What's new

China Cementing Global Dominance of Renewable Energy and Technology

Shanghai Electric Launches 11 MW Direct-Drive Turbine Petrel Platform SEW11.0-208

15 Oct, 08:00


SHANGHAI, Oct. 15. /PRNewswire/ Shanghai Electric ("Shanghai Electric" or "the Company") (601727.SS and 02727.HK) announced the release of its latest offshore wind turbine model, Petrel platform SEW11.0-208, at a forum themed around "zero carbon" that invited the leaders in China's wind power industry to shed light on opportunities in the context of China's commitment to carbon emissions reduction. Another stride forward along its offshore innovation pathway, the Shanghai Electric's flagship direct-drive turbine, of which the company has full proprietary intellectual property, features a nameplate capacity of 11 MW – the largest of its kind in Asia – marking a major breakthrough for China's homegrown innovation in offshore wind technology.
SEW11.0-208 is the first offshore wind turbine to take full advantage of the prowess of Shanghai Electric's self-developed Petrel platform that is purpose-built to withstand high temperatures, humidity and salt, as well as changeable and complex marine environments such as earthquakes and typhoons. Against the backdrop of China's peak carbon and carbon neutrality goals, SEW11.0-208 is an extension of Shanghai Electric's effort in making wind energy a dominant energy source by launching an extremely economical direct-drive wind power product capable of maintaining high power-generation efficiency and a low failure rate in both ordinary and typhoon sea areas.
Adopting full-cycle digital design, production, O&M management, SEW11.0-208 harnesses Shanghai Electric's latest LeapX control system to reduce operating load and improve the operating stability of the unit. The new offshore giant uses S102 102-meter carbon-fiber blades that deliver enormous strength and superior performance thanks to its world-leading aerodynamic design. As a fully digitized smart wind turbine, SEW11.0-208 is also supercharged by Shanghai Electric's Fengyun system, a cloud-based remote management platform, to boost operational efficiency and profitability for developers.
"As a global leader in offshore wind, Shanghai Electric is dedicated to helping China achieve peak carbon and carbon neutrality by leveraging its extensive proven technology in the field of renewable energy. The launch of our Petrel platform is a huge achievement for Shanghai Electric, which marks an important leap forward in our journey as we explore better and superior new energy products and solutions that lead the world stepping towards a greener future," said Jin Xiaolong, Vice President of Shanghai Electric.

Shanghai Electric, as one of the innovation powerhouses in China's wind power industry, will continue spearheading the development of renewable technologies to support China's carbon neutrality goal using big data, cloud computing, Internet of Things, artificial intelligence, and 5G, pioneering technological innovations to establish an advanced zero-carbon power system.
Shanghai Electric is also in pole position to reap the benefit of Shantou Offshore Wind Power Industry Alliance in its push to establish and consolidate the offshore wind power industry chain for the city, establishing a new energy industry ecosystem by synergizing industry players. Built upon Shanghai Electric's success in building the first zero-carbon factory, it will continue exploring new technologies and business models with the aim of helping China usher in the era of zero-carbon emissions.
Photo - https://mma.prnewswire.com/media/1660237/1.jpg
Photo - https://mma.prnewswire.com/media/1660236/2.jpg
Logo - https://mma.prnewswire.com/media/1629353/Logo.jpg

https://tass.com/press-releases/1350073
 
. .
来自 微博 weibo.com​
【坎德拉新能源飞轮储能交付湖州滨湖光储充示范工程】11月25日,由坎德拉(深圳)新能源科技有限公司提供的飞轮储能系统顺利交付浙江湖州滨湖光储充电站示范工程,开启了飞轮储能在浙江省配电网中首次示范应用。​

Polaris Power Network
11-26 15:28 from Weibo

[Candela New Energy Flywheel Energy Storage Demonstration Project delivered to Huzhou Binhu Photovoltaic Storage and Charging Demonstration Project]

On November 25, the flywheel energy storage system provided by Candela (Shenzhen) New Energy Technology Co., Ltd. was successfully delivered to Zhejiang Huzhou Binhu Photonic Storage and Charging Station Demonstration Project , Opened the first demonstration application of flywheel energy storage in the distribution network of Zhejiang Province.

1637932993781.png

1637933059183.png

1637933093543.png
 
. . . . .
Incidently, Yumen is the place where quite recently, America claimed to have found a large number of ICBM silo under construction via satellite.

来自 低碳赋能iPhone客户端​
12月22日零点55分,随着2号主变带电一次成功,标志着中核玉门七墩滩二期风电项目顺利并网。中国核电旗下中核汇能投资控股的中核玉门七墩滩风电项目(以下简称“七墩滩风电项目”)位于甘肃省酒泉玉门市境内,装机规模400MW,是中核汇能单体容量最大的风电项目,同时也是中核集团目前并网的单体容量最大的风电项目。​

China Nuclear Power
21-12-22 11:33

At 0:55 on December 22, with the successful charging of No. 2 main transformer, it marked the smooth grid connection of the second phase of China Nuclear Yumen Qiduntan Wind Power Project. CNNC Yumen Qiduntan Wind Power Project (hereinafter referred to as the "Qiduntan Wind Power Project"), a subsidiary of China Nuclear Power Investment and Holding, is located in Yumen City, Jiuquan, Gansu Province, with an installed capacity of 400MW. It is the largest single-capacity wind power in China Nuclear Power The project is also the largest single-capacity wind power project currently connected to the grid by China National Nuclear Corporation.

1640153891962.png
 
. . .
来自 iPhone客户端​
关注​
#能建动态##粤港澳大湾区单体连片规模最大渔光互补一体化项目# 首期并网】12月28日,中国能建广东院参与投资建设的广东台山500兆瓦渔光互补项目首期工程成功并网。台山海宴渔光互补一体化项目占地面积约6500亩,总投资约22亿元,计划安装44.6万多块光伏发电板,首期工程200兆瓦。项目是迄今粤港澳大湾区单体连片规模最大的渔光互补一体化项目,光伏板是目前国内最先进的高效单晶光伏发电组件。全面投产后,年发电量可达5.43亿千瓦时,满足11万户家庭全年用电量,每年可节省标煤约19.3万吨,减少二氧化碳约53.4万吨,相当于大湾区约7.5万亩森林的碳汇量,对实现碳达峰碳中和目标具有积极意义​

Energy China
21-12-28 13:59

[Guangdong-Hong Kong-Macao Greater Bay Area, the largest single contiguous fishery and photovoltaic complementary integrated project# first phase of grid connection]

On December 28, the first phase of the Guangdong Taishan 500MW fishing and photovoltaic complementary project, which was invested and constructed by the Guangdong Research Institute of Energy China, was successfully connected to the grid. The Taishan Haiyan Fishing and Photovoltaic Complementary Integration Project covers an area of about 6,500 acres and has a total investment of about 2.2 billion yuan. More than 446,000 photovoltaic power generation panels are planned to be installed. The first phase of the project is 200 MW. The project is the largest single integrated fishery and photovoltaic complementary integrated project in the Guangdong-Hong Kong-Macao Greater Bay Area so far. The photovoltaic panel is currently the most advanced high-efficiency monocrystalline photovoltaic power generation module in China. After full production, the annual power generation capacity can reach 543 million kilowatt-hours, which can meet the annual electricity consumption of 110,000 households, save about 193,000 tons of standard coal and reduce about 534,000 tons of carbon dioxide each year. It is equivalent to the carbon sink of approximately 75,000 mu of forests in the Greater Bay Area, which is of positive significance for achieving the carbon peak and carbon neutral goal.

