What's new

Energy Projects...Updates

.
The test run of two 900MW power plants, Lucky and Thar Energy Ltd has paved the way for the launch of their commercial operations.

1644454549288.png


At present, the power plants of the Southern region include :....
China Hub with 1,240 MW, E
ngro Thar with 600 MW,
Port Qasim with 1,250 MW,
Wind Energy Plants with 200 MW,
K-2 with 1,040 MW,
and Hubco with 300 MW of electricity are operational.

From this system, 1,500 MW of electricity is being used by Sindh, 500 MW of electricity is benefiting Hyderabad Electric Supply Company and 1,000 MW of electricity is being used by K-Electric. 3,130 MW of electricity is being supplied to north-urban centers of Punjab.

According to the sources, as soon as the generation touches the figure of 400 MW, the testing of 660 kV Martiari-Lahore High Voltage Direct Current transmission line would be carried out on full load/installed.
 
. .
A team of Monitoring officers from Planning Commission of Pakistan , Mr. Majid Mustafa and Miss. Mehwish Roze visited DHPP to review the current progress. Mr. Shehzad Akbar, Director Main Works briefed the guests about the construction activities going on in the project.

1644676036214.png





1644676075139.png
 
.
Diamer Basha Dam 4500MW - Under Construction
The Construction works were commenced in July 2020 on this monumental project.
InshAllah, on completion, this dam will reduce water scarcity and also address power woes of the country...


1645110825678.png




1645110850550.png
 
.
Under Construction Suki Kinari Hydropower Project..

Another milestone was achieved on 19th Feb, 2022 at Suki Kinari Hydropower Project.
247m deep lower pressure shaft (PS1) has been completed successfully and provides space for subsequent steel lining works.

Out of 6 pressure shafts, the 04 pressure shafts had already been completed.


1645484898987.png



1645484926617.png
 
.
World's highest roller compacted concrete dam Diamer Bhasha Dam.

Wapda is building a project on the Sindh River Dam on the Damir Bhasha Dam which is to be completed in 2028-29. Continuous work is being done day and night at the Damir Bhasha Dam so that this project can be completed as soon as possible and made available for public interest.

The project will have the capacity to store 8.1 million acres of total water to plow 1.23 million acres of additional land which will revolutionize the agriculture sector.

With 4,500 MW electricity production capacity, the project will provide the National Grid with more than 18 billion units annually, which will not only replace Pakistan but also help to eradicate problems like load shedding in Pakistan, which will help Pakistani industries. There will also be benefit.

The construction of the Damir Bhasha Dam will also have a positive impact on the annual energy production of current Hydal power stations including Tarbela, Ghazi Brotha etc. which will increase an additional 2.5 billion units.

1645626386167.png





1645626419390.png
 
. .
aa
Mohmand Dam Hydropower Project - 800 MW
Under Construction since September 2019
Gross Storage 1.2 MAF
Annual Energy Production 2,862 GWh
Completion date: 2025...


1646399932233.png




1646399951832.png

.

1646399972939.png
 
.
.
Surge Shaft area of 884MW Suki Kinari Hydropower Project...

1647007365346.png


The project is under construction since 2017.

234m deep shaft is located at the end of the 23.2km long headrace tunnel. It has two chambers namely upper and lower chambers while will neutralize the hammering effect of water due to the sudden shutdown of generating units.

Due to poor ground conditions, mechanical excavation and installation of heavy support system including lattice girders and rock anchors are being implemented.

1647007408736.png




1647007428942.png

...
 
.
......

Tarbela Dam water level drops alarmingly

The Newspaper
March 13, 2022

HARIPUR: General Manager Tarbela Dam Mohammad Azam Joya has said the water level in the reservoir has been stagnant at its dead level of 1,392 feet for last two weeks, reducing irrigation water supply to the provinces.

This he said while briefing members of the Indus River System Authority during their visit to the reservoir on Friday evening.

“The water is being discharged to provinces in line with the amount of inflow in the reservoir, which certainly causes reduction in the supply to provinces,” he said, adding the dam had been at dead level for last about a fortnight.

The IRSA members, including Amjad Saeed Mughal from Punjab, Abdul Hameed Mengal from Balochistan, Eng Zahid Abid from Khyber Pakhtunkhwa and director operations IRSA Mohammad Khuld Rana took a round of the site and intakes of the fourth and fifth extension projects and examined the work progress.

The general manager Tarbela briefed the IRSA members on the progress of work on the fifth extension project and told them that three units with a capacity of 510MW each were being installed, thus adding 1,530MW of electricity to the national grid.

It may be added that the Tarbela reservoir has a 1,550 feet of storage at its crest level, with its 17 units generating a total of 4,888MW electricity.

However, according to the statistics by Friday evening, the electricity generation has dropped to only 248MW as its only six units are operational due to reduced water inflow.

The inflow of water was 15,900 cusecs by Friday evening.

Published in Dawn, March 13th, 2022
.....................
 
. . .
****
Construction work on multipurpose Mohmand Dam Hydropower Project has been carrying out day and night. Resultantly, the project is moving ahead with a good pace and WAPDA is confident to complete the project during high flow season in 2025 as per the timelines.


1647605276267.png




1647605336088.png




1647605363928.png


*****************************
 
.
:;""
1647955471864.png


Exploratory drilling for further geotechnical investigation of Dam abutment of Balakot Hydropower Project is in Progress.

1647955538659.png



300MW power project would be completed with an estimated cost of Rs85.00 billion in a period of six years with the financial assistance of the Asian Development Bank. It is pertinent to mention here that it is the biggest ever project of hydropower generation under the KP government and important development in the energy sector...

1647955579622.png
..
.//.>
 
.

Latest posts

Pakistan Defence Latest Posts

Pakistan Affairs Latest Posts

Back
Top Bottom