ghazi52
PDF THINK TANK: ANALYST
- Joined
- Mar 21, 2007
- Messages
- 103,045
- Reaction score
- 106
- Country
- Location
Formal Inauguration of 969 MW Neelum Jhelum HEP. April 13, 2018 when Unit # 4 was put online.
The most strategic and state-of-the-art Neelum-Jhelum hydropower project, located in AJK, has started generating 242 MW electricity. However, it will be fully functional by June-July this year to inject 969 MW electricity in the national grid.
The project with capacity of 969MW electricity will generate 5,150 gegawatt per hour at the levelised tariff of Rs. 13.50 per unit for 30 years. The annual benefits of the project have been estimated at Rs55 billion. Prime Minister Shahid Khaqan Abbasi has performed the inauguration ceremony of the project.
The Neelum-Jhelum Hydropower Project is a world class hydropower facility executed in the deep mountains where geology is neither predictable nor readable.
Never in Pakistan before, has such a complex project, which is one of a kind and is being branded as the new wonder of Pakistan, as only 10 percent of the whole project is on the surface, while 90 percent is underground with water-way system of 32 km tunnels (overall being ~52 km). Besides, transformer hall and powerhouse are also underground. The India's Kishenganga Dam of 330MW has been constructed on the same Neelum river. Since the water destined for Pakistan has been diverted to the Kishenganga project by India, therefore 10 percent less water will flow into the Neelum river. (ICA)
The project witnessed many upheavals on its way to completion and 86 percent of the project got completed without any financial closure. The cost of the project has been revised five times. Its initial cost was Rs80 billion but ended up at Rs500.343 billion. The Executive Committee of National Economic Council approved the project in 2002 at the cost of Rs84.502 billion for the initial design being prepared in 1997 while construction of project started on 30 January 2008. The cost of the project scaled up to Rs277.502 billion, which the ECNEC approved in 2012, and then once again its cost surged to Rs404.331 billion in 2015. And after that it again hiked to Rs500.343 billion.
The initial cost of Rs84 billion increased in the wake of the 2005 earthquake causing design modifications keeping in view the fault line passing through the Dam site thus considerably changing the scope of the project.
Furthermore, due to the rising value of dollar the cost escalated to over Rs277 billion. And then the cost of the project was revised upwards by 86 percent to Rs404 billion mainly because of the inclusion of duties, taxes which further pushed the cost to Rs500.343 billion because of the inclusion of IDC (interests during construction) till completion of the project and the cost of the consultant.
The most strategic and state-of-the-art Neelum-Jhelum hydropower project, located in AJK, has started generating 242 MW electricity. However, it will be fully functional by June-July this year to inject 969 MW electricity in the national grid.
The project with capacity of 969MW electricity will generate 5,150 gegawatt per hour at the levelised tariff of Rs. 13.50 per unit for 30 years. The annual benefits of the project have been estimated at Rs55 billion. Prime Minister Shahid Khaqan Abbasi has performed the inauguration ceremony of the project.
The Neelum-Jhelum Hydropower Project is a world class hydropower facility executed in the deep mountains where geology is neither predictable nor readable.
Never in Pakistan before, has such a complex project, which is one of a kind and is being branded as the new wonder of Pakistan, as only 10 percent of the whole project is on the surface, while 90 percent is underground with water-way system of 32 km tunnels (overall being ~52 km). Besides, transformer hall and powerhouse are also underground. The India's Kishenganga Dam of 330MW has been constructed on the same Neelum river. Since the water destined for Pakistan has been diverted to the Kishenganga project by India, therefore 10 percent less water will flow into the Neelum river. (ICA)
The project witnessed many upheavals on its way to completion and 86 percent of the project got completed without any financial closure. The cost of the project has been revised five times. Its initial cost was Rs80 billion but ended up at Rs500.343 billion. The Executive Committee of National Economic Council approved the project in 2002 at the cost of Rs84.502 billion for the initial design being prepared in 1997 while construction of project started on 30 January 2008. The cost of the project scaled up to Rs277.502 billion, which the ECNEC approved in 2012, and then once again its cost surged to Rs404.331 billion in 2015. And after that it again hiked to Rs500.343 billion.
The initial cost of Rs84 billion increased in the wake of the 2005 earthquake causing design modifications keeping in view the fault line passing through the Dam site thus considerably changing the scope of the project.
Furthermore, due to the rising value of dollar the cost escalated to over Rs277 billion. And then the cost of the project was revised upwards by 86 percent to Rs404 billion mainly because of the inclusion of duties, taxes which further pushed the cost to Rs500.343 billion because of the inclusion of IDC (interests during construction) till completion of the project and the cost of the consultant.