Turbulence ahead for Indian fighter jet: analysts
NEW DELHI — India's homegrown fighter jet, the Tejas, has finally been cleared for operations but analysts say any celebration of India's entry into an elite club of military hardware producers is premature.
Initial operational approval for the Tejas Light Combat Aircraft (LCA) has taken 26 years -- the result of endless developmental delays, technological hiccups and massive cost overruns.
First conceived as a direct replacement for the Indian Air Force's (IAF) ageing fleet of Russian-made MiG-21s -- tagged "flying coffins" for their abysmal safety record -- the LCA was hyped as a milestone in India's bid to reduce its dependency on military imports.
Although conceived, designed and assembled in India, its "indigenous" label is somewhat misleading as 40 percent of its components are foreign-made, including the radar and US-built engine.
Formal induction of the Tejas is still two or three years away, and questions remain over its eventual suitability.
"Only after the aircraft is put in use by the pilots will its strength and limitations become clear," said Ajey Lele, a Research Fellow at the Institute for Defence Studies and Analyses in New Delhi.
"India's peculiar security requirements demand a very capable air force with state-of-the-art platform and weapon systems. Naturally, the Tejas will have to fulfil major expectations," he added.
"Its too early to pop the bubbly," warned military aviation specialist Kapil Kak, saying procuring engines for a second generation of Tejas could become a headache for India.
Accepting the LCA's operational clearance certificate last week, Air Chief Marshal P.V. Naik seemed less than enthused, noting that the aircraft was really a "Mig-21, plus, plus" and not the fourth generation fighter it was conceived as.
From an initial budget of 5.6 billion rupees ($123 million), the cost of developing the fighter has snowballed over the years to around 180 billion rupees.
While acknowledging the LCA's troubled history, Arun Sharma, a former chief of naval staff and chairman of the National Maritime Foundation think-tank, said the project should still be applauded for overcoming major challenges.
Read full article at Google News
NEW DELHI — India's homegrown fighter jet, the Tejas, has finally been cleared for operations but analysts say any celebration of India's entry into an elite club of military hardware producers is premature.
Initial operational approval for the Tejas Light Combat Aircraft (LCA) has taken 26 years -- the result of endless developmental delays, technological hiccups and massive cost overruns.
First conceived as a direct replacement for the Indian Air Force's (IAF) ageing fleet of Russian-made MiG-21s -- tagged "flying coffins" for their abysmal safety record -- the LCA was hyped as a milestone in India's bid to reduce its dependency on military imports.
Although conceived, designed and assembled in India, its "indigenous" label is somewhat misleading as 40 percent of its components are foreign-made, including the radar and US-built engine.
Formal induction of the Tejas is still two or three years away, and questions remain over its eventual suitability.
"Only after the aircraft is put in use by the pilots will its strength and limitations become clear," said Ajey Lele, a Research Fellow at the Institute for Defence Studies and Analyses in New Delhi.
"India's peculiar security requirements demand a very capable air force with state-of-the-art platform and weapon systems. Naturally, the Tejas will have to fulfil major expectations," he added.
"Its too early to pop the bubbly," warned military aviation specialist Kapil Kak, saying procuring engines for a second generation of Tejas could become a headache for India.
Accepting the LCA's operational clearance certificate last week, Air Chief Marshal P.V. Naik seemed less than enthused, noting that the aircraft was really a "Mig-21, plus, plus" and not the fourth generation fighter it was conceived as.
From an initial budget of 5.6 billion rupees ($123 million), the cost of developing the fighter has snowballed over the years to around 180 billion rupees.
While acknowledging the LCA's troubled history, Arun Sharma, a former chief of naval staff and chairman of the National Maritime Foundation think-tank, said the project should still be applauded for overcoming major challenges.