Karot Hydropower Station | April 2020 Progress
Follow along with the video below to see how to install our site as a web app on your home screen.
Note: This feature may not be available in some browsers.
Karot Hydropower Station | April 2020 Progress
ECNEC approves Rs175 bn to settle Diamer Basha land issues
Ecnn approves 755 billion rupees to solve Diamer Basha land matters
The Executive Committee of National Economic Council (Ecnn) approved 1,575.43 billion rupees to solve land and settlement matters related to Diamer basha dam project
Okay.
Okkayyy but article saying 175.
Never mind.
Corrected, Thanks.
LAND ACQUISITION
GBA 7,936 Acres
- Land Acquisition process started in 2010 and details are as under:-
- Total Land to be acquired = 37,419 Acres
- Private Land being purchased = 18,357 Acres
- Govt. Land to be transferred (free of cost) = 19,062 Acres
- Private Land Acquired = 8,098 Acres
KPK 162 Acres
- Govt. Land transferred to DBDP (free of cost) = 17,214 Acres
Another project by federal pro government as a gift to those who love 18th amendment.
that is blasphemy. Central gov is not giving anything to sindh.Another project by federal pro government as a gift to those who love 18th amendment.