The test run begun on Monday to inspect all aspects of the Cat Linh-Ha Dong Metro Line, including functioning stations with staff on duty in operation rooms and at ticket booths.
Even though no passengers have been allowed in, automatic ticket gates and lighting are turned on for inspection.
Safety features such as fire systems have all been checked.
All 13 trains will participate in the trial run, with six to nine operating each day, running the complete route.
Signs have been installed in Vietnamese and English to assist commuters, along with a loud speaker system.
The 20-day trial is a mandatory step in the inspection process before the Chinese contractor can hand over the project to the Ministry of Industry and Trade.
The depot for train maintenance is almost completed.
From Vietnam Express
The test run begun on Monday to inspect all aspects of the Cat Linh-Ha Dong Metro Line, including functioning stations with staff on duty in operation rooms and at ticket booths.
Even though no passengers have been allowed in, automatic ticket gates and lighting are turned on for inspection.
Safety features such as fire systems have all been checked.
All 13 trains will participate in the trial run, with six to nine operating each day, running the complete route.
Signs have been installed in Vietnamese and English to assist commuters, along with a loud speaker system.
The 20-day trial is a mandatory step in the inspection process before the Chinese contractor can hand over the project to the Ministry of Industry and Trade.
The depot for train maintenance is almost completed.