor into a shady deal who now cannot work since land is not secured

Sometimes for Political statement purpose , or press release purpose , folks put pressure on organizations like WAPDA to give our offical statements , and that is why I think they may have stated "OH WE ARE RUNNING ALREADY MAKING PROGRESS" however in reality they had no land secured and this is why there is a problem
 
Last edited:
.
1) Removal of CRFP will not effect the construction of Dam as they were contracted to execute resettlement sites and building the Shatial museum – two schemes that are part of the Dasu hydroelectric power project.Korea Electric Power Company is building the Dasu Hydropower Project on the Indus River through a consortium, with the first stage of the project to be serviceable by 2021

2) Wapda officers should be fired and interrogated for awarding a contract to company with past practice of engaging in bribery "In October 2013 that China’s anti-graft authorities punished eight people at a state-owned rail construction firm, China Railway Construction Corp. Ltd, for spending more than $100m on ‘hospitality’ in 2012.."In other case they spent $135m on receptions for guests. One of the officials received a suspended death sentence, meaning life imprisonment."

Wapda is very famous for there honesty so one needs to do detail inquiry in this case..The should be questioned why did they award contract to this company at first stage ?
thanks for clearing the confusion :enjoy: i was under the impression that this incident is going to further delay the construction
 
.
Current Wapda chairman retired Lt Gen Muzammil Hussain is having a hard time understanding what's going on. Jab tak isay samajh aay gi kay bijli kaisi bnti hai tb tk koi aur is ki jaga lay aain gay.
 
.
Contract work is quite to the point , you can't just terminate a contract with out no reason

If Land is not scured , not contractor's problem you (WAPDA) have to pay their due salaries if their staff is present on site ready for work as stated on start date of project

I can see , WAPDA , chair must have been thinking , if Land is not secured the workers will not be demanding compensation.

In worse case the staff / contractor should have been told to go home , and with assumption the WAPDA company will notify when the alternative start date is instead of termination of contract

Reasonable thing to do should have been

a) Pay the staff/ worker the compensation to the date of new notification
b) Negotiate with contractor a new start date when contratcor staff member should return
c) Ensure all the Land is 100% secured specially the % where work can commence


If it was 100% known that land acquisition will be adhoc basis , as project progresses , then this should be discussed with contractor to explain , yes work can start
 
Last edited:
. .
Tohray paisay wapda higher ups ko tohray paisay military ko and we will have a new shinny dam! Or they can always use sub standard materials and do a good finishing job and call it a new shinny dam!
 
.
Wapda should sue Chinese firm for panelty for breach of contract.
 
.
\

Because for now, we have water.

Let them (Wapda) wait 20 more years. tab pochun ga inse kay ab batao maadrc*****. kahan hay Paani. this sort of acts will further increase the insecurity among contractors.

Good move by Pakistan..... These Chinese company deserves this. :toast_sign:

deserve why. ?

Wapda was responsible for land acquisition. they failed to complete it on time. and now blaming Chinese Company for not "starting" their work. ............. abay kaisay start kary ? zameen to leky do.
 
. .

Pakistan Defence Latest Posts

Back
Top Bottom