What's new

Lahore Metro Train Project | News and Updates

Orange Metro Train to be connected with Metro Bus, Railway Station


LAHORE: For achieving the objectives of Mass Transit System in the provincial metropolis, the Lahore Orange Line Metro Train will be connected with the Lahore Metro Bus System (Green Line) as well as the Lahore Railway Station by constructing two special walkways for pedestrians.

Advisor to Chief Minister Punjab and Chairman of the Steering Committee for the Lahore Orange Line Metro Train Project (LOMTP) Ahmad Hassan informed on Friday, that the Lahore Development Authority would execute this project at a cost of Rs 2.75 billion.

He said that an underpass would be constructed for connecting the underground Anarkali Station of Orange Line, being constructed at Jain Mandir area, with the M.A.O College station of Lahore Metro Bus. Pedestrians will be able to embark or disembark from one mode of transport for getting ride on the other one by using this walkway.

Similarly, a 40-feet elevated ‘walkulator’ (moving walkway) will be installed for connecting Lahore Railway Station with the Bohrwala Chowk Station of Orange Line Metro Train at Nichelson Road.

Passengers intending to move between these two locations will not have to walk a step for this purpose. They will be able to go from one point to the other just by standing on this moving ‘walkulator’, he informed.

He said that the LDA had invited applications for pre-qualification of engineering firms and contractors, willing to execute the project by September 9, 2017.

https://www.pakistantoday.com.pk/201...ilway-station/
 
.
20992567_477517595942035_6135016427801173518_n.jpg




20953982_477517592608702_8357835643153833294_n.jpg
 
. .
Orange Train coaches to reach Lahore next month

LAHORE: First shipment of coaches manufactured in China for Lahore Orange Line Metro Train has been dispatched from Shanghai, which is likely to reach Karachi by the 15th of September and subsequently to Lahore by the end of next month.

Adviser to the Chief Minister, Punjab and Chairman of the steering committee for project (LOMTP) Khawaja Ahmad Hassaan informed this during the weekly progress review meeting here Wednesday. He directed for speeding up work for finalising all arrangements for parking the consignment of coaches at Depot at Dera Gujan as well as at stabling yard at Raiwind Road.

He informed that 45 kanal land is being acquired at village Kotli Ghassi and Bagrian Saydan for construction of a retention pond for storm water with a view to improving the underground water table in the adjoining area of Orange Line Metro Train’s Depot at Dera Gujran.

The meeting was informed that 74 percent of the civil work on Lahore Orange Line Metro Train Project has so far been completed. Progress on package-I from Dera Gujran, GT Road to Chauburji was 86 percent, on package-II from Chauburji to Ali Town was 53.2 percent, on Depot near Dera Gujran was 79 percent while on stabling yard near Ali Town it was 75 percent. An overall 17 percent electrical and mechanical work of the project has also been completed. Electrical and mechanical work on 20 elevated stations of metro train was in full swing. Civil work on available area along package-I had almost been completed, the meeting was told.

Khawaja Ahmad Hassaan directed that cleanliness and public facilitations must be given top priority during forthcoming Eid-ul-Azha days. All the utility services departments should chalk out a comprehensive plan for this festival for ensuring uninterrupted supply of services during these days. He directed for eliminating illegal sale points of sacrificial animals and shifting them to places designated for this purpose.

Member of the Provincial Assembly Ch Shahbaz, Chief Engineer LDA Asrar Saeed, General Manage Operations Punjab Mass Transit Authority Syed Uzair Shah, Chief Engineer Tepa Saif-ur-Rahman, General Manager Nespak Salman Hafeez, senior officials of Lesco, Wasa, PTCL, Sui gas, Traffic Police, Railways, Rescue 1122, Civil Defence, Chinese Contractor, CR- NOROINCO, Representatives of Chinese Engineering Consultant and local contractors of the project attended the meeting.
 
. . .
When will all the court stopped areas be resolved? ... any news on that?

Our system is all liking or disliking. Judges are no exception.
Those sites are already destroyed by the traffic and people. So what is the use of not allowing to construct. They should allow.
 
.
Structure of Lahore Orange Line's 24 stations completed

Structures of 24 out of 26 stations of Lahore Orange Line Metro Train Project have been completed with the constructions of another three stations at Hanjarwal, Canal View and Tokhar Niaz Baig.

Chinese contractor CR-NORINCO is executing electrical and mechanical works at all these places.

This was informed at a meeting chaired by Advisor to Chief Minister and Chairman of steering committee for LOMTP Kh Ahmad Hasan to review progress on the project on Wednesday.

The meeting was informed that structure of another station at Ali Town, Raiwind Road will be completed next week. Construction of underground Central Station near GPO Chowk will start after the vacation of restraining order by the court.

The meeting was told that work for pre-casting U-Tub girders and transoms for package II of the train, from Chuberji to Ali Town, has sped up with the employment of Steam Curing Technology, which has been introduced for the first time in Pakistan.

The very first experiment in this regard has been fruitful which has facilitated speedy manufacturing of the track along this stretch. An average of nine U-Tub girders were being pre-cast daily and as many girders will be launched by the recently imported machinery.

The meeting was told that pace of construction work on package –II, from Ali Town to Chuberji, was satisfactory. A total of 806 U-tub girders are being fabricated for constructing 40 feet elevated track for the train. Each U-tub girder is 30 meters long, 5.5 meters wide and weighs 216 tons.

After launching of these structures, the track for the train will start taking shape along package-II. So far 261 U-tub girders have been launched, the meeting was told.

The meeting was informed that 74 per cent of the civil work on the project has so far been completed. Progress on package-I from Dera Gujaran, GT Road to Chuberji was 86 per cent, on package-II from Chuberji to Ali Town was 53.3 per cent, on Depot near Dera Gujran was 79.1 per cent while on Stabling Yard near Ali Town it was 75 per cent.

An overall 18 per cent electrical and mechanical work of the project has also been completed.

http://nation.com.pk/national/06-Sep...ions-completed
 
.

Orange Line Metro Train Project Under Construction Package-II near Thokar Niaz Baig



DJn4sYxWsBEKYHw.jpg




DJn4sY8XkAAuZF6.jpg





DJn4sY4WsAE9oCd.jpg





DJn4sYzWAAAm3aG.jpg



 
.
Orange Line Metro Train first shipment reaches Pakistan

pti-petitions-sc-to-become-party-to-orange-line-metro-train-case-16ae1e59c24934e2e9f19e45d7e5ce9a-1.jpg


LAHORE: First shipment of rolling stock for Lahore Orange Line Metro Train will arrive Karachi tomorrow (Friday) from China and reach Lahore in the first week of October.

This was revealed by Adviser to the chief minister, Punjab and Chairman of the steering committee for Lahore Orange Line Metro Train Project (LOMTP) Khawaja Ahmad Hassaan while addressing the weekly progress review meeting here Wednesday. He told that a team of Chinese Operations and Maintenance Engineers has already arrived Lahore for operating the train.

A total of 27 trains, each comprising of five cars, will be operated under the LOMTP, he said, adding by the end of this year, 23 sets of trains are scheduled to reach Lahore from China. Khawaja Ahmad Hassaan informed that a befitting ceremony will be held in Lahore for receiving the first batch of locomotive for Orange Line Metro Train.

He directed for quickly finalising all arrangements for parking these bogies at Depot at Dera Gujran and stabling yard at Ali Town, Raiwind Road.

The meeting was told that gray structures of 24 out of the 26 stations of Lahore Orange Line Metro Train Project has been completed and execution of electrical and mechanical work at all these places was in full swing by Chinese contractor CR-NORINCO.

https://timesofislamabad.com/orange-line-metro-train-first-shipment-reaches-pakistan/2017/09/14/
 
. .
Orange Line Metro Train consignment reaches Lahore


DLIzIG6X0AIw1Ev.jpg



DLIzIvrXoAMCBiD.jpg





LAHORE – The first consignment of Orange Line Metro Train containing three coaches and two engines has arrived in Lahore.

According to a spokesman of Punjab Mass Transit Authority, launching of the first Orange Line Metro Train will be held on the 7th of this month.
He said efforts are underway to complete Orange Line Metro Train project by December this year.

Punjab government is making hectic efforts in completing the mega project despite the court stay orders in certain sections of the project.
 
. .
wow amazing project......hatts off to SS with so much criticism to his work he still manages to complete them and those who were criticizing metro buss projects are now dreaming of it to be there in their own cities. Just imagine what would happen if SS didnt complete metro buses and now this this project on criticism? those who were criticizing metro bus should be asked why they want the same in their cities now? hope our politicians become literate enough to not to politicize development for political point scoring.:disagree:
 
. .

Pakistan Defence Latest Posts

Pakistan Affairs Latest Posts

Back
Top Bottom