What's new

12,568 MW electricity to be added to national grid by 2018

Devil Soul

ELITE MEMBER
Joined
Jun 28, 2010
Messages
22,931
Reaction score
45
Country
Pakistan
Location
Pakistan
12,568 MW electricity to be added to national grid by 2018
By APP
June 13, 2016


ISLAMABAD: Over 12,568 Megawatts of electricity would be added to the national grid after completion of a number of power generation projects by year 2018.

Under a long term plan, the country would have an additional generation capacity of 30,948 MW by the year 2022 through Neelum Jhelum, Chashma nuclear, wind, hydel, LNG, Jamshoro Coal and Bagasse power projects, according to a senior official of the Ministry of Water and Power here.

Around 8,630 MW would be generated under the prioritized China Pakistan Economic Corridor (CPEC) projects in the same period.

Under the Power Generation Policy 2015, several initiatives were taken including Transmission Lines Investment Policy; focus on Coal Based Power, LNG Based Power, CPEC power generation projects of 8630 MW, production through LNG – 3600 MWs and the CASA-1000 project.

In a recently held briefing, he said, under the policy to facilitate new IPPs, 12,113 MW of electricity would be generated.

Giving a breakdown of power generation by year 2022, he said, a total of 30,948 MWs would be generated; of which 38% would be obtained from Hydel, 14% from Renewable, 16% from imported coal, 13% from indigenous coal, 12% from imported LNG and 7% from nuclear.

Under the CPEC, the work was in progress on the $ 36 billion power projects and the completion of these projects will make the country self-sufficient in power sector.

He clarified that the inflow of foreign capital in power projects under CPEC was investment and not loan.

Under the Prime Minister’s direction, transparency was being ensured in all power projects including wind, hydel, coal and solar.

He said, in 2016 the estimated investment in the power sector was estimated to be US$ 3,617 million. In 2017 it was expected to be US$ 11,420 million and by 2019-22 it would be US$ 36,084 million.

He said the customer service has also been improved through enhanced employee efficiency and reduction in response time.

He said, daily payment instructions to generation companies were also published on website including payments made to IPPs and power sector entities.

Similarly the performance of DISCOs was also published on website on quarterly basis.

He said work was going on to upgrade and improve the transmission lines and network, adding, line losses have decreased while power generation increased.

There was no loadshedding during the Sehri, Iftari and Taraweeh timings and said it would further decline by year’s end.

Giving an overview of history of loadshedding he said, it has cut down to eight hours in rural areas, six hours in urban areas, while it is zero for the industrial sector.

He said, by June 2017, the loadshedding hours for rural areas would be down to 3 hours and for urban areas to two hours only.

It may be mentioned here that in 2013 the country faced a power deficit of 5500 MW and its industrial and urban sectors were facing 12 hours loadshedding, while the rural areas faced 14 hours power outage leading to low industrial output, higher unemployment and loss of economic growth.
 
.
We need New transmission lines. Many New power projects are in development phase... even if no further power projects are initiated, then even we would have enough power that can not be transported through the current transmission system.
Long and short distance transmission lines were required like yesterday
 
.
Great news if all projects complete on time we will be fine for 15 years , that window will give us enough time to build all big dams if we want too.
But my main concern is Transmission lines , we need to upgrade all of them and have to build few more with 5000Mgw minimum capacity each , and we must have to upgrade our National Grid .
National Grid is far more important then any motorway or I would say any Hospital (please don't mind ) ,
Thank you all
 
.
:D :D
13173723_864501333677566_326879407834458826_n.jpg


We need New transmission lines. Many New power projects are in development phase... even if no further power projects are initiated, then even we would have enough power that can not be transported through the current transmission system.
Long and short distance transmission lines were required like yesterday

D. G. Khan Loralai Transmission Line 90% Completed
Dadu Khuzdar Transmission line 60% Completed
Moro-Dadu Transmission Line
AES-R.Y. Khan-Moro-Jamshoro Transmission Line

These are Under Construction
 
. .
Thanks omar. These are small but vital projects. But not the type that will sustain economic boom or activity in business areas. I believe that amongst these Aes - rahim Yar khan to Jamshoro is important...
But
We need lines to and fro from intensive power drainage areas.. Like Lahore... Multan... Fsd.. Ghotki distt.. Gujranwala and soon to be operational chashma... Mangla / neelum jehlum and thar field.
Transmission lines take time to built and they pass through barren and Rugged areas. Time for their construction has come and we are wasting precious time day in and day out.
 
. . . . .
Can Pml N achieve a load shedding free Pakistan before 2018 gen elections ?
 
. .
@Muhammad Omar i will send you sweet bro if even 80% project complete in time......
your energy related posts give me optimism which is very rare to find in Pak. matters...
 
.
@Muhammad Omar i will send you sweet bro if even 80% project complete in time......
your energy related posts give me optimism which is very rare to find in Pak. matters...

I have Pictures of like 20 Under Construction Power Projects + Transmission lines :D :D should i make you more Optimistic :D
 
.
Obviously it would.N league would have a safe side and a honey trap for this nation to capture the votes.And this nation besides learning a lesson would again elect them.Pathetic we !!:frown:
 
.
Back
Top Bottom