WAPDA - Water WingPRESENT STATUS OF DIAMER BASHA DAM:
The Feasibility Study completed.
Review of the Feasibility Study is completed. Detailed Engineering Design and Preparation of Tender Documents is underway.
Excavation of Adits, Trenches, Drilling of boreholes and Topographic Surveys completed.
Micro Seismic Monitoring System has been installed at the dam site. Data retrieval is in progress.
Two Nos. Strong Motion Accelerographs have been installed at dam site.
Cadastral Survey is in progress to collect information for land acquisition, replacement, and re-location of people & for Resettlement Action Plan (RAP).
92 % Construction work of Officer’s hostel and laboratory is completed.
Vocational Training Institute is established at Chillas, to make readily available skilled and semi skilled labour at site.
Climatological data is collected regularly and an additional Automatic Meteorological Station is being established at dam site.
Model studies for Diversion Works and sectional model of spillway completed. Construction of Comprehensive Model of at IRI, Nandipur is completed and testing in progress.
PC-I of Land Acquisition for DBDP submitted to GOP, for approval.
Revised PC-I for up gradation of KKH from Manshra to Dam site is under approval by ECNEC.
A bridge at Thakot on Indus River is under construction by NHA. Rs. 302.600 million allocated in PSDP 2007-08. Progress is 12%.
Rock Mechanics Testing Programme in Adits and at dam site is being planned.
Tentative project cost as estimated by Diamer Basha Consultants is US $ 8.505 Billion.
Hydrology and Sediment Data is collected regularly.
Samples for Trial Mix Design collected from the site are being tested in CMTL and PCSIR Laboraties.
The Consultants have completed 90% Detailed Engineering Design work upto Feburary 2008. Rs.500million allocated for Detailed Engineering Design in PSDP 2007-08.
Updates:
Thanks for the updates as i have heard that opening of it is due in 2012 but is is now where near completion...
Updates:
even with corrupt politicians, we still manage to grow 4-6% every year, wt we really need is a game changing leader^^^^^^^^^
Beautifull !
Iran and India are setting off a crazed development pace in the region. Then there is China :-@ ... Gulf states (Dubai is practically next doors). Also newly independent former Soviet republics the other - rich stans, and it seems Pak's falling back. Like Canads to the US, Pak should make hay while the sun shines and become India's bijlee-paani (power & water), cement, fertiliser + food supplier.
Big money :-$ .
^^^^^^^^^
Beautifull !
Iran and India are setting off a crazed development pace in the region. Then there is China :-@ ... Gulf states (Dubai is practically next doors). Also newly independent former Soviet republics the other - rich stans, and it seems Pak's falling back. Like Canads to the US, Pak should make hay while the sun shines and become India's bijlee-paani (power & water), cement, fertiliser + food supplier.
Big money :-$ .
Updates: