Karot Hydro Power Plant, progress


1653576262813.png
 
.
.,.,

84-MW Gorkin-Matiltan Hydropower Project, Swat

The project is located on Ushu river (a tributary of Swat river) in Kalam, Tehsil Bahrain, District Swat.


BRIEF OF THE PROJECT:

84 MW Gorkin Matiltan HPP is a run-off the river project located on Ushu river for production of cheaper and renewable annual energy generation of about 346 GWh, which shall be sold to NTDC/PESCO through Existing Grid System at Madyan.


SALIENT FEATURES OF THE PROJECT:

Capacity84 MWDischarge42 m³/s
Net Head253 mTunnel6671 m
Annual Energy346 GWh


The tentative date of project completion is 31st July 2023.
 
.
.,.,

Bin Qasim Port, Karachi...900 MW

PP III

1653914559700.png





1654002676899.png


..

The No. 1 steam turbine of the BQPS III 900MW Project in Karachi, constructed by HEI has successfully realized the combined cycle power generation, marking a big step towards the provisional turnover of the 1# Unit of the Project.
 
Last edited:
.
,..,

700.7MW Azad Pattan Hydropower Project, AJK/Punjab​

Project700.7MW Azad Pattan Hydropower Project, AJK/Punjab
Primary Energy InputHydel
Installed Capacity (MW)700.7
LocationJhelum River
Estimated Cost (US $ Million)1,600
Executing Company / SponsorsLaraib Energy / China Gezhouba Group Company
FinancingIndependent Power Producer (IPP)
Coordinating MinistryMinistry of Energy (Power Division)
Supervising AgencyPrivate Power and Infrastructure Board (PPIB)
Total Jobs Opportunities During the Construction of this Project3000
Project Progress Update
  • Land Acquisition process started.
  • TPPA, GoP-IA, and GoPb-WUA Signed in July 2020.
  • GoAJK-IA and GoAJK-WUA signed in December 2020.
  • Financial Close (FC) under progress.
 
.
.,.,
Under Construction - Mohmand Dam 800MW
Left Bank Irrigation Tunnel with Blasting , Excavation and Support Works in progress.


1654174662367.png




1654174691984.png
 
.
.,.,
Matiari Lahore High Voltage Direct Current (HVDC) Transmission Line Project under CPEC ensured environment friendly electricity supply in Pakistan. This BRI flagship project is one of the best masterpiece of Pak China friendship under CPEC..


1654464544002.png
 
. .
.,.,
Matiari Lahore High Voltage Direct Current (HVDC) Transmission Line Project under CPEC ensured environment friendly electricity supply in Pakistan. This BRI flagship project is one of the best masterpiece of Pak China friendship under CPEC..


View attachment 851691
One thing that i never understood is karachi nuclear plants..

These plants should have been near chashma

While karachi should have been supplied from thar/coastal coal plants

Didnt make sense to me why
 
. .
,.,.,.,
The International Monetary Fund (IMF) has asked Pakistan’s government to renegotiate the China-Pakistan Economic Corridor (CPEC) energy deals before making payments of around Rs300 billion to the Chinese power plants, putting Islamabad in a tight spot.

IMF has asked the government to treat the Chinese CPEC power plants at par with the power plants established under the 1994 and 2002 power policies. These plants had been set up under the CPEC framework agreement.
 
.
.,.,
Under Construction Jaggran II Hydropower Project - 48MW. Weir, Water Distribution Assembly and Bifurcators/Manifolds...

1655641911131.png



Concrete pouring under the Steel liner at Weir Flushing Section “Under Sluice Section”. 16mm thick Steel Liner is installed at the Weir Flushing Section of 48MW Jaggran-II Hydropower Project to resist the extensive abrasion by the sediments. Instead of pouring Abrasion Resistant Concrete, the Designer had proposed the Steel Liner on the “Weir Under Sluice Section” to precipitate the rubbing & bumping impact of large size boulders and gravels which the highly steep-sloped river channel is carrying with it.


1655641939608.png




1655641968457.png
 
.
,.,.,.,.
Dollsar Engineering Inc.Co has signed a Consultancy Servives Agreements for the Detailed Engineering Design, Preparation of Bidding documents and PC-I of Chinot Dam Project.

The Chiniot Dam, located on the Chenab River, almost five kilometres from Chiniot city, the dam is projected to generate 80 megawatts of cheap and environment friendly electricity. Additionally, the gross storage of Chiniot Dam will be 0.9 million acre feet (MAF).

The feasibility study of the Chiniot Dam Project was carried out by WAPDA and completed in 2019. The PC-II Proforma for Detailed Engineering Design was submitted to Ministry of Water Resources (MoWR), for consideration in forthcoming Departmental Development Working Party (DDWP) meeting. The DDWP has approved the PC-II Proforma, subject to certain conditions.


1655849594742.png





1655849617379.png
 
.
,.,.,
Update on 800 MW Under Construction Mohmand Dam. Work is being done simultaneously on nine different sites. It could be operational by 2025.


1656364073726.png




1656364100588.png





1656364128783.png




1656364151540.png
 
. .