Prime Minister Shahid Khaqan Abbasi will inaugurate Golen Gol Hydropower Project at District Chitral, Khyber Pakhtunkhwa (K-P) today (Saturday).

The project has been constructed on Golen Gol – a tributary of River Mastuj – near Chitral. The first unit of the project can generate up to 36MW and is exclusively meant to provide electricity to Chitral town and adjacent areas.

PM Abbasi inaugurates DigiSkills programme

In the wake of the devastating floods of 2015 in Chitral, the federal government directed Water And Power Development Authority (WAPDA) to supply electricity generated from the first unit of the project to Chitral in order to meet the energy needs for socio-economic development of far-flung areas of K-P province.

This quantum of electricity is three times more than the present requirements of Chitral, and will also cater for the probable surge in electricity demand in future.

Golen Gol Hydropower project will result in a new era of progress and prosperity in Chitral, besides stabilising the national economy by providing low-cost and environment-friendly electricity to the national grid.

The total generation capacity of the project is 108MW with three generating units – each of them having a capacity of 36MW. The first unit has been completed, while the second and the third unit will be commissioned in March and May 2018 respectively.

The project will provide 436 million units of electricity to the National Grid every year. Benefits of the project have been estimated at Rs3.7 billion per annum. The approved PC-I of the project amounts to Rs29 billion.

PM inaugurates free trade zone, first international Gwadar expo

In addition to WAPDA’s own sources, United States Agency for International Development (USAID), Saudi Fund for Development, Kuwait Development Fund and OPEC Fund for International Development have also been providing financial assistance for completion of the project.

https://tribune.com.pk/story/1625403/1-pm-inaugurate-golen-gol-hydropower-project-k-p/
 
.
I use to work for a Korean company who was involved in the construction of this dam. Good to know this project is finally completed.
 
.
Hydro energy is the real life. Any news about neelam jehlum progress. It was said that it will start wet testing in February 2018.
 
.

Country Latest Posts

Back
Top Bottom