1640697010332.png

1640696766010.png
 
.
来自 微博 weibo.com​
【国内单机最大、阳江巨型“充电宝”正式移交生产】12月28日上午,在位于广东省阳春市与电白县交界处的八甲山区、阳江抽水蓄能电站厂房内,由哈电集团哈尔滨电机厂有限责任公司研制的国内单机容量最大的抽水蓄能机组-阳蓄电站首台机组,正式移交生产,投入南方电网调度使用,此举对保障粤港澳大湾区电力供应、促进海上风电等清洁能源消纳,实现国家“碳达峰、碳中和”目标具有重要意义。​
抽水蓄能机组在电网中承担调峰、填谷、紧急事故备用任务,兼有调频、调相和黑启动、储能作用,是电网的“稳定器”、“调节器”、“充电宝”。哈电电机研制的这台巨型“充电宝”阳江1号机组运行稳定性极高,工作人员在机组盖板上放置两枚1元硬币,硬币居然纹丝不动。不止于此,这台超高水头、大容量、高转速、综合技术难度极高的巨型“充电宝”,从每一个零部件的诞生到安装调试、试运行等各个环节,创造的“第一”不胜枚举。在机组整机调试中,所有试验全部一次成功、100%通过,试运行稳定,振动、温度数据良好,上导、下导、水导摆度均在0.10毫米以内,为机组正式投入商业运行奠定了良好基础。​
哈电电机党委副书记、总经理刘玉强表示,哈电长期的技术积累和独有的抽水蓄能研发制造体系,以科研攻关和技术创新为主要手段,解决了机组水力稳定性和效率难以兼顾的世界性难题,取得了一系列原创性成果,实现了100%自主知识产权,成功与业主共同站在了世界抽水蓄能技术领域的前沿。(科技日报记者 李丽云 通讯员 张弘,图片由张弘拍摄)​

Science and Technology Daily
21-12-28 16:06

[The largest single-unit in China, giant Yangjiang "Power Bank" is officially handed over to production]

On the morning of December 28, in the Bajia Mountain area at the junction of Yangchun City and Dianbai County, Guangdong Province, in the Yangjiang Pumped Storage Power Plant, the largest single-unit pumped storage capacity in China developed by Harbin Electric Group Co., Ltd. The first unit of the Yangxu Power Plant was officially handed over to production and put into the Southern Power Grid for dispatching. This move will help ensure the power supply of the Guangdong-Hong Kong-Macao Greater Bay Area, promote the consumption of clean energy such as offshore wind power, and realize the national “carbon peak and carbon neutral”. The goal of harmony is of great significance.

The pumped-storage unit is responsible for peak regulation, valley filling, emergency backup tasks in the power grid. It also has the functions of frequency regulation, phase regulation, black start, and energy storage. It is the "stabilizer", "regulator", and "charger" of the power grid. . The giant "power bank" Yangjiang No. 1 unit developed by Harbin Electric Motor has extremely high operating stability. The staff placed two 1 yuan coins on the cover of the unit, but the coins did not move. More than that, this giant "power bank" with ultra-high water head, large capacity, high speed, and extremely difficult comprehensive technology, from the birth of each component to installation, commissioning, and trial operation, has created the "first "The list goes on. During the commissioning of the unit, all tests were successful and passed 100% at one time. The trial operation was stable, the vibration and temperature data were good, and the swings of the upper guide, lower guide, and water guide were all within 0.10 mm, which laid the foundation for the formal commercial operation of the unit. A good foundation.

Liu Yuqiang, deputy secretary of the party committee and general manager of Harbin Electric Motor, said that Harbin Electric’s long-term technological accumulation and unique pumped storage R&D and manufacturing system use scientific research and technological innovation as the main means to solve the problem of hydraulic stability and efficiency of the unit. Global problems, a series of original results have been achieved, 100% independent intellectual property rights have been achieved, and the owner has successfully stood at the forefront of the world's pumped storage technology. (Science and Technology Daily reporter Li Liyun, correspondent Zhang Hong, picture taken by Zhang Hong)

1640698074094.png

1640698134922.png
 
. . . .

Pakistan Affairs Latest Posts

Country Latest Posts

Back
Top Bottom