Neelum-Jhelum project enters final stage
By Our Correspondent
Published: December 29, 2017
52SHARES
SHARE TWEET EMAIL
Representational image PHOTO: AFP
LAHORE: The 969-megawatt (MW) Neelum-Jhelum Hydropower Project – a hydel power generating scheme of strategic importance – is in its final stage of completion, a press release issued by the Water and Power Development Authority (Wapda) said on Friday.
NEPRA approves Rs3.11-per-unit reduction in power tariff
It further listed completion of dam and start of water filling in the reservoir, completion of water way system comprising 51.5-kilometre long tunnels, installation of turbines, generators, transformers and other electro-mechanical equipment in the powerhouse, and dry testing of electro-mechanical equipment, as the infrastructural operational ‘milestones’ achieved.
NEPRA approves Rs3.11-per-unit reduction in power tariff
“The transmission line by the NTDC is expected to be completed by the end of this month, while water filling (pressurisation) of water way system will commence during first week of January 2018,” the release said.
Published in The Express Tribune, December 29th, 2017.
Like Business on Facebook, follow @TribuneBiz on Twitter to stay informed and join in the conversation.
By Our Correspondent
Published: December 29, 2017
52SHARES
SHARE TWEET EMAIL
Representational image PHOTO: AFP
LAHORE: The 969-megawatt (MW) Neelum-Jhelum Hydropower Project – a hydel power generating scheme of strategic importance – is in its final stage of completion, a press release issued by the Water and Power Development Authority (Wapda) said on Friday.
NEPRA approves Rs3.11-per-unit reduction in power tariff
It further listed completion of dam and start of water filling in the reservoir, completion of water way system comprising 51.5-kilometre long tunnels, installation of turbines, generators, transformers and other electro-mechanical equipment in the powerhouse, and dry testing of electro-mechanical equipment, as the infrastructural operational ‘milestones’ achieved.
NEPRA approves Rs3.11-per-unit reduction in power tariff
“The transmission line by the NTDC is expected to be completed by the end of this month, while water filling (pressurisation) of water way system will commence during first week of January 2018,” the release said.
Published in The Express Tribune, December 29th, 2017